Presentation is loading. Please wait.

Presentation is loading. Please wait.

R&D SDM 1 Software Project Management Project Scheduling and Tracking

Similar presentations


Presentation on theme: "R&D SDM 1 Software Project Management Project Scheduling and Tracking"— Presentation transcript:

1 R&D SDM 1 Software Project Management Project Scheduling and Tracking
2010 Theo Schouten

2 Content What is project scheduling & tracking ?
Which steps can be recognized in project scheduling? Work Breakdown Structure Techniques: CPM, Gantt Charts Examples Final remarks Book chapter 24 (27 for 7e)

3 What is project scheduling&tracking?
The partitioning of the total work in tasks, which deliver defined products. The planning of those tasks in calendar time. The allocation of resources to these tasks. Tracking: Following of the progress of the tasks. Adapting the schedule according the latest developments. How software projects fall behind schedule?

4 Why software is delivered late?
Unrealistic deadline established outside the team Changing customer requirements not reflected in schedule Underestimating the resources required to complete the project Risks that were not considered when project began Technical difficulties that have not been predicted in advance Human difficulties that have not been predicted in advance Miscommunication among project staff resulting in delays Failure by project management to recognize project falling behind schedule and failure to take corrective action people, process, technology

5 Perspectives the end-date for the software release is set externally
the software organization is constrained to distribute effort in the prescribed time frame. the rough chronological bounds have been discussed by the developers and customers the end-date is best set by the developer after carefully considering how to best use the resources needed to meet the customer's needs. negotiation process

6 Basic principles for scheduling
Compartimentalization decomposition of both the product and the process the work is divided in tasks (work-breakdown structure) each delivers (possible in combination with other tasks) a part of the product. Interdependency minimize the dependency between tasks which products of other tasks are needed to start a task sequential and parallel tasks Time allocation for each task How much work is needed in e.g. person-days Determine whether this will be part-time of full-time Assign a start and completion date (not assigned yet to a person).

7 …continued Matching total time with available resources
Are the needed resources (persons, tools, hardware) available? (not assigned yet to a person). Defining responsibilities Every task should be the responsibility of a person. Defining outcomes of tasks Each task should have a defined outcome. (SMART) More than 1 of these work products may be grouped into a deliverable. Defining milestones the milestones of the project: a moment in time on which a (group of) deliverables should be finished.

8 Effort distribution Use the data on the organization’s historical experience with similar projects When such data is not available, publicly available factors can be used for guidance. The rule (a rule of thumb): 40% front-end analysis and design 20% coding 40% back-end testing Generally accepted guidelines are: 02-03 % planning 10-25 % requirements analysis 20-25 % design 15-20 % coding 30-40 % testing and debugging

9 Critics of % rule Some Software Engineering Managers believe that more than 40% of overall effort should be expended during Analysis and Design. Some proponents of Agile Development Method argue that Less time should be expended on “Front-end’’ of Project Phase and that a team should move quickly to Construction Phase (Build phase). Theo: when a program is working, the documentation still need a lot of work.

10 Parts and steps Project task: A task is executable and delivers a well defined work product (SMART); Work-breakdown structure: Division of the total trajectory into tasks; Deliverable Intermediate or final product delivered by a task or a number of tasks; Milestone: Date on which a deliverable should be ready; Network of dependencies of project tasks: sequential parallel

11 …continued Determine which tasks are critical in the network: they determine the run time of a project; Determine what the size of the tasks are; Determine which resources are needed to execute each task; Building up of a project schedule:: dividing the tasks over time and allocating resources to tasks; Tracking of the progress of the project on basis of its schedule.

12 Milestones, deliverables
Steering project Steer on goals Steering Committee Project Sponsor Project Steering Committee Steer on goals, milestones and deliverables Attention in this course Steer on Milestones, deliverables and tasks Project Manager(s) Technical Project Leader Functional/Process Groups (User Focal Points) Steer on Tasks and resources Analysts Designers programmers ….. User Group 1 User Group 2 User Group n

13 Work-Breakdown Structure
A detailed breakdown of the product into manageable work elements. A method for breaking down work within a project into logical steps: Product WBS: Work is broken down by system, subsystem, modules & the structure of the software product. Activity WBS: Work is broken down by activities of the project members such as management, requirements analysis, design & programming.

14 Product WBS

15 Activity WBS

16 Work-breakdown structure
Example Main phases of an information system based on software packets on the market. Phase 1 Develop Blueprint Phase 2 Design Information system Phase 3 Realize Information system Phase 4 Implement Information system

17 Steps in phase 1 Development blueprint Deliverables phase 1 Blue-
1.1. Pre- paration & Project- definition 1.2. Develop process- model current situation 1.3. Analysis current situation 1.4. Develop blueprint 1.5 Fit-analysis shortlist Packets 1.6 make principle choice 1.7. Make plan next phases Principle -choice Fit- analysis Plan phase 2

18 Steps in phase 2 Design Information System Iterative Input
Deliverables Phase 2 Blue- print Final choice Iterative Principle -choice Process model future sit. Preparation Execution Fit- analysis 2.1. Develop simulation case 2.2. Make simulation environment 2.3. Prototype step- through 2.4. End- report 2.5. Design interfaces + conversion Final- report Plan phase 2 Solutions for “gaps”

19 Relation deliverables-milestones
Project Goals Constraints Deliverable 1 Deliverable n Milestone 1 ...... Milestone n Task 1 Task n Timing, resourcing and dependencies

20 Relation between people and effort
Putnam-Nordon-Rayleigh (PNR) curve putting more people on a project does not decrease time linearly people need time for communication 4 zones in the curve for a certain defined project: 1) it can not be completed within a certain time 2) overstaffed: completed fast, but inefficient 3) linear range: efficient staffing, man-power trade-off with time is good possible 4) understaffed: becomes also inefficient

21 PNR Formula’s The number of delivered lines of code L is related to effort and development time by the equation: L = P × E 1/3 t 4/3 E is development effort in person-months P is a productivity parameter that reflects various factors (typically 2,000-12,000) t is the project duration in calendar months Rearranged to solve for development effort: E = L3/(P 3t 4)

22 Setting up of a schedule
Define deliverables and milestones; Identify tasks which belong to deliverables; Identify relations between deliverables and activities; Determine the type and size of the resources needed for a task; Allocate people to activities; Create activity networks and ‘bar charts’ (Gantt Charts).

23 Example Task Run time in workdays Dependencies (milestone) T1 8 T2 15
T1 (M1) T4 10 T5 19 T2, T4 (M2) T6 5 T1, T2 (M3) T7 20 T8 25 T4 (M5) T9 T3, T6 (M4) T10 T5, T7 (M7) T11 7 T9 (M6) T12 T11 (M8)

24 Activity network Insight in parallel and sequential tasks
+ dependencies 15 days 14/7/99 T3 15 days 8 days M1 4/8/99 T9 T1 M4 4/7/99 25/7/99 5 days 25/8/99 M3 M6 Start T6 15 days 7 days T2 20 days T11 T7 25/7/99 10 days 5/9/99 M2 11/8/99 T4 T5 M8 M7 10 days 18/7/99 15 days 10 days M5 T10 25 days T12 T8 End 19/9/99

25 Critical path Start End T3 M1 T9 M4 M3 M6 T2 T11 T7 M2 T4 T5 M8 M7 M5
15 days 14/7/99 T3 15 days 8 days M1 4/8/99 T9 T1 M4 4/7/99 25/7/99 5 days 25/8/99 M3 M6 Start T6 15 days 7 days T2 20 days T11 T7 25/7/99 10 days 5/9/99 M2 11/8/99 T4 T5 M8 M7 10 days 18/7/99 15 days 10 days M5 T10 25 days T12 T8 = Critical Path End 19/9/99

26 Bar chart (Gantt chart)
4/7 18/7 11/7 1/8 25/7 8/8 22/8 15/8 29/8 5/9 12/9 19/9 26/9 Start T4 T1 T2 M1 T7 T3 M5 T8 M3 M2 T6 T5 M4 T9 M7 T10 M6 T11 M8 T12 End

27 Extra time 4/7 18/7 11/7 1/8 25/7 8/8 22/8 15/8 29/8 5/9 12/9 19/9
26/9 T4 T1 T2 T7 T3 T12 End T9 T8 T5 T6 T10 T11 M1 M5 M8 M7 M4 M2 M3 M6 Start

28 Allocation of persons to tasks and time
Software Engineer T1 Jan T2 Carolien T3 T4 Frank T5 Isabel T6 T7 Jim T8 T9 T10 T11 T12 4/7 18/7 11/7 1/8 25/7 8/8 22/8 15/8 29/8 5/9 12/9 19/9 26/9 Frank Jan Carolien Jim Isabel T5 T2 T12 T11 T8 T4 T9 T3 T1 T7 T10 T6 Resources can influence the critial path, e.g. Frank with T8-T11

29 Gantt chart


Download ppt "R&D SDM 1 Software Project Management Project Scheduling and Tracking"

Similar presentations


Ads by Google