Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Wastewater Storage Pond Design Prepared by J.E. Andrews, PE, NRCS - Lakewood, CO.

Similar presentations


Presentation on theme: "Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Wastewater Storage Pond Design Prepared by J.E. Andrews, PE, NRCS - Lakewood, CO."— Presentation transcript:

1 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Wastewater Storage Pond Design Prepared by J.E. Andrews, PE, NRCS - Lakewood, CO

2 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Workshop Objectives Assemble some basic design data Estimate pond size required Develop a preliminary cost estimate

3 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Consult with a knowledgeable Engineer to: Consider other options and alternatives Evaluate pond site location(s) & lining requirements Analyze technical requirements for storage period and pump needs solids trap and snow removal hydrologic & waste loading factors need for treatment Design inlet, outlet & other related facilities Prepare construction drawings & specs Perform construction inspection

4 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Design Considerations

5 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop

6 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Information Needed for Estimating Pond Volume Storage Period Size of Runoff Producing Areas Roofs, Paved Lots & Unpaved Lots Areas for future expansion Other Areas Climate Data for site location (including evaporation) Volume of manure, wastewater & other by products to be stored in the pond. Worksheet #8 &Tables 8a, 8b & 8c

7 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Example - Frank’s Dairy Located near Fort Morgan, Colorado Pond effluent can be applied May through September 5 acres of earthen feedlot & solid manure stacking area 2,000 sq. ft. concrete surfaced holding area 1,000 sq. ft. of roofs that drain across the concrete lot 2,000 gal. wastewater per day from the milking center Manure & other solids are kept out of the pond No plans for expansion at this site

8 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 1 - Get Climate Fort Morgan Climate Station Annual Rainfall = 12.7” 43% runs off paved areas 15% runs off earthen feedlots 25yr-24hr Rainfall = 3.4” Average Lake Evaporation = 48”

9 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop

10 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 2 - Calculate Roof Runoff Volume

11 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 3 - Calculate Paved Area Runoff Volume * Annual Runoff = Annual Runoff % x Annual Rainfall  100 ** Find 25yr-24hr runoff from 3.4” rain in Table 8b.

12 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Finding runoff depth from a 3.4” rain on a concrete feedlot using Table 8b.

13 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 4 - Calculate Earthen Area Runoff Volume * Annual Runoff = Annual Runoff % x Annual Rainfall  100 ** Find 25yr-24hr runoff from 3.4” rain in Table 8b.

14 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Finding runoff depth from a 3.4” rain on a earth surfaced feedlot using Table 8b. (include areas outside the feedlot too)

15 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 5 - Total Runoff Volumes

16 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 6 - Calculate Design Volume * Process Wastewater Volume = 2,000 gal/day x 365 days/year / 7.5gal/cu. ft. = 97,333 cu. ft.

17 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 7 - Choose Pond Dimensions Choose a depth between 6’ & 12’ As deep as possible within site limits Pond bottom should be 4’ above the water table From Table 8c, select a length & width, such that: Fits available space Selected volume is greater than design volume

18 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Use Table 8c - for a given depth choose a width & length that results in a volume greater than 177,453 cu ft. Assume an 8 foot depth for Frank’s Dairy

19 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Step 8 - Estimate Construction Cost Volume Selected x $0.10 per cu. ft. ~ Cost 178,944 x $0.10 = $17,894 (round to nearest $1,000) Estimated Cost ~ $18,000

20 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Worksheet 8 should now be complete for your operation.

21 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop However, a complete engineer’s evaluation... results in a smaller pond, reducing cost ~ $4,000 for Frank

22 Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop


Download ppt "Section 8 - Wastewater Storage Pond Design Colorado CNMP Workshop Wastewater Storage Pond Design Prepared by J.E. Andrews, PE, NRCS - Lakewood, CO."