Presentation is loading. Please wait.

Presentation is loading. Please wait.

B ROWN W OOD P RESERVING S UPERFUND S ITE Live Oak, Florida U.S. Environmental Protection Agency Lisa Moore Daniel Stern.

Similar presentations


Presentation on theme: "B ROWN W OOD P RESERVING S UPERFUND S ITE Live Oak, Florida U.S. Environmental Protection Agency Lisa Moore Daniel Stern."— Presentation transcript:

1 B ROWN W OOD P RESERVING S UPERFUND S ITE Live Oak, Florida U.S. Environmental Protection Agency Lisa Moore Daniel Stern

2 S ITE I NTRODUCTION Located 2 miles west of Live Oak city in Florida 1948 to 1978 – wood preserving pressure treatment facility using two treatment cylinders Products used mainly creosote and water Brown Wood Site Waste water from the treatment cylinders was fed into oil/water separator Creosote moved to storage tanks and the water treated and drained into a nearby lagoon

3 S ITE I NTRODUCTION Pressure Treatment Cylinders Treated Lumber is Dried and Stored

4 C ONTAMINATION P ROBLEM Florida Department of Environmental Regulation (FDER) sampled the site in July 1982. Contaminated with polynuclear aromatic hydrocarbons. The Environmental Protection Agency (EPA) placed the site on the National Priorities list in December 1982 Six PAHs were considered high risk. EPA issued administrative order in September 1983. In April 1988 a ROD was signed which established a clean goal of 100 mg/kg or less of Total Carcinogenic Indicator Chemicals (TCIC) within two years.

5 I NTERIM R EMOVAL A CTIVITIES Interim removal activities were carried out between December 1987 and March 1988 including: - Removal and treatment of 200,000 gallons of lagoon water - Excavation, treatment and disposal of 15,000 tons of highly contaminated sludge and soil at an Emelle, Alabama, landfill. - Sampling, analysis and stockpiling of contaminated soil for land treatment.

6 A LTERNATIVE S OLUTIONS No action On-site incineration Off-site incineration Land treatment Treatment of sludge and off-site disposal of wastes Treatment and disposal of sludge's and land treatment of soils Biological treatment of sludge’s using sequenced batch reactors followed by land treatment of sludge and soil

7 L AND T REATMENT A REA LTA Pond Lagoon Stockpile The option of land treatment of soils was selected LTA was constructed including a retention pond and an irrigation and drainage system Vegetation and structures cleared from four acres of ground Contaminated soil was excavated and stored in a stockpile area

8 T REATMENT A CTIVITIES LTA construction completed in October 1988 The site was divided into eight equal subplots The contaminated stockpiled soil was transported in three lifts The first lift began in January 1989 and was 3,300 yds 3 of soil, which was irrigated and fertilized Twice a week the soil was inoculated with PAH degrading micro organisms Inoculums were developed in on-site reactors, then sprayed onto the soil using the irrigation system

9 T REATMENT A CTIVITIES A soil moisture content of 10% was maintained Samples were collected to monitor the soils TCICs concentration The first level was treated until the concentration fell below the required level (100 mg/kg) The the second lift of soil (3,000 yd 3 ) was distributed in September 1989 Final lift (1,800 yd 3 ) was then spread and treated, resulting in a total quantity of around 8,100 yd 3

10 S UMMARY This case is one of the earliest applications of land treatment at a superfund site contaminated with creosote compounds. The total cost for the treatment of 8,100 cubic yards of soil was approximately $565, 400, corresponding to a cost of $70 per cubic yard of soil. The cleanup goal of 100 mg/kg TCIC was met after 18 months.


Download ppt "B ROWN W OOD P RESERVING S UPERFUND S ITE Live Oak, Florida U.S. Environmental Protection Agency Lisa Moore Daniel Stern."

Similar presentations


Ads by Google