Presentation is loading. Please wait.

Presentation is loading. Please wait.

System Development Methodology “Lite”. The SDM Lite Team! Who would have ever thought this would be a good team? Jim A.K.A. “Popeye” Rutushni Team Leader.

Similar presentations


Presentation on theme: "System Development Methodology “Lite”. The SDM Lite Team! Who would have ever thought this would be a good team? Jim A.K.A. “Popeye” Rutushni Team Leader."— Presentation transcript:

1 System Development Methodology “Lite”

2 The SDM Lite Team! Who would have ever thought this would be a good team? Jim A.K.A. “Popeye” Rutushni Team Leader Ron A.K. A. ‘”The Politician” San Angelo Len A.K.A. “Jarhead” Smith Jeanne A.K.A. “The Doctor” Lee Keith A.K.A. “ The Farmer” McHugh

3 Benefits of a Standard Methodology How does a standard methodology Benefit Us? Saves Time and MoneyTimeMoney We will deliver projects successfullydeliver Effective planning will enable us to achieve agreed upon objectivesplanningobjectives Our resources will be coordinatedresources Our risks will be identified and managedrisks We will achieve an agreed upon outcomeachieve an agreed upon outcome

4 What are the Benefits of SDM? 1.State agencies will utilize the same process for managing technology projects within established SDM Lite criteria. 2.Allows Project Steering Committees to understand what phase a particular project is in and also to identify that the goals of the project are being met according to the Project Plan. 3.Improves the ability of a Project Manager to clearly understand the Goals and Objectives of an Executive Sponsor.

5 SDM LITE Characteristics SDM Lite Characteristics Check List Form - helps Technology Managers understand SDM Lite criteria. It answers the question: Does my project qualify as a SDM Lite project? SDM Lite is designed to support projects that are smaller in scope and are lower in risk, complexity, cost or duration then those that meet the criteria of SDM Standard. Projects using SDM Lite can choose to include any of the deliverables that are part of the SDM Standard if that helps manage and improve the project’s outcomes.

6 General Project Characteristics (Requires that all apply, regardless of project type). Estimated implementation costs are less than $400,000 Including hardware, software, and all other resource costs, and Estimated duration (calendar time) is less than or equal to six (6) months, and Limited to one (1) agency (not including DOIT if hosting service is required) and Your product / solution is compliant with the Enterprise-Wide Technical Architecture standards and patterns – or – you have an already approved exception by Technology Review Board for your use of a non-standard platform.

7 Applications Projects, Only (Requires that all apply) Your application requires data from no more than one (1) other application. Your application requires only one (1) dedicated database

8 Operations Projects, Only (Requires that one be checked) Network Projects - Network Refreshes, New WAN/Router Rollouts and Upgrades, New Switch/VLAN Rollouts, CSS Deployments, Firewall Deployments, Upgrades, Patches and/or Service Packs Desktop Projects - Desktop Refreshes, Citrix Server/Client Rollouts, Antivirus, Upgrades, Patches and/or Service Packs Application Hosting Projects - New Server Refreshes (Wintel, Linux, Unix), Upgrade, Patches and/or Service Packs, New Software Hosting, Existing Software Hosting Operations projects that only involve patch upgrades Agency Legacy migration to DOIT hosting. Database Projects - New/Existing Database Rollouts, Database Conversions, Upgrades, Patches and/or Service Packs Directory & Messaging Projects - MS-Exchange Rollouts, Active Directory, Novell Single Sign-on, Server refreshes, upgrade/patches/services packs Projects Mainframe Projects - New Software Releases, Software Maintenance, and Hardware Refresh Data Center Projects - UPS Upgrades, Air Handling, Server Install & Wiring, and All Electrical and Mechanical Upgrades

9 Exception Process If your project does not fit the criteria for an SDM Lite Project and you would like to file an exception with the PMO to use SDM Lite, please complete the SDM Lite Exception Request form. The exception form is located on the SDM Lite portal site under the link titled Reference Materials. The DOIT CIO or his/her designee must approve the exception.

10 7 Phases of SDM Lite Business Issues Business Requirements Design Construction Testing Implementation Post Implementation

11 So what is the Difference between: SDM Standard/ SDM Lite? A number of people have asked me what they think is an important question…

12 Does it Taste great or is it Less Filling?

13 Business Issues Formal - Phase Kick–off Presentation The Business Issues phase it the only phase that requires a formal kick off meeting.  SDM Lite Required Characteristics Form  Project Description  Constraints  Key Assumptions  Team Meeting Objectives  Team Wheel  Roles and Responsibilities  Lessons Learned from other Projects  Guiding Principles

14 Project Management Plan The Project Management Plan should include the following plan components that are updated at then end of each Phase:  Project Organization  Project Description  Project Scope Statement  Project Detailed Schedule  Solution Approach  Cost Benefit Analysis (Standard)  Project Budget Summary  Communication Plan  External Project Considerations  Issues Log  Risk Management Plan  Organizational Standards and Polices  High Level –General Deployment Strategy  Procurement Plan All meetings must be Planned and Documented in the Communication Plan and approved by the Executive Sponsor!

15 PROJECT PROFILE PROJECT PROFILE Project Profile: A DOIT Project Profile is required for all SDM Lite projects that are approved by the PSC to move beyond Phase 1. Business Manager Creates Profile Executive Sponsor Approves Profile PSC Approves Profile DOIT Profile Cmte. Accepts Profile

16 PHASE–END DECISION POINT PRESENTATION Phase-End Decision Point Presentation The Phase-End Decision Point presentation summarizes the team’s completion of the requirements for the phase, its recommendation for the project, and the plan for the next phase. Owner: Technology Manager

17 Business Requirements Phase The purpose of the Business Requirements Phase is to define the system or process in more detail with regard to those things that must happen in order for the new solution to be declared usable by the business.

18 PROCURE 3RD PARTY SERVICES PROCURE 3RD PARTY SERVICES This activity and deliverable is only needed when there is a need to procure outside staffing support through a third party vendor or contractor. There may be circumstances that require the State to procure 3rd party human resource services to own full or partial development and implementation of a custom solution (i.e., staff augmentation).

19 BUSINESS AND TECHNICAL REQUIREMENTS DOCUMENT BUSINESS AND TECHNICAL REQUIREMENTS DOCUMENT Business and Technical Requirements Document – One document includes two Deliverables: Business Requirements Workbook and the Technical Requirements Workbook. This document is co-owned by the Business Requirements Lead and Technology Manager.

20 SOLUTION ALTERNATES DOCUMENT Once the requirements have been fully defined, the project team should provide a list of viable solution alternatives that were considered by the project team. Viable solution alternatives would be those solutions which would satisfy the defined requirements and fit within the defined constraints of the project (i.e. budget constraints, desired timeline constraints). The conclusion at the end of this document is the Recommended Solution. Owner: Business Manager What are the solutions to the Business Problem?

21 Design The purpose of the SDM Lite Design Phase is to translate the business and technical requirements into detailed design components that will later be used to construct the business solution in Phase 4, the Construction Phase. During the Design Phase, there may be 1 design review; the System Design review. Was this part of the design?

22 System Design Document Provide a system design specification that shows how the solution components further decompose into sets of integrated modules and sub-processes. This Activity is a combination of the General and Detail design Activities from SDM Standard. Partition the design into a set of subcomponents that can be more easily managed, assigned, and defined to meet the business and technical requirements of the solution. Owner: Development Lead. What should this System look like?

23 Should we meet with the TRB? If a project involves technology that is compliant with existing EWTA standards and patterns – or – if the project has been granted a prior EWTA exception, no formal DOIT TRB reviews will be necessary, provided that: 1.Any infrastructure, or shrink-wrap or COTS software changes are limited to an “in place” refresh or upgrade with a newer version of the same basic product, or 2.Changes to any existing application through routine maintenance or enhancements do not materially change the architecture of the application and that the application remains EWTA compliant or within the boundaries of any existing EWTA exception, or 3.The introduction of any new or extended infrastructure or a new or enhanced application features or functionality is compliant with EWTA standards and patterns or remains within the boundaries of any existing EWTA exception.

24 PHASE-END DECISION POINT MEETING PHASE-END DECISION POINT MEETING Optional in SDM Lite! The PSC and the Technology Manager decide if a Meeting is needed or not. The PSC should be sent a project Stautus Report and any other neccesary information according to the Communication Plan within the Project Management Plan.

25 Construction Phase The purpose of the Construction Phase is to translate the business requirements, technical requirements, and detailed design components into functioning software modules, and supporting test and training artifacts.

26 Deliverables no longer Required in SDM Lite! Conduct the Phase Kick-off Meeting Environment Migration Checklist * Back-out and Recovery Plan Disaster Recovery Assessment (If needed get er done) LC Update and/or Create Training Plan Phase-End Decision Point Presentation Smaller projects by nature result in less work in Construction Phase! * = Required for when DOIT Hosting Services are used – recommend for agency-hosted projects.

27 TESTING The purpose of the SDM Lite Testing phase is to prove that the developed system satisfies the requirements defined in the Business and Technical Requirements Document. Several types of tests will be conducted in this phase.

28 Minor changes in Testing Phase Testing requires a Phase-End Decision Point meeting Eliminated Deliverable 1. Conduct the Phase Kick-off Meeting Combined Form 1. Integration Test Case Description 2. System Test Case Description 3. UAT Test Case Description 4. Performance Test Case Description 5. Regression Testing

29 Implementation The purpose of the SDM Lite Implementation Phase is to introduce the solution to the business users in the selected deployment sites. The Implementation Phase allows for pilot deployments. Typical deployment strategies are either a “Big-Bang” deployment or a “Phased-Based” deployment.

30 Deliverables no longer Required in SDM Lite! Conduct the Phase Kick-off Meeting Complete the Environment Migration Checklists End User Training Phase-End Decision Point Presentation

31 Post-Implementation The purpose of the SDM Lite Post-Implementation Phase is to ensure a smooth transition to the appropriate teams who will provide the ongoing management of the solution. If there are multiple deployments, many of the activities within this phase will be executed for each deployment.

32 TRANSITION THE SOLUTION TO PRODUCTION SUPPORT TRANSITION THE SOLUTION TO PRODUCTION SUPPORT The purpose of this activity is to ensure that the solution is now accepted as a part of everyday business and will be supported as a matter of doing business.

33 SHUTDOWN THE PROJECT SHUTDOWN THE PROJECT The purpose of this activity is to formally shutdown of the project. Project Summary: Create an overall project summary to include phase-based planned to actual schedule comparisons, planned to actual budget comparisons, and lessons learned by the project team. This project summary should be distributed with the formal project closeout communication.

34 Project Reviews Projects that qualify under the SDM Lite criteria are not subject to standard project review meetings at DOIT! Inventories still need to be maintained. The CIO or PMO have the right to call for a review of any Technology Project if they deem it to be necessary.

35 Thank You! The SDM Lite Team! Jim A.K.A. “Popeye” Rutushni Team Leader Ron A.K. A. ‘”The Politician” San Angelo Len A.K.A. “Jarhead” Smith Jeanne A.K.A. “The Doctor” Lee Keith A.K.A. “ The Farmer” McHugh

36


Download ppt "System Development Methodology “Lite”. The SDM Lite Team! Who would have ever thought this would be a good team? Jim A.K.A. “Popeye” Rutushni Team Leader."

Similar presentations


Ads by Google