Presentation is loading. Please wait.

Presentation is loading. Please wait.

Multidisciplinary Senior Design Rochester Institute of Technology Dresser-Rand Painted Post P10459 Detailed Design Review 2/26/10 Team: Phil Eaton (ME)

Similar presentations


Presentation on theme: "Multidisciplinary Senior Design Rochester Institute of Technology Dresser-Rand Painted Post P10459 Detailed Design Review 2/26/10 Team: Phil Eaton (ME)"— Presentation transcript:

1 Multidisciplinary Senior Design Rochester Institute of Technology Dresser-Rand Painted Post P Detailed Design Review 2/26/10 Team: Phil Eaton (ME) Alex Frenkel (ME) Rachel Koch (ME) Pete Lowry (ISE) Yi Xie (ISE) Faculty Guide: John Kaemmerlen

2 Overview Expectations Background Systems Level Breakdown
Project Status Update Target Specifications Update Machine Configuration Status Update Layout Concepts Process Improvement Concepts Material Handling Detailed Design Material Storage Detailed Design Risk Assessment Update MSD II Project Plan

3 Expectations Discussion Decisions to me made today.
Feedback on current status Suggestions for improvement Different thoughts/points to consider Clear view of next steps Action items for MSD II Decisions to me made today. Location: shop 6 or 17 Heiligenstadt Money for pallet prototype Gilbert

4 Background Problem Objective Stakeholders
Liner cell is located in 3 different parts of the plant One part is in a location that will be closed off Objective Provide a detailed plan for movement/consolidation Maximize productivity, safety, quality, and profitability in new layout Stakeholders RIT: John Kaemmerlen, Senior Design Program D-R: Dennis Rice, Mike Decerbo, John Woedy,

5 Machine Configuration
Systems Level Design Mechanical Engineering Alex Rachel Phil Machine Material Material Handling Material Handling Machine Configuration Machine Configuration Material Storage Material Storage New Layout with best safety, productivity and quality Cell Layout Problem Solving Visual Controls Method Man Metrics Industrial Engineering Pete Yi

6 Project Status Overview
Time Frame MSD I: Nov. 30, 2009 – Feb. 19, 2010 (Completed) MSD II: Mar. 8, 2010 – May 14, 2010 Customer Needs Concept Generation Concept Improvement Concept Selection Detailed Design Machine Configuration Floor Layout Process Improvement Material Handling Material Storage

7 Target Specifications Updated
Need Metric Current* Marginal Target Machine Configuration (Alex) Overhead Cost $87,991 -10% -20% Process Time 35.47 hrs -50% Man Power 4 3 Defect Cost $40,623 Cell Layout (Pete) Travel Distance Next Slide -40% Mfg Footprint 6584 sq ft -30% Process Improvement (Yi) # Injuries Material Handling (Rachel) $6,000 -100% Material Storage (Phil) Space Utilization 480 sq ft -60% 1,280 ft *Based on 2009 Metrics (Jan – Sep)

8 Travel Distance Production Service Large Liner 1890 ft 2464 ft
Small Liner 1952 ft 1745 ft

9 Machine Configuration
Currently parts are machined on vintage 50’s and 60’s machines. Slow machining time Frequent maintenance and repair Parts are difficult to find and expensive Manual machines can lead to more frequent defects in parts or “out of round” conditions. Machining operation depends on tribal knowledge of operators We are researching other alternatives such as the purchase of a used or new CNC horizontal or vertical lathe. We will attempt to justify the cost with the savings in process time as well as reduced operating cost of the machines. R· I· T Mechanical Engineering Department

10 Machine Configuration
Currently the average process time is about hours per liner (shop order details) We will attempt to reduce that number by about 50% to hours. In the last 2 years liner cell produced 555 liners. At a burden rate of $105, One hour of reduced process time comes out to about $29,138 a year R· I· T Mechanical Engineering Department

11 Machine Configuration
This results in a total savings per year of about $513,994 A brand new Toshiba TUE 150 costs around $500,000 with tooling. Looking at a payback period of about one year R· I· T Mechanical Engineering Department

12 Machine Configuration
Justification Video taped time studies on in house machines Data from Morris Great Lakes CICS hours charged on liners Production data from 2008 and 2009 Morris Great lakes has already been brought in on this project to provide assistance on the best machine choice and they are putting together a proposal for us. R· I· T Mechanical Engineering Department

13 Cell Layout Design & Selection
Options include everything from: Utilizing Shop 6 Utilizing Shop 17 Buying a new VTL Scrapping old machines Bringing in machines from other departments.

14 As Is Liner Cell in Shop 21, Shop 6, & Shop 17
High travel distance & future wall necessitate the re-layout.

15 Option #1 Moving Shop 21 into Shop 17
Cost of removal of the Heyligenstaedt & the Betts Room available for possible new machine(s)

16 Option #2 Moving Shop 21 & the Gilbert porting machine into Shop 17
Cost of removal of the Heyligenstaedt & the Betts Porting brought to Shop 17

17 Option #3 Moving Shop 21 & a new VTL CNC machine into Shop 17
Cost of removal of the Heyligenstaedt & the Betts Majority of work performed on VTL with Shop 21 machines for backup Need to propose a viable business case for the new machine

18 Option #4 Moving Shop 21 & Shop 6 into Shop 17
Cost of removal of the Heyligenstaedt & the Betts Cost of foundation preparation & move of Norton Grinder & American Lathe Liner Cell moved out of Shop 21 & 6

19 Option #5 Moving Shop 21, the Gilbert porting machine & a new VTL CNC into Shop 17 Cost of removal of the Heyligenstaedt & the Betts Porting brought to Shop 17 Majority of work performed on VTL with Shop 21 machines for backup Need to propose a viable business case for the new machine

20 Option #6 Moving Shop 21 & the Gilbert porting machine into Shop 17, along with the removal of the Summit machine – Drawing A Cost of removal of the Heyligenstaedt, the Betts, & the Summit Porting brought to Shop 17

21 Option #7 Moving Shop 21 & the Gilbert porting machine into Shop 17, along with the removal of the Summit machine – Drawing B Cost of removal of the Heyligenstaedt, the Betts, & the Summit Porting brought to Shop 17

22 Option #8 Moving Shop 21, the Gilbert porting machine, & a new VTL CNC into Shop 17, along with the removal of the Summit machine Cost of removal of the Heyligenstaedt, the Betts, & the Summit Porting brought to Shop 17 Majority of work performed on VTL with Shop 21 machines for backup Need to propose a viable business case for the new machine

23 Option #9 Moving Shop 21, Shop 6, & the Gilbert porting machine into Shop 17, along with the removal of the Summit machine Cost of removal of the Heyligenstaedt & the Betts Porting brought to Shop 17 Cost of foundation preparation & move of Norton Grinder & American Lathe Liner Cell moved out of Shop 21 & 6

24 Option #10 Moving Shop 21 into Shop 6 All moving can be done in house
Already open & available floor space Liner Cell moved entirely into Shop 6 Room available for possible new machine(s)

25 Option #11 Moving Shop 21 into Shop 6 All moving can be done in house
Already open & available floor space Liner Cell moved entirely into Shop 6 Room available for possible new machine(s)

26 Decision Matrix Layout - Pete As Is #1: 21 to 17 #2: 21 to 17 w/ Gilbert #3: 21 to 17 w/ new VTL #4: 21 & 6 to 17 #5: 21 to 17 w/ Gilbert & VTL #6: 21 to 17 w/ Gilbert, Summit Removed - A #7: 21 to 17 w/ Gilbert, Summit Removed - B #8: 21 to 17 w/ Gilbert & VTL, Summit Removed #9: 21 & 6 to 17 w/ Gilbert, Summit Removed #10: 21 to 6 - A #11: 21 to 6 - B Weight Move Time 5 2.5 2 1.5 1 4 Productivity 3 3.5 Footprint Cost 0.5 Safety Travel Distance 4.5 Flexibility Feasibility Total: 22.5 25 22 23.5 29 30 Weighed Total: 41 49 40 47.5 48.75 42.5 39.75 58.5 60 The breakdown of all the possible layouts (several are no longer possible as shown by feasibility) comes to show that one of the simplest solutions is proven to be the ideal one. Option #11 is ideal due to all the necessary machines being capable of in house movement, a nice semi-linear flow, the layout space only being used presently for WIP, & the open space left available in Shop 17 for possible additional machines.

27 Process Improvement Concept Selection and Improvement
Process control board Machine downtime board Cell safety and information placard Standardized work charts Waste tracking sheet R· I· T Mechanical Engineering Department

28 Value Stream Map R· I· T Mechanical Engineering Department

29 Process Control Board R· I· T Mechanical Engineering Department

30 Machine D/T Board R· I· T Mechanical Engineering Department

31 Cell Safety Information
R· I· T Mechanical Engineering Department

32 Standard Work Charts 3 1 5 2 8 7 4 6 9 R· I· T Mechanical Engineering Department

33 Waste Tracking Sheet R· I· T Mechanical Engineering Department

34 Material Handling Current Material Handling Procedure:
Liners set vertically onto wooden pallets, moved by forklift Causes parts to fall if forklift must stop short, resulting in defects Current Defect Cost: Approximately $6,000 (Over 2 years) Many more unreported incidents Major safety concerns R· I· T Mechanical Engineering Department

35 Concept Selection Concept Selected: #6, Standard w/ VBlock Fixture
R· I· T Mechanical Engineering Department

36 Final Concept R· I· T Mechanical Engineering Department
Large V Block Holes for adjustable V Block spacing Small V Blocks Standard wooden pallet Method for strapping the liner to the pallet Standard wooden pallet with adjustable V Block fixtures for different sizing/length of liners R· I· T Mechanical Engineering Department

37 Material Selection R· I· T Mechanical Engineering Department

38 Material Handling BOM R· I· T Mechanical Engineering Department H-2089
Product Number Vendor Product Desc Qty List Price Total Part Price Lead Time  H-2089 ULINE 48X40 HEAT TREAT RECYCLED PALLET 30 $16.00 $480.00 <1 Week 4023 Lowes Pine 8 ft 4”x4” Lumber 16 $9.67 $154.72 In Store 1640T37 McMasterCarr Architectural Aluminum (Alloy 6063) 1" Diameter, 8' Length 6 $36.41 $218.46 2VKN5 Grainger Retractable Tie Down, 10 Ft L, PK2 $88.35 $2,650.50 2936T31 Hot-Dipped Galvanized Steel U-Bolt 1/4"-20 X 3/4" Thread Length, for 9/16" OD, 435# Wll 60 $0.66 $39.60 (---) Dresser Rand Gorilla Glue 1 R· I· T Mechanical Engineering Department

39 Feasibility Analysis Through a series of FEA analyses in COMSOL, it was determined that an oak pallet could withstand the weight of a 2000lb liner with a factor of safety of at least 4. R· I· T Mechanical Engineering Department

40 Test Plan Prototype pallet (1-3 units) Run prototype at Dresser Rand
Purchase base pallet to specifications Mfg V Blocks in RIT machine shop Band Saw, Lathe, Hand Tools Done in weeks 1-3 of MSD II Mechanical engineer will manufacture Run prototype at Dresser Rand Use on shelf, floor, forklift Place on liners (smallest to largest) Check for any failures in the pallet, V blocks or straps R· I· T Mechanical Engineering Department

41 Action to Minimize Risk
Material Handling Risk Analysis Risk Item Effect Cause Likelihood Severity Importance Action to Minimize Risk Pallet design does not meet needs Poor grade, Dissatisfied customer Inadequate communication with management 2 3 6 Weekly meetings with management to determine accuracy of design to needs Maintenance of tools/ process after completion Downtime Poor planning, lack of research 4 Documentation of processes and tools Pallet Fails Wasted time and effort, Unsatisfied customer Poor Craftsmanship, Low reliability, Complex design 1 Maintenance documents, Proper training, Simple design, Design for robustness V Blocks fail Pallet used by other department Lost pallet, wasted effort Not properly labeling pallet, no rules for usage Label all pallets with department number, assign responsibility to maintain pallets R· I· T Mechanical Engineering Department

42 Material Storage Current State
R· I· T Mechanical Engineering Department

43 Concept Generation Pallet rack for liners Functions of Drum Rack
Liners stored on rack Take up less floor space Increase safety Functions of Drum Rack Support load of drums (14,475 lb) Restrict drum movement (Brackets) Built to OSHA standards for safety R· I· T Mechanical Engineering Department

44 Material Storage First Design Change
Include a wire mesh decking in order to support a wooden pallet if needed Rack will be able to support any pallet Second Design Change Large liners stored vertically Large liners will deform under their own weight R· I· T Mechanical Engineering Department

45 Material Storage Third Design Change Rack dimensions changed
Went from 48” x 144” to 42” x 86” based on availability of racks at DR R· I· T Mechanical Engineering Department

46 Concept Selection Matrix
R· I· T Mechanical Engineering Department

47 Feasibility Analysis Operational feasibility for installation of a rack system is high since it is cheap and easy to use. The only issue with a shelf would be loading and unloading safely within the area of the shelf. There needs to be enough clearance above the rack to be able to load the top shelf, and a clear path to and from the storage area. There will need to be front to back supports to reduce the likelihood of an inaccurately placed load falling between the beams. R· I· T Mechanical Engineering Department

48 Test Plan Placing liners onto pallets and then place the loaded pallet on the rack. The desired outcome is a rack system that can carry the load and maintain an excellent level of safety for the workers in Liner cell. Testing the spacing between shelves. The shelves need to be adequately spaced to provide easy placement and removal of loaded pallets. Use various forklifts to load and unload the rack to ensure compatibility with rack location. R· I· T Mechanical Engineering Department

49 Bill of Materials R· I· T Mechanical Engineering Department
Manufacturer Part number Description Quantity Vendor Lead time Price Total Lodi LBC50-86 Beam, 86" long, max load: 11,197; max δ, 0.27" 12 Material Flow 2 week $35.20 $422.40 LM30 Upright, 42" deep, 120" height, Max load: lb 6 $98.86 $593.16 Lyon WD4442H Wire decking, 44" wide, 42" deep $25.39 $304.68 McMaster 92188A301 Upright anchor 24  Material Flow 1 week $4.00  $96.00 $1,320.24 R· I· T Mechanical Engineering Department

50 Risk Assessment R· I· T Mechanical Engineering Department
Risk Assessment Table Risk Item Effect Cause Likelihood Severity Importance Action to Minimize Risk Injury of student or DR team member Downtime for employees, Loss of student man hours Liner falling off of rack 1 3 Review safety procedures, do not distract others when working Pallet breakage Material damage, injury Weathering, poor construction 2 6 Inspect pallet before placing on the rack Rack failure Injury or death, material damage Disregarding design criteria, overloading rack Use a smaller, more robust rack Rack does hold all liners Excess material on the floor Not taking into account all sizes of liners Take into account all liner sizes, confirm with management entire range of liners R· I· T Mechanical Engineering Department

51 Comparison to Target Specs (Space Utilization)
Estimated Liners in inventory Current State: On floor 480 sq. ft. total Future State: On racks 78.75 sq. ft. Initial Estimated Reduction (60%) Actual Planned Reduction (80%)

52 Risk Assessment Update
Importance* Action to mitigate Management Restructuring 3 Weekly meetings with management, get buy in from multiple stakeholders, have contingency plans Failure to pass budget approval 6 Have contingency plan, create detailed cutover plan Machine move takes longer than expected Have all details for move ready, support move while occurring, make clear DR capabilities Operators reject process improvements Have meeting to explain importance, guide supervisor and operator in implementation *Based on Severity (1-3) x Likelihood (1-3). 1= lowest, 9= highest

53 Risk Assessment Comparison

54 MSD II Project Plan


Download ppt "Multidisciplinary Senior Design Rochester Institute of Technology Dresser-Rand Painted Post P10459 Detailed Design Review 2/26/10 Team: Phil Eaton (ME)"

Similar presentations


Ads by Google