PROJECTS. 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity.

Similar presentations


Presentation on theme: "PROJECTS. 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity."— Presentation transcript:

1 PROJECTS

2 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): € Hot runner system: Moldmaster Steel: cavity each mould

3 1- Joint 2 - Duct Execution Period: 4 weeks Price: € Cold Runner Steel: cavities 1 2 Execution Period: 4 weeks Price: € Cold runner Steel: cavities

4 Ecran sous Reservoir (sandwich mould) Execution Period: 10 weeks Price: € Hot runner system: Moldmaster Steel: cavities

5 Colector (sandwich mould) Execution Period: 13 weeks Price: € Hot runner system: Incoe Steel: hardened cavities

6 Carcasa Volvo Execution Period: 6 weeks Price: € Hot runner system: Dan Tip Steel: cavities

7 Lens Holder Execution Period: 6 weeks Price: € Hot runner system: Hasco Steel: hardened 2 cavities

8 Tirador Puerta Execution Period: 7 weeks Price: € Cold Runner Steel: cavities

9 Cañon Retinidor de Sonido Execution Period: 5 weeks Price: € Cold Runner Steel: cavities

10 Bas de Caisse Execution Period: 12 weeks Price: € Hot runner system: Incoe sequential Steel: HH cavities

11 Bracket a Digital Execution Period: 5 weeks Price: € Cold runner Steel: cavities

12 Bracket G2 Execution Period: 5 weeks Price: € Hot Runner System: EMP Steel: cavities

13 Base Filtros Soplados Execution Period: 4 weeks Price: € Cold Runner Steel: cavity

14 Helmet Execution Period: 8 weeks Price: € Hot nozle Steel: cavity

15 Multibutton Execution Period: 4 weeks Price: € Injection System of 3 Plates Steel: cavities

16 Stand Foot Execution Period: 6 weeks Price: € Hot Runner System: EMP Steel: cavities

17 1. Mascara 2. Cristal Execution Period: 6 weeks Price: € Cold Runner Steel: Execution Period: 6 weeks Price: € Hot Runner System: Moldmaster Steel:

18 Support (Sandwich mould) Execution Period: 13 weeks Price: € Hot Runner System: Incoe Steel: hardened cavities

19 Maleta K72 Execution Period: 6 weeks Price: € Hot Runner System: EMP Steel:

20 Culata Execution Period: 12 weeks Price: € Hot Runner System: Incoe Steel:

21 Windweiser LH/RH Execution Period: 4 weeks Price: € Cold Runner Steel: cavities