Notes This set of slides (Handout #7) is missing the material on Reductions and Greed that was presented in class. Those slides are still under construction,

Similar presentations


Presentation on theme: "Notes This set of slides (Handout #7) is missing the material on Reductions and Greed that was presented in class. Those slides are still under construction,"— Presentation transcript:

1 Notes This set of slides (Handout #7) is missing the material on Reductions and Greed that was presented in class. Those slides are still under construction, and will be posted as Handout #6. The quiz on Thursday of 8 th week will cover Greed and Dynamic Programming, and through HW #4

2 Topological Sorting Prelude to shortest paths Generic scheduling problem Input: –Set of tasks {T 1, T 2, T 3, …, T n } Example: getting dressed in the morning: put on shoes, socks, shirt, pants, belt, … –Set of dependencies {T 1  T 2, T 3  T 4, T 5  T 1, …} Example: must put on socks before shoes, pants before belt, … Want: –ordering of tasks which is consistent with dependencies Problem representation: Directed Acyclic Graph –Vertices = tasks; Directed Edges = dependencies –Acyclic: if  cycle of dependencies, no solution possible

3 Topological Sorting TOP_SORT PROBLEM: Given a DAG G=(V,E) with |V|=n, assign labels 1,...,n to v i  V s.t. if v has label k, all vertices reachable from v have labels > k “Induction idea”: –Know how to label DAG’s with < n vertices Claim: A DAG G always has some vertex with indegree = 0 –Take an arbitrary vertex v. If v doesn’t have indegree = 0, traverse any incoming edge to reach a predecessor of v. If this vertex doesn’t have indegree = 0, traverse any incoming edge to reach a predecessor, etc. –Eventually, this process will either identify a vertex with indegree = 0, or else reach a vertex that has been reached previously (a contradiction, given that G is acyclic). “Inductive approach”: Find v with indegree(v) = 0, give it lowest available label, then delete v (and incident edges), update degrees of remaining vertices, and repeat

4 Dynamic Programming Key Phrases As we discuss shortest paths, and then the dynamic programming approach, keep in mind the following “key phrases” –“Principle of Optimality”: Any subsolution of an optimal solution is itself an optimal solution –“Overlapping Subproblems”: Can exploit a polynomially bounded number of possible subproblems –“Bottom-Up D/Q” / “Table (cache) of Subproblem Solutions”: avoid recomputation by tabulating subproblem solutions –“Relaxation / Successive Approximation”: Often, the DP approach makes multiple passes, each time solving a less restricted version of the original problem instance Eventually, solve completely unrestricted = original problem instance

5 Single-Source Shortest Paths Given G=(V,E) a directed graph, L : E   + a length function, and a distinguished source s  V. Find the shortest path in G from s to each v i  V, v i  s. Let L*(i,j) = length of SP from v i to v j Lemma: Suppose S   V contains s = v i and L*(1,w) is known  w  S. For v i  S: –Let D(v i ) = min w  S L*(1,w) + L(w,i) (*) L*(1,w) = path length, with path restricted to vertices of S L(w,i) = edge length –Let v v minimize D(v i ) over all nodes v i  S (**) Then L*(1,v) = D(v v ). Notation: D(v) = length of the 1-to-v SP that uses only vertices of S (except for v). (D(v) is not necessarily the same as L*(1,v), because the path is restricted!)

6 Single-Source Shortest Paths Proof of Lemma: To prove equality, prove  and  L*(1,v)  D(v) is obvious because D(v) is the minimum length of a restricted path, while L*(1,v) is unrestricted Let L*(1,v) be the shortest path s=v 1, v 2, …, v r = v from the source v 1 to v. Let v j be the first vertex in this SP that is not in S Then: L*(1,v) = L*(1, v j-1 ) + L(v j-1, v j ) + L*(v j,v) // else, not a shortest path  D(v j ) + L*(v j,v) // D(v j ) minimizes over all w in S, including v j-1  D(v) + L*(v j,v) // because both v j and v v  S, but v v chosen first  D(v) // since L*(v j,v)  0. Lemma  Dijkstra’s Algorithm

7 A Fact About Shortest Paths Triangle Inequality:  (u,v)   (u,x) +  (x,v) (shortest path distances induce a metric) u x v

8 Shortest Path Formulations Given a graph G=(V,E) and w: E   –(1 to 2) “s-t”: Find a shortest path from s to t –(1 to all) “single-source”: Find a shortest path from a source s to every other vertex v  V –(All to all) “all-pairs”: Find a shortest path from every vertex to every other vertex Weight of path =  w(v[i],v[i+1]) Sometimes: no negative edges –Examples of “negative edges”: travel inducements, exothermic reactions in chemistry, unprofitable transactions in arbitrage, … Always: no negative cycles –Makes the shortest-path problem well-defined <0

9 Shortest Paths First case: All edges have positive length –Length of (v i,v j ) edge = d ij Condition 1: d ij > 0 Condition 2: d i + d jk  d ik for some i,j,k –else shortest-path problem would be trivial Observation 1: Length of a path > length of any of its subpaths Observation 2: Any subpath of a shortest path is itself a shortest path Principle of Optimality Observation 3: Any shortest path contains  n-1 edges pigeonhole principle; assumes no negative cycles; n nodes total

10 Shortest Paths Scenario: All shortest paths from v 0 = source to other nodes are ordered by increasing length: –|P 1 |  |P 2 |  …  |P n-1 | –Index nodes accordingly Algorithm: Find P 1, then find P 2, etc. Q: How many edges are there in P 1 ? –Exactly 1 edge, else can find a subpath that is shorter Q: How many edges are there in P k ? –At most k edges, else can find k (shorter) subpaths, which would contradict the definition of P k Observation 4: P k contains  k edges To find P 1 : only look at one-edge paths (min = P 1 ) To find P 2 : only look at one- and two-edge paths –But, need only consider two-edge paths of form d 01 + d 1i –Else would have  1 paths shorter than P 2, a contradiction

11 Another Presentation of Dijkstra’s Algorithm Terminology –Permanent label: true SP distance from v 0 to v i –Temporary label: restricted SP distance from v 0 to v i (going through only existing permanently-labeled nodes) Permanently labeled nodes = set S in previous development Dijkstra’s Algorithm 0. All vertices v i, i = 1,…, n-1, receive temporary labels l i with value d 0i LOOP: 1. Among all temporary labels, pick l k = min I l i and change l k to l k * (i.e., make l k ‘s label permanent) // stop if no temporary labels left 2. Replace all temporary labels of v k ‘s neighbors, using l i  min (l i, l k * + d ki )

12 Prim’s Algorithm vs. Dijkstra’s Algorithm Prim: Iteratively add edge e ij to T, such that v i  T, v j  T, and d ij is minimum Dijkstra: Iteratively add edge e ij to T, such that v i  T, v j  T, and l i + d ij is minimum Both are building trees, in very similar ways! –Prim: Minimum Spanning Tree –Dijkstra: Shortest Path Tree What kind of tree does the following algorithm build? Prim-Dijkstra: Iteratively add edge e ij to T, such that v i  T, v j  T, and c  l i + d ij is minimum // 0  c  1

13 Bellman-Ford Algorithm Idea: Successive Approximation / Relaxation –Find SP using  1 edges –Find SP using  2 edges –… –Find SP using  n-1 edges  have true shortest paths Let l j (k) denote shortest v 0 – v j pathlength using  k edges Then, l i (1) = d 0j  j = 1, …, n-1 // d ij =  if no i-j edge In general, l j (k+1) = min { l j (k), min i (l i (k) + d ij ) } –l j (k) : don’t need k+1 arcs –min i (l i (k) + d ij ) : view as length-k SP plus a single edge

14 Bellman-Ford vs. Dijkstra B S C D A 2 2 13 8 4 Pass 1 2 3 4 Label A 8 min(8, 3+4,  +1, 2+  ) = 7 min(7, 3+4, 4+1, 2+  ) = 5 min(5, 3+4, 4+1, 2+  )= 5 B 3 min(3, 8+4,  + , 2+  ) = 3 min(3, 7+4, 4+ , 2+  ) = 3 min(3, 5+4, 4+ , 2+  ) = 3 C  min( , 8+1, 3+ , 2+2) = 4 min(4, 7+1, 3+ , 2+2) = 4 min(4, 5+1, 3+ , 2+2) = 4 D 2 min(2, 8+ , 3+ ,  +2) = 2 min(2, 7+ , 3+ , 4+2) = 2 min(2, 5+ , 3+ , 4+2) = 2

15 Bellman-Ford vs. Dijkstra B S C D A 2 2 13 8 4 Pass 1 2 3 4 Label A 8 min([8], 2+  ) = 8 min([8], 3+4) = 7 min([7], 4+1) = 5* B 3 min([3], 2+  ) = 3* C  min([  ], 2+2) = 4 min(4, 3+  ) = 4* D 2*

16 Special Case: DAGs (24.2) Longest-Path Problem: well-defined only when there are no cycles DAG: topologically sort the vertices  labels v 1, …, v n s.t. all edges directed from v i to v j, i < j Let l i denote longest v 0 – v j pathlength –l 0 = 0 –l 1 = d 01 // d ij = -  if no i-j edge –l 2 = max(d 01 + d 12, d 02 ) –In general, l k = max j<k (l j + d jk ) Shortest pathlength in DAG: replace max by min, use d ij = +  if no i-j edge

17 DAG Shortest Paths Complexity (24.2) Bellman-Ford = O(VE) Topological sort O(V+E) (DFS) Will never relax edges out of vertex v until have done all edges in to v –Runtime O(V+E) Application: PERT ( program evaluation and review technique ) – critical path is the longest path through the DAG

18 All-Pairs Shortest Paths (25.1-25.2) Directed graph G = (V,E), weight E   Goal: Create n  n matrix of SP distances  (u,v) Running Bellman-Ford once from each vertex O( ) = O( ) on dense graphs Adjacency-matrix representation of graph: – n  n matrix W = (w ij ) of edge weights –assume w ii = 0  i, SP to self has no edges, as long as there are no negative cycles

19 Simple APSP Dynamic Programming (25.1) d ij (m) = weight of s-p from i to j with  m edges d ij (0) = 0 if i = j and d ij (0) =  if i  j d ij (m) = min k {d ik (m-1) + w kj } Runtime = O( n 4 ) n-1 passes, each computing n 2 d’s in O(n) time j i  m-1

20 Matrix Multiplication (25.1) Similar: C = A  B, two n  n matrices c ij =  k a ik  b kj O(n 3 ) operations replacing: ‘‘ + ’’  ‘‘ min ’’ ‘‘  ’’  ‘‘ + ’’ –gives c ij = min k {a ik + b kj } –D (m) = D (m-1) ‘‘  ’’ W –identity matrix is D (0) –Cannot use Strassen’s because no subtraction Time is still O(n  n 3 ) = O(n 4 ) Repeated squaring: W 2n = W n  W n (addition chains) Compute W, W 2, W 4,..., W 2 k, k = log n  O(n 3 log n)

21 Floyd-Warshall Algorithm (26.2/25.2) Also DP, but even faster (by another log n actor  O(n 3 )) c ij (m) = weight of SP from i to j with intermediate vertices in the set {1, 2,..., m}   (i, j)= c ij (n) DP: compute c ij (n) in terms of smaller c ij (n-1) – c ij (0) = w ij –c ij (m) = min {c ij (m), c im (m-1) + c mj (m-1) } intermediate nodes in {1, 2,..., m} j i c im (m-1) c mj (m-1) m c ij (m-1)

22 Floyd-Warshall Algorithm (26.2/25.2) Difference from previous: we do not check all possible intermediate vertices. for m=1..n do for i=1..n do for j = 1..n do c ij (m) = min {c ij (m-1), c im (m-1) + c mj (m-1) } Runtime O(n 3 ) Transitive Closure G* of graph G: –(i,j)  G* iff  path from i to j in G –Adjacency matrix, elements on {0,1} –Floyd-Warshall with ‘‘ min ’’  ‘‘OR’’, ‘‘+’’  ‘‘ AND ’’ –Runtime O(n 3 ) –Useful in many problems

23 BEGIN DIGRESSION (alternative presentation, can be skipped)

24 CLRS Notation: Bellman-Ford (24.1) SSSP in General Graphs Essentially a BFS based algorithm Shortest paths (tree) easy to reconstruct for each v  V do d[v]   ; d[s]  0 // initialization for i =1,...,|V|-1 do for each edge (u,v)  E do d[v]  min{d[v], d[u]+w(u,v)} // relaxation for each v  V do if d[v]> d[u] + w(u,v) then no solution // negative cycle checking for each v  V, d[v]=  (s,v) // have true shortest paths

25 Bellman-Ford Analysis (CLRS 24.1) Runtime = O(VE) Correctness –Lemma: d[v]   (s,v) Initially true Let d[v] = d[u] +w(u,v) by triangle inequality, for first violation d[v] <  (s,v)   (s,u)+w(u,v)  d(u)+w(u,v) –After |V|-1 passes all d values are  ’s if there are no negative cycles s  v[1]  v[2] ...  v (some shortest path) After i-th iteration d[s,v[i]] is correct and final

26 Dijkstra Yet Again (CLRS 24.3) Faster than Bellman-Ford because can exploit having only non-negative weights Like BFS, but uses priority queue for each v  V do d[v]   ; d[s]  0 S   ; Q  V While Q   do u  Extract-Min(Q) S  S + u for v adjacent to u do d[v]  min{d[v], d[u]+w(u,v)} (relaxation = Decrease-Key)

27 Dijkstra Runtime (24.3) Extract-Min executed |V| times Decrease-Key executed |E| times Time = |V|  T(Extract-Min) // find+delete = O(log V)) + |E|  T(Decrease-Key) // delete+add =O(log V)) Binary Heap = E  log V (30 years ago) Fibonacci Heap = E + V  log V (10 years ago) Optimal time algorithm found 1 year ago; runs in time O(E) (Mikel Thorup)

28 Same Lemma as for Bellman-Ford: d[v]   (s,v) Thm: Whenever u is added to S, d[u] =  (s,u) Proof: –Assume that u is the first vertex s.t. d[u] >  (s,u) –Let y be first vertex  V-S that is on actual shortest s-u path  d[y] =  (s,y) –For y’s predecessor x, d[x] =  (s,x) –At the moment that we put x in S, d[y] gets value  (s,y) –d[u] >  (s,u) =  (s,y) +  (y,u) = d[y] +  (y,u)  d[y] Dijkstra Correctness (24.3) s x y u S Q

29 END DIGRESSION (alternative presentation, can be skipped)

30 Dynamic Programming (CLRS 15) Third Major Paradigm so far –DQ, Greed are previous paradigms Dynamic Programming = metatechnique (not a particular algorithm) “Programming” refers to use of a “tableau” in the method (cf. “mathematical programming”), not to writing of code

31 Longest Common Subsequence (CLRS 15.4) Problem: Given x[1..m] and y[1..n], find LCS x: A B C B D A B  B C B A y: B D C A B A Brute-force algorithm: –for every subsequence of x, check if it is in y –O(n2 m ) time 2 m subsequences of x (each element is either in or out of the subsequence) O(n) for scanning y with x-subsequence (m  n)

32 Recurrent Formula for LCS (15.4) Let c[i,j] = length of LCS of X[i]=x[1..i],Y[j]= y[1..j] Then c[m,n] = length of LCS of x and y Theorem: if x[i] = y[j] otherwise Proof: x[i] = y[j]  LCS([X[i],Y[j]) = LCS(X[i-1],Y[j-1]) + x[i]

33 DP Properties(15.3) Any part of the optimal answer is also optimal –A subsequence of LCS(X,Y) is the LCS for some subsequences of X and Y. Subproblems overlap –LCS(X[m],Y[n-1]) and LCS(X[m-1],Y[n]) have common subproblem LCS(X[m-1],Y[n-1]) –There are polynomially few subproblems in total = mn for LCS –Unlike divide and conquer

34 DP (CLRS 15.3) After computing solution of a subproblem, store in table Time = O(mn) When computing c[i,j] we need O(1) time if we have: –x[i], y[j] –c[i,j-1] –c[i-1,j] –c[i-1,j-1]

35 DP Table for LCS y B D C A B A xABCBDABxABCBDAB

36 DP Table for LCS y B D C A B A xABCBDABxABCBDAB 0 0 0 0 1 1 0 1

37 DP Table for LCS y B D C A B A xABCBDABxABCBDAB 0 0 0 0 1 1 0 1 2 0 1

38 DP Table for LCS y B D C A B A xABCBDABxABCBDAB 0 0 0 0 0 0 0 0 0 0 0 1 1 1 0 1 1 1 1 2 2 0 1 1 2 2 2 2 0 1 1 2 2 3 3 0 1 2 2 2 3 3 0 1 2 2 3 3 4 0 1 2 2 3 4 4

39 Optimal Polygon Triangulation Polygon has sides and vertices Polygon is simple = not self-intersecting. Polygon P is convex if any line segment with ends in P lies entirely in P Triangulation of P is partition of P with chords into triangles. Problem: Given a convex polygon and weight function defined on triangles (e.g. the perimeter). Find triangulation of minimum weight (of minimum total length). # of triangles: Always have n-2 triangles with n-3 chords

40 Optimal Polygon Triangulation Optimal sub-triangulation of optimal triangulation Recurrent formula: t[i,j] = the weight of the optimal triangulation of the polygon ; If i=j, then t[i,j]=0; else Runtime O(n 3 ) and space is O(n 2 ) v[i-1] v[i] v[j] v[i-1] v[i] v[j] v[k]


Download ppt "Notes This set of slides (Handout #7) is missing the material on Reductions and Greed that was presented in class. Those slides are still under construction,"