Presentation is loading. Please wait.

Presentation is loading. Please wait.

PROJECTS. 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity.

Similar presentations


Presentation on theme: "PROJECTS. 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity."— Presentation transcript:

1 PROJECTS

2 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity each mould

3 1- Joint 2 - Duct Execution Period: 4 weeks Price: 18.000 € Cold Runner Steel: 1.2711 2 cavities 1 2 Execution Period: 4 weeks Price: 32.500 € Cold runner Steel: 1.2711 2 cavities

4 Ecran sous Reservoir (sandwich mould) Execution Period: 10 weeks Price: 170.500 € Hot runner system: Moldmaster Steel: 1.2311 1 + 1 cavities

5 Colector (sandwich mould) Execution Period: 13 weeks Price: 156.000 € Hot runner system: Incoe Steel: 1.2344 hardened 2 + 2 cavities

6 Carcasa Volvo Execution Period: 6 weeks Price: 98.000 € Hot runner system: Dan Tip Steel: 1.2311 1 + 1 cavities

7 Lens Holder Execution Period: 6 weeks Price: 22.000 € Hot runner system: Hasco Steel: 1.2344 hardened 2 cavities

8 Tirador Puerta Execution Period: 7 weeks Price: 29.000 € Cold Runner Steel: 1.2311 1 + 1 cavities

9 Cañon Retinidor de Sonido Execution Period: 5 weeks Price: 29.000 € Cold Runner Steel: 1.2711 2 cavities

10 Bas de Caisse Execution Period: 12 weeks Price: 213.000 € Hot runner system: Incoe sequential Steel: 1.2738 HH 1 + 1 cavities

11 Bracket a Digital Execution Period: 5 weeks Price: 86.000 € Cold runner Steel: 1.2311 2 cavities

12 Bracket G2 Execution Period: 5 weeks Price: 88.000 € Hot Runner System: EMP Steel: 1.2311 2 cavities

13 Base Filtros Soplados Execution Period: 4 weeks Price: 29.000 € Cold Runner Steel: 1.2311 1 cavity

14 Helmet Execution Period: 8 weeks Price: 45.000 € Hot nozle Steel: 1.2311 1 cavity

15 Multibutton Execution Period: 4 weeks Price: 21.500 € Injection System of 3 Plates Steel: 1.2311 4 cavities

16 Stand Foot Execution Period: 6 weeks Price: 18.750 € Hot Runner System: EMP Steel: 1.2311 2 cavities

17 1. Mascara 2. Cristal Execution Period: 6 weeks Price: 27.100 € Cold Runner Steel: 1.2711 Execution Period: 6 weeks Price: 37.000 € Hot Runner System: Moldmaster Steel: 1.2711 1 2

18 Support (Sandwich mould) Execution Period: 13 weeks Price: 155.000 € Hot Runner System: Incoe Steel: 1.2344 hardened 2 + 2 cavities

19 Maleta K72 Execution Period: 6 weeks Price: 44.800 € Hot Runner System: EMP Steel: 1.2311

20 Culata Execution Period: 12 weeks Price: 60.000 € Hot Runner System: Incoe Steel: 1.2711

21 Windweiser LH/RH Execution Period: 4 weeks Price: 30.000 € Cold Runner Steel: 1.2711 1 + 1 cavities


Download ppt "PROJECTS. 1 st and 2 nd row right + left (Ford Galaxy) Execution Period: 6 weeks Price (4): 188.678 € Hot runner system: Moldmaster Steel: 1.2711 1 cavity."

Similar presentations


Ads by Google