1 ECOSTILER, coordinators MEETING November 14, 2011

2 Demo sites Amsterdam New West London Lambeth Måbjerg

3 Amsterdam 72 months highlights All refurbishment demo’s complete Biogas plant in waste to energy plant complete Exhaust gases in waste incinerator being tested District heating backbone of 12 km complete, current connection rate about 4000 dwellings/year Renewables support program complete Ongoing: monitoring of dwellings

4 London Lambeth 72 month highlights All planned refurbishment buildings complete (maybe one will be added) CHP installations complete, but being optimized R&D program complete Some loose ends being finalized

5 Måbjerg 72 month highlights Biogas plant construction started August 2010 All related research almost finalized To be completed December 2011, Operation April 2012 Auditing of Farms completed Energy monitoring of farms ongoing Energy efficiency measures being executed.

6 Yet to do Amsterdam Finalizing of monitoring (buildings and biogas utilization) London Tentative: implement Loughborough estate refurbishment Måbjerg Make biogas plant operational Execute energy efficiency measures in stables Monitoring

7 Progress summary