Presentation is loading. Please wait.

Presentation is loading. Please wait.

Special Report NuMI Target Updates Special Report NuMI Target Updates Status Update I.Target Hall Target module ready to accept new target General target.

Similar presentations


Presentation on theme: "Special Report NuMI Target Updates Special Report NuMI Target Updates Status Update I.Target Hall Target module ready to accept new target General target."— Presentation transcript:

1 Special Report NuMI Target Updates Special Report NuMI Target Updates Status Update I.Target Hall Target module ready to accept new target General target hall working ongoing (e.g., dehumidifier maintenance) II.NT-06 Preparation for Beamline Installation Successful downstream water turnaround retrofit of NT-06 QA of weldments revealed excellent results (X-ray shows no internal defects and target pressure tested to 150 psig for 40 minutes with no pressure loss) Reassembled target core in canister Completed survey- all features fall within specified tolerance (~ ¼ mm) Target will be installed and surveyed in carrier frame assembly this week Expect to start installation in NuMI Target Hall Monday 4/4 III. Reclaim NT-02 as a contingency spare ALARA plan in preparation to remedy slipping couplers and install a new DS screw drive bearing block Efforts should re-start later this week May require ~2 weeks of effort to reclaim z-drive motion (if possible) Kris Anderson 28-Mar-2011 Kris Anderson 28-Mar-2011

2 Special Report NuMI Target Updates Special Report NuMI Target Updates NuMI Low Energy Target General Assembly Layout Downstream Water Turnaround Weldments Previously Identified Potential Failure Location Previously Identified Potential Failure Location

3 NT-06 Cooling tube transition sleeves cleaned and ready for new water channel design Special Report NuMI Target Updates Special Report NuMI Target Updates NT-06 Retrofit

4 NT-06 Retrofit ready for welding and X-ray inspection Tuesday 3/22 Special Report NuMI Target Updates Special Report NuMI Target Updates NT-06 Retrofit

5 Successful Installation of Welded Retrofit Turnaround Special Report NuMI Target Updates Special Report NuMI Target Updates NT-06 Retrofit

6 Reassembled NT-06 Target Core into Canister Assembly Survey shows can features compared to previous referencing within 0.002” Target tube straight vertically within ± 0.005” Target tube straight horizontally within +0.009”/-0.003” Excellent Results Special Report NuMI Target Updates Special Report NuMI Target Updates NT-06 Assembly

7 NT-07 and NT-08 Current proposal is IHEP will send finished target core with the exception of the downstream water turnaround and we will install our design and finish target assembly here NT-07 and NT-08 are expected from IHEP 9/30/2011 Special Report NuMI Target Updates Special Report NuMI Target Updates NT-07 and NT-08 Approach

8 Special Report NuMI Target Updates Special Report NuMI Target Updates Estimated Key Dates-Nominal Scenario I.NT-06 Installation NT-06 Target/Baffle Carrier final outfitting at MI-8, survey, and Q/A this week 3/28 thru 4/2 Installation of NT-06 into beamline chase 4/4 – 4/9 Estimate for beam ~12:00 on Sunday 4/10 II. NT-02 Path (Contingency Target) NT-02 is leak tight but status of z-drive reclamation is still TBD Likely to take about 2 weeks of effort to define and implement procedure to assess and return z-drive mechanism to operational status; Will resume work to recover z-drive later this week pending approval of ALARA plan Key Dates


Download ppt "Special Report NuMI Target Updates Special Report NuMI Target Updates Status Update I.Target Hall Target module ready to accept new target General target."

Similar presentations


Ads by Google