Wastewater Storage Pond Design

Similar presentations


Presentation on theme: "Wastewater Storage Pond Design"— Presentation transcript:

1 Wastewater Storage Pond Design
Prepared by J.E. Andrews, PE, NRCS - Lakewood, CO Colorado CNMP Workshop

2 Workshop Objectives Assemble some basic design data
Estimate pond size required Develop a preliminary cost estimate Colorado CNMP Workshop

3 Consult with a knowledgeable Engineer to:
Consider other options and alternatives Evaluate pond site location(s) & lining requirements Analyze technical requirements for storage period and pump needs solids trap and snow removal hydrologic & waste loading factors need for treatment Design inlet, outlet & other related facilities Prepare construction drawings & specs Perform construction inspection Colorado CNMP Workshop

4 Design Considerations
Colorado CNMP Workshop

5 Colorado CNMP Workshop

6 Information Needed for Estimating Pond Volume
Storage Period Size of Runoff Producing Areas Roofs, Paved Lots & Unpaved Lots Areas for future expansion Other Areas Climate Data for site location (including evaporation) Volume of manure, wastewater & other by products to be stored in the pond. Worksheet #8 &Tables 8a, 8b & 8c Colorado CNMP Workshop

7 Example - Frank’s Dairy
Located near Fort Morgan, Colorado Pond effluent can be applied May through September 5 acres of earthen feedlot & solid manure stacking area 2,000 sq. ft. concrete surfaced holding area 1,000 sq. ft. of roofs that drain across the concrete lot 2,000 gal. wastewater per day from the milking center Manure & other solids are kept out of the pond No plans for expansion at this site Colorado CNMP Workshop

8 Step 1 - Get Climate Data @ Fort Morgan Climate Station
Annual Rainfall = 12.7” 43% runs off paved areas 15% runs off earthen feedlots 25yr-24hr Rainfall = 3.4” Average Lake Evaporation = 48” Colorado CNMP Workshop

9 Colorado CNMP Workshop

10 Step 2 - Calculate Roof Runoff Volume
Colorado CNMP Workshop

11 Step 3 - Calculate Paved Area Runoff Volume
* Annual Runoff = Annual Runoff % x Annual Rainfall 100 ** Find 25yr-24hr runoff from 3.4” rain in Table 8b. Colorado CNMP Workshop

12 Finding runoff depth from a 3
Finding runoff depth from a 3.4” rain on a concrete feedlot using Table 8b. Colorado CNMP Workshop

13 Step 4 - Calculate Earthen Area Runoff Volume
* Annual Runoff = Annual Runoff % x Annual Rainfall 100 ** Find 25yr-24hr runoff from 3.4” rain in Table 8b. Colorado CNMP Workshop

14 Finding runoff depth from a 3
Finding runoff depth from a 3.4” rain on a earth surfaced feedlot using Table 8b. (include areas outside the feedlot too) Colorado CNMP Workshop

15 Step 5 - Total Runoff Volumes
Colorado CNMP Workshop

16 Step 6 - Calculate Design Volume
* Process Wastewater Volume = 2,000 gal/day x 365 days/year / 7.5gal/cu. ft. = 97,333 cu. ft. Colorado CNMP Workshop

17 Step 7 - Choose Pond Dimensions
Choose a depth between 6’ & 12’ As deep as possible within site limits Pond bottom should be 4’ above the water table From Table 8c, select a length & width, such that: Fits available space Selected volume is greater than design volume Colorado CNMP Workshop

18 Use Table 8c - for a given depth choose a width & length that results in a volume greater than 177,453 cu ft. Assume an 8 foot depth for Frank’s Dairy Colorado CNMP Workshop

19 Estimated Cost ~ $18,000 Step 8 - Estimate Construction Cost
Volume Selected x $0.10 per cu. ft. ~ Cost 178,944 x $0.10 = $17,894 (round to nearest $1,000) Estimated Cost ~ $18,000 Colorado CNMP Workshop

20 Worksheet 8 should now be complete for your operation.
Colorado CNMP Workshop

21 However, a complete engineer’s evaluation ...
results in a smaller pond, reducing cost ~ $4,000 for Frank Colorado CNMP Workshop

22 Colorado CNMP Workshop