Presentation is loading. Please wait.

Presentation is loading. Please wait.

KAGRA subgroup report Cryogenics T. Suzuki, Y. Sakakibara KEK/ICRR 2015.02.05.

Similar presentations


Presentation on theme: "KAGRA subgroup report Cryogenics T. Suzuki, Y. Sakakibara KEK/ICRR 2015.02.05."— Presentation transcript:

1 KAGRA subgroup report Cryogenics T. Suzuki, Y. Sakakibara KEK/ICRR 2015.02.05

2 Contents of this report Introduction of subgroup members (T.Suzuki) Status of fabrication (T.Suzuki) Installation of cryostats and duct shields (T.Suzuki) Performance of duct shield (Y.Sakakibara) Topics will be presented in 6 th Feb. Cryo-suspension design (K.Yamamoto, D.Chen, T.Miyamoto, H.Tanaka) Surveying and alignment (T. Kume)

3 KAGRA Cryogenics Group Toshikazu SUZUKI Chief KEK, Prof. Nobuhiro KIMURA Cryostat sub-chief KEK, Assoc. Prof. Kazuhiro YAMAMOTO Cryo-Payload sub-chief ICRR, Assist. Prof. Takayuki TOMARU Cryo-Payload KEK, Assoc. Prof. Tatsuya KUME Surveying, Alignment KEK, Assoc. Prof. Rahul KUMAR Simulation, Payload KEK, PD Yusuke SAKAKIBARA Cryostat, Scattering ICRR, Grad. Student Dan CHEN Cryo-Payload, Q ICRR, Grad. Student Ayako HAGIWARA CAD KEK, Technical Staff Shinichi TERASHIMA Machining KEK, Technical Staff Iwao MURAKAMI Welding, Assembly KEK, Technical Staff Hiroki TANAKA Cryo-Payload, Q ICRR, Grad. Student Takahiro MIYAMOTO Cryo-Payload ICRR, Grad. Student Rookie Suguru TAKADA Cryogenics NIFS, Assist. Prof.

4 Mr. Shigeaki KOIKE, KEK Engineer, passed away in last Nov. 15 He designed KAGRA Cryostat and gave many contribution to KAGRA. We lost a good friend, but his work will be in KAGRA.

5 KAGRA Cryogenics Manufacturing – Cryostats and 4K cooler units (done 4 sets in 2011~2012) – Duct-shields (done 3 in 2013, fabricating 3 in 2014, will fabricate 2 in 2015) – 80K coolers for cooling duct- shields ( fabricating 8 in 2014) Installation – Transport from the warehouse – Carry cryostats through the tunnel – Assembling on a target point Cryogenic payload – > Topic 3 6 th Feb.

6 Transportation of cryostats to X and Y ends

7 Assembling and leak test of  2400 upper flange Construct a simple clean booth around a cryostat. Set blower to supply filtered air. Put a metal gasket to the upper flange and fasten the flange. Set side port flanges. KAGRA requirement < 1x10 -10 Pa*m 3 /sec Detector background 1x10 -12 Pa*m 3 /sec No excess leak found above the background. Surveying and alignment -> Topic 9 6 th Feb.

8 Design of duct shield Duct and baffles are coated with black coating Solblack to absorb thermal radiation and scattered light – Calculated thermal radiation input < 0.38 W (<KAGRA requirement 0.5 W) Baffles are tilted to catch scattered light Cooled down by vibration-isolated cryocooler unit during observation – Cryocooler was directly connected here for testing 8 Length in mm 5 m Baffle Scattered light Duct

9 Calculated scattered light noise Calculated result was found to satisfy KAGRA requirement 9 Resonance 1 Hz Power inside cavity 400 kW Mass 23 kg Solblack reflectivity and scattering property: Genesia, T. Akutsu PSD of mirror surface: E. Hirose et al. Phys. Lett. D 89 (2014) 062003 D. J. Ottaway et al. OPTICS EXPRESS 20 (8) (2012) 8329

10 Summary Fabrication – Three duct-shields and eight 80K cooler units are fabricating in 2014fy. – Two duct-shields will be fabricated in 2015fy. Installation – Two cryostats installed to X-end and Y-end. – Another two will be installed to X-front and Y-front in Feb. and Mar. 2015. – No leak was found for the cryostat in X-end. – Measurement of attitude of cryostat will be continued Duct-shield – Suppression of thermal radiation and scattered light were evaluated


Download ppt "KAGRA subgroup report Cryogenics T. Suzuki, Y. Sakakibara KEK/ICRR 2015.02.05."

Similar presentations


Ads by Google