1 12 th ANTAH GROUP CONFERENCE 11 th - 14 th AUGUST 2005 Guoman Hotel, PortDickson Negeri Sembilan 12 th ANTAH GROUP CONFERENCE 11 th - 14 th AUGUST 2005 Guoman Hotel, PortDickson Negeri Sembilan PRIVATISATION OF LEBUHRAYA KAJANG - SEREMBAN

2 Project Title Privatisation of Lebuhraya Kajang Seremban (KASEH) Concessionaire/ Client KASEH Lebuhraya Sdn. Bhd. Turnkey Contractor IJM Construction Sdn. Bhd. Design Consultant HSS Integrated Sdn. Bhd. Project Architect Arkitek M & L Sdn. Bhd. Toll Equipment Consultant (TCS & TCSS) Perunding Eagles Sub-Contractor (Package 1B & 2A) WCT Construction Sdn. Bhd. Packages Package 1B Package 2A Package 2B Package 3 Project Information

3 Other Consultants Scope Of Work SADEC Projects Sdn Bhd Technical Support Services SADEC Sdn Bhd Project Advisor Zul Rafique and Partners Legal Hasrah Sdn Bhd Land Consultant Symonds Travers Morgan/MAG Traffic Consultants Khairi Consult Sdn Bhd Independent Consulting Engineer TRARS Consult Sdn Bhd Road Safety Audit Raine & Horne (M) Sdn Bhd Land Valuer Project Information

4 KASEH IJM (Turnkey Contractor) Governmen t Lenders Independent Consulting Engineer (ICE) Khairi Consult Design & Consultant (SC) HSS Integrated Arkitek M&L Perunding Eagles MHA reporting information reporting monitoring Contractual Relationship Functional Responsibility PRIVATISATION OF LEBUHRAYA KAJANG SEREMBAN (KASEH) Relationship Between Various Parties With Respect of the Works

5 SECTION Section 1 Section 2 Section 3 TOTAL SUB-SECTION 1A 1B 2A 2B- SECTIONAL LIMITS LOCATION LENGTH (Km) INTERCHANGES TOLL PLAZAS REST & SERVICES AREAS 1.4416.767.806.70 11.575 3 nos2 nos 1 nos + Partial Grade Separated Junction 3 nos2 nos1 nos - 2 nos - CH 0.00 to Kajang Selatan Interchange Kajang Selatan Interchange to CH 18200 To CH26000 To CH32700 CH 0.00 to Kajang Selatan I/C Kajang Selatan I/C to South of Pajam I/C To south of Mantin I/C South of Mantin I/C to south of Setul I/C South of Setul I/C To Paroi (partial Grade Separated Junction) Highway Information 44.275 7 6 2 Note: Section 1A has been completed CH32700 To CH44275

6 Proposed Senawang – Paroi Link Road Proposed Nilai - Pajam Link Road S E R E M B A N PAJAM INTERCHANGE NILAI INTERCHANGE MANTIN INTERCHANGE SETUL INTERCHANGE N E G E R I S E M B I L A N S E L A N G O R NILAI SEMENYIH MANTIN PAJAM BERANANG BANGI INTERCHANGE SEMENYIH INTERCHANGE PORT DICKSON INTERCHANGE PRIVATISATION OF LEBUHRAYA KAJANG SEREMBAN NORTH-SOUTH HIGHWAY PANTAI PAROI INTERCHANGE KAJANG KAJANG SELATAN INTERCHANGE SENAWANG INTERCHANGE KLIA INTERCHANGE KASEH Highway Proposed Realignment of Mantin-Setul Road Revised Alignment between Jelebu to Panchor as approved by UPEN N BEROGA JELEBU INTERCHANGE KAJANG Sg. Rinching Sg. Semenyih Sg. Beranang KTM RAILWAY TRACK Legend: Revised Alignment between Jelebu to Panchor as approved by UPEN Proposed Realignment of Mantin-Setul Road N24 N28 N36 B18 B34 1 N34 1 1 1 N38 86 97 N38 86 51 KAJANG – SEREMBAN HIGHWAY Lebuhraya ELITE BYPASS Sg. Langat SEREMBAN (N) INTERCHANGE BANGI NEW NILAI INTERCHANGE Alignment as per Concession Agreement

7 Kajang Selatan I/C FR 1 B18 N36 Kajang Selatan Toll Plaza Semenyih Interchange Pajam Interchange, Jelebu Toll Plaza FR1 Toll Plaza Mantin Interchange Section 1 Section 2 FR1 Setul Interchange Jelebu Interchange Paroi Interchange Section 3 FR51 FR86 Toll Plaza Setul Toll Plaza Tolling Concept

8 Implementation Programme

9 Supplemental Concession Agreement (SCA) CHANGES TO THE CONCESSION AGREEMENT In principle the Steering Committee for Privatisation have agreed to forward the following changes to be part of the Supplemental Concession Agreement. 1To adopt PLUS’s Toll Rates approved in 2002. 2To extend to Concession Period by seven years ending 2037. 3To extend the construction period to first quarter of 2007. 4To reschedule the payment for the reimbursable land cost after all commercial borrowings had been fully paid. 5To accept and adopt the realignment proposal for Package 2B (Mantin to Setul). 6To allow for Sectional Tolling on completed sections.

10 Status of Land Acquisition PACKAGE 1A -FULL POSSESSION OF SITE OBTAINED  PACKAGE 1A -FULL POSSESSION OF SITE OBTAINED  PACKAGE 1B-FULL POSSESSION OF SITE OBTAINED  PACKAGE 2A-FULL POSSESSION OF SITE OBTAINED  PACKAGE 2B - MANTIN – SETUL (PENDING FINALISATION OF REALIGNMENT) (PENDING FINALISATION OF REALIGNMENT)  PACKAGE 3 - LAND ACQUISTION 100% COMPLETED

11 Progress Status Packages Package 1B Package 2A Package 2B Package 3 Commencement Date 15-Jul-04 To be advised by KASEH Physical Progress 29.25000 Schedule 30.45000 Ahead / Delays -1.2000 Ahead / Delays (days) -9000 Design Progress 98.80%99.10%33.85%47.67%

12 Progress Photographs

13 Location : CH 0+800 FR 1 (Kajang Selatan Interchange) Description : Pavement works in progress Progress Photograph

14 Location : Bridge No. 1 (Kajang Selatan Interchange) Description : Maintain Load Test for 500mm dia spun pile Progress Photograph

15 Location : Bridge No. 1 Description : Rebar fixing for I-18 beam Progress Photograph

16 Location : CH 3+300 (Mainline – Kajang Selatan Toll Plaza Area) Description : Earthworks in progress Progress Photograph

17 Location : CH 3+500 (Mainline - Kajang Selatan Toll Plaza Area) Description : Earthworks in progress

18 Progress Photograph Location : CH 0+525 (Semenyih Interchange) Description : Bridge over Mainline

19 Location : CH 1500 – Slip Road 2B (Semenyih Interchange) Description : Earthworks in progress. Progress Photograph

20 Location : Semenyih Toll Plaza Area Description : Installation of Rebar for DBC No. S-4 Progress Photograph

21 Location : CH 5+900 Description : Preparation of formation

22 Progress Photograph Location : CH 6+600 (Mainline) Description : Preparation of formation

23 Progress Photograph Location : Bridge No.3 (B18) Description : Location of Mainline Bridge at Semenyih-Bangi road (B18)

24 Location : Bridge No. 4 - Sg. Semenyih Description : I-18 Beam casting in progress Progress Photograph

25 Location : Bridge No. 4 - Sg. Semenyih Description : Preparation of formation (view looking northbound)

26 Progress Photograph Location : CH 8+300 (Mainline) Description : Preparation of formation (view looking northbound)

27 Location : CH 10+850 (Mainline) Description : Earthworks in progress Progress Photograph

28 Location : CH 13+750 (Mainline) Description : Preparation of formation (view looking southbound)

29 Location : Bridge No.6 - Sg. Batang Benar Description : Bored pile works in progress Progress Photograph

30 Location : Ch 14000 (Mainline) Description : Preparation of formation level in progress Progress Photograph

31 Location : CH 14+750 (Mainline) Description : Laying of sub-base (view looking northbound)

32 Location : Bridge No.7 Description : Bore hole works for soil investigation in progress. Progress Photograph

33 Location :CH 0+400 Slip Road (Pajam Interchange) Description : Earthworks in Progress

34 Progress Photograph Location :CH 1+200 Slip Road 2A/2B (Pajam Interchange) Description : Earthworks in Progress

35 Progress Photograph Location : DBC TR11-1 CH17660 Description : Construction of RC sump in progress

36 Progress Photograph Location : Pajam Toll Plaza Description : View of site office

37 THANK YOU PRIVATISATION OF LEBUHRAYA KAJANG - SEREMBAN