Presentation is loading. Please wait.

Presentation is loading. Please wait.

LCLS LCLS-II Survey & Alignment

Similar presentations


Presentation on theme: "LCLS LCLS-II Survey & Alignment"— Presentation transcript:

1 LCLS LCLS-II Survey & Alignment
International Review for PAL-XFEL Survey & Alignment May 31, 2011 Catherine LeCocq SLAC Metrology Department

2 SLAC Site

3 From John Galayda LCLS-II DOE CD-1 Review April 26, 2011
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

4 A Five Step Process Planning Monument Network
Information gathering - Physics requirements - Engineering interfaces - Geodetic aspects Simulation Monument Network Component Fiducialization Installation Girder Alignment (if applicable) Component Alignment Mapping Operation Phase Monitoring (if applicable) Mapping and re-alignment LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

5 SLAC Instrumentation Primary Instrumentation: Accessories:
Automatic Levels: Leica DNA03 Laser Trackers: FARO Xi (Leica AT401 to be acquired for LCLS-II) In-house portable wire system  Accessories: Bar code rods: 2 meters and 0.6 meters long Tripods: Brunson heavy stands, Kara portable tooling stands Survey targets: 1 ½” Corner Cube Reflectors (12 per laser tracker) Field Data Collectors: Paravant and Allegro  Additional Equipment: Total Stations: Leica TC2002 and TDA5005 FARO platinum portable arms (4ft, 8ft, 12ft) Gyrotheodolites: GYROMAT 2000 Optical Plummet: Wild NL GPS Receivers: Leica SR-530 Laser Scanner: Z+F Imager 5006 LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

6 Software Model Parametric Model Stochastic Model Least Square Solution
l = observation vector x = unknown (or parameter) vector Stochastic Model = variance-covariance matrix = variance factor Least Square Solution Free Net Solution LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

7 LCLS-I UH Network Simulation
Tunnel dimensions: 130 m long, 5 m wide and 2 m high Floor is 1.0 m below beamline, wall monuments are 0.75 m above beamline, laser tracker set-ups are 0.4 m and 0.6 m above beamline 49 Points – 17 Laser Tracker Set-ups sD = 30 μm sh = 30 μm / D sv =50 μm /D sdh = 50 μm W23 sz = 22 μm sx = 47 μm sy =46 μm LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

8 LCLS-I Single Total Station Set-up
Single TC2002 Set-up sD = 100 μm sh = 50 μm/D sv = 50 μm/D “Plate15” sz = 83 μm sx = 108 μm sy = 72 μm LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

9 Monumentation Network
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

10 (with removable spherical target)
UH Monumentation See ESD Undulator Tunnel Survey Monument Positions wall monuments (with removable spherical target) floor monument 6’ 1‘ stay-clear LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

11 LCLS-I UH with LCLS-II Undulators
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

12 Observation Schema Laser Tracker Precision Level Other
Adapt observation scheme tested in simulation to real world 3 triplets per point Calibrate instrument Follow observation guidance: 1 triplet = 2 sets of direct and reverse Precision Level Loop over floor points Calibrate instrument and rod 1 shot = average of 3 readings Other Total station Nadir plummet Gyrotheodolite Portable wire LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

13 LCLS-I Network for UH Installation
Points 451 Tracker 86 Total Station 11 Triplets 1475 Height Differences 473 Azimuth 14 Wire 3 Horizontal Offsets 79 Point Coordinates 1329 Instrument Coordinates 291 Instrument Rotations 269 Nuisance Parameters 7 Datum Parameters 4 Total Unknowns 1900 LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

14 LCLS-I Portable Wire Results
Position [m] Sigma [µm] Network measurements alone Wire measurements included Coordinate change [µm] Impact of wire on standard deviations Impact of wire on coordinates Network of 393 points with the following observation schema: triplets from 69 tracker setups, 465 height differences and 57 offset measurements to two overlapping wires (240m long and 370m long). A-priori standard deviations: Laser Tracker: sD=50 µm, sHz=70 µm/m, sV=100 µm/m Level: sDh=70 µm Offset measurement: sDo=30 µm Extracted from IWAA08 Poster LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

15 Component Fiducialization
Advantage: repeatable references Methodology: mechanical or magnetic Tooling Choices: compatible with observation techniques in the field Instrument: CMM Laser tracker Optical tooling Robotic arm Photogrammetry LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

16 Mechanical Fiducialization
LCLS-I Tweeter Quadrupole Magnet Tooling Ball FORM DIAMETER X Y Z TB 1 TB 2 TB 3 TB 4 LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

17 Magnetic Fiducialization
See LCLS-TN-05-11 LCLS-I Undulator Quadrupole Magnet Overall fiducialization accuracy in x and y < 25 µm 3 Step Process: Place wire at quadrupole center: 10 µm Locate wire: 15 µm Locate tooling balls: 10 µm LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

18 Undulator Fiducilization
From Zack Wolf & Georg Gassner LCLS-II DOE CD-1 Review, April 26, 2011 LCLS-I Case: Pointed magnets with same sign poles are added to the ends of the undulator. These magnets have a well defined zero field point in the center. The distance from the measurement axis to the zero field point is determined. A calibration gives the distance from the zero field point to tooling balls on the pointed magnet fixture. The distance from the tooling balls on the pointed magnet fixture to tooling balls on the undulator is measured with a CMM. LCLS-II Case: More fiducials, independent treatment of the jaws, Measurement with laser trackers. Expected accuracy: 30 to 50 μm LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

19 Girder Alignment Advantages: Variations:
Better relative component alignment Speed up installation phase Variations: Individual component adjustment Mover Mechanism: Fixed Remote Feedback LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

20 LCLS-I Undulator Girder
Extract from LCLS TN-08-03: Girder Alignment Plan The Undulator Girder alignment was carried in 2 steps: Pre alignment and all connection installation (wiring and plumbing in a staging area (see picture above) Final alignment in a controlled temperature environment on a CMM LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

21 LCLS Coordinate Measuring Machine
Leitz Reference Model CMM manufactured in Wetzlar (Germany) Weight capacity 3000 kg Measuring range is 0.9 x 1.5 x 4.5 m Resolution is 0.1 µm Spatial accuracy formula in µm based on L, the length measured in mm: L/350. After specific tuning for the undulator segment weight and location on the CMM, the expected accuracy for the undulator segment should be upgraded to: L/500. LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

22 Component Alignment Timeline: Principle:
Template layout Stand/base plate alignment Component/girder alignment Principle: Solid monument network Component fiducialization Local instrument set-ups Variations and possible difficulties come with the hardware installed: Clearance around bolts Mover system centered around their range Component pre-set to nominal Fiducial and mover in-line when possible Right balance between fine and coarse thread LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

23 Example LCLS-I BTH West
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

24 Mapping Phase Observation scheme: Computation phase: Move list
Identical to monument network Including component fiducials Computation phase: Generating observed position and attitude (and their standard deviations) for each component Move list Option 1: to ideal Option 2: to smooth line The next 2 graphs show the as-built results for the 33 quadrupole magnets in the Undulator Hall in December 2008, right before the start of LCLS-I. LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

25 LCLS LCLS-II Survey & Alignment
Pohang Accelerator Laboratory,

26 LCLS LCLS-II Survey & Alignment
Pohang Accelerator Laboratory,

27 Linac Laser Alignment - Line
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

28 Linac Laser Alignment - Changes
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

29 LCLS-I Measurement Campaigns
LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

30 UH Wall Deformations Both Undulator Hall and X-Ray Tunnel show slow shrinking of the tunnel walls relative to each other by <1mm/year LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

31 Floor Deformations LTU UH XRT FEH Dump FEE NEH
3 mm initial floor deformation, correlated with earth backfill above dump area Since July 08 deformation < 0.5 mm (~0.5 μm/day for largest deformation) LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,

32 LCLS Survey & Alignment Timeline
Nov 2007 Dec 2007 Jan 2008 Feb 2008 Mar 2008 Apr 2008 May 2008 Jun 2008 Jul 2008 Aug 2008 Sep 2008 Oct 2008 Nov 2008 Dec 2008 Monument Template Stand / Plate Component Mapping / Move LCLS-I e-beam Installation Feb 2004 May 2005 Outside Network Fiducialization Girder Assembly May 2010 May 2011 LCLS-II LCLS LCLS-II Survey & Alignment Pohang Accelerator Laboratory,


Download ppt "LCLS LCLS-II Survey & Alignment"

Similar presentations


Ads by Google