Christchurch Town Hall November 27th, 2013. Introduction What happened –Settlement –Lateral Spread –Measurements Analysis –Current capacity Repair and.

Similar presentations


Presentation on theme: "Christchurch Town Hall November 27th, 2013. Introduction What happened –Settlement –Lateral Spread –Measurements Analysis –Current capacity Repair and."— Presentation transcript:

1 Christchurch Town Hall November 27th, 2013

2 Introduction What happened –Settlement –Lateral Spread –Measurements Analysis –Current capacity Repair and strengthening –Foundation options and implications –Superstructure strengthening Relevelling Peer Review

3 Damage sustained

4

5

6

7 Level Survey 300mm 210mm 150mm 90mm

8 Verticality Survey 50 mm 30 mm 55 mm 20 mm 16 mm 35 mm

9 Analysis Full 3D computer analysis model developed –Non-linear, i.e. models strength and then determines outcomes Quake records run –From major Canterbury earthquakes –Scaled to reflect code demands Performance assessed –Compared to current code, IL3

10 Computer Modelling

11 Computer Analysis – Canterbury earthquake sequence

12 Computer Analysis – Code comparison

13 Current Seismic Status 45%NBS 14%NBS 45%NBS 63%NBS 27%NBS

14 Repair and Strengthening Repair –Reinstate as nearly as practical to original condition Accept or reinstate concrete damage where no structural implications Strengthen –Upgrade of foundations critical to prevent future damage Option 1 – Piles Option 2 – Grouting –CCC policy is to achieve 100%NBS

15 Option 1 - Piles

16 Option 2 - Grouting

17 Beneficial effect Movement under moderate earthquake –Piles: 10mm lateral, 15mm vertical –Grouting: 0mm lateral, 15mm vertical Movement under design level earthquake –Piles: 150mm lateral, 30mm vertical –Grouting: 50mm lateral, 75mm vertical Conclusions: Jet Grouting selected as preferred option as: –Less intrusive construction process –Superior resistance to lateral spread –Easier waterproofing detailing

18 Structural Work Summary Upgrade foundations first –Primary need before any other work –Jet grouting Re-level (Limes Room) Strengthen Repair & refurbish

19 Strengthening Minimal strengthening required to Auditorium, James Hay Theatre and Kitchen Foyer –Columns too flexible and under-strength: rebuild –Bracing excluded as too intrusive –Steel frame alternative under consideration Limes Room/restaurant –Columns too flexible and under-strength: add bracing below level1

20

21

22

23

24 Relevelling Consideration All of ground floor slab must be removed to complete foundation work Relevelling of structure –Must be done, in case of Limes Room –Could be accommodated by careful detailing in case of Auditorium, Foyer, James Hay Theatre

25 Peer Review

26 End