Ground Anchoring Work Preliminary Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test StressingDe - Tensioning Fabrication.

Similar presentations


Presentation on theme: "Ground Anchoring Work Preliminary Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test StressingDe - Tensioning Fabrication."— Presentation transcript:

1 Ground Anchoring Work Preliminary Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test StressingDe - Tensioning Fabrication in Workshop Assembly on Site Construction Flowchart

2 Excavation until 1st layer elevation Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test Stressing Excavation until 2 nd layer elevation Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test Stressing Construction Flowchart Ground Anchoring Work (2 Layers)

3 GROUND ANCHORING WORK STAGES

4

5

6

7

8

9 STAGE 1 - EXCAVATION WORK 1st stage of site excavation (for 1st layer anchors installation) 2nd stage of site excavation (after completion of 1st layer anchors)

10 Drilling in progress STAGE 2 - DRILLING WORK

11 Tendon being fabricatedFabricated tendon STAGE 3 - FABRICATION WORK

12 Fabricated TendonFabricated tendon STAGE 3 - FABRICATION WORK

13 Temporary tendon being installed/homed (Plaza Asia & Sudirman Mansion Project) STAGE 4 - INSTALLATION WORK Permanent anchor being installed (Long Stoorage Kali Item Project)

14 Grout pump used for anchor grouting STAGE 5 - GROUTING WORK Grout cube samples

15 Completed anchor after stressing Anchor being stressed STAGE 6 - STRESSING WORK


Download ppt "Ground Anchoring Work Preliminary Setting Out Drilling Coring ( Optional ) Homing/Installation Grouting Grout Cube Test StressingDe - Tensioning Fabrication."