Presentation is loading. Please wait.

Presentation is loading. Please wait.

Lahmeyer International 2013 Lahmeyer International GmbH Engineering and Consulting Services Energy Division; Business Unit Renewables and Economics Initial.

Similar presentations


Presentation on theme: "Lahmeyer International 2013 Lahmeyer International GmbH Engineering and Consulting Services Energy Division; Business Unit Renewables and Economics Initial."— Presentation transcript:

1 Lahmeyer International 2013 Lahmeyer International GmbH Engineering and Consulting Services Energy Division; Business Unit Renewables and Economics Initial Performance History - O&M Lessons Learned Kuno Schallenberg Kuno.Schallenberg@de.lahmeyer.com +49 6101 55 1886 26 August 2013

2 Lahmeyer International 2013 Solar Tower Technology 2 Brief facts on the current status: 3 operational projects considered commercial: – PS-10 (10 MW) – PS-20 (20 MW), and – Gemasolar (20 MW) Large commercial projects under construction (e.g. Ivanpah) Some pilot and demonstration experiences around the world (e.g. Solar One, Solar Two, Themis, etc.)

3 Lahmeyer International 2013 Tower Project Focus: Gemasolar (Spain) 3 Source: Torresol

4 Lahmeyer International 2013 Gemasolar: Key Data 4 Source: Torresol

5 Lahmeyer International 2013 Gemasolar: Layout 5 Decoupled System Source: Torresol

6 Lahmeyer International 2013 Gemasolar: Plant behaviour (full summer week) 6 Meinel DNI (W/m²) Actual DNI (W/m²) Heliostats focusing (u) Receiver Power (MWt) Storage Level (%) Gas use (kg/s) Net Output (MWe) Source: Torresol

7 Lahmeyer International 2013 Gemasolar: Operation - Preliminary Results 7 Plant is still on ramp-up period (2 nd operational year) Performance exceeds expectations on clear sky days but is lower than expected on cloudy days Plant can operate continuously 24 hours/day (mainly summer) Fine control of solar field and receiver temperature achieved Cleanness factor of the solar field exceeds 95% Storage tanks loose around 1°C/day in average Water consumption per year rounds 400,000 m³

8 Lahmeyer International 2013 Gemasolar: Operation Event – Frozen Receiver 8 Event: Frozen salts on receiver tubes Cause: operation exceeding boundary conditions (high winds) Solution: gradual heating of the tubes using the solar field Result: salts were melted and tubes freed Consecuences: no mechanical or structural damages to the receiver Source: Torresol

9 Lahmeyer International 2013 Gemasolar: Maintenance 9 Source: Torresol

10 Lahmeyer International 2013 Gemasolar: Maintenance – Key Facts 10 Typical maintenance activities: preventive, predictive and corrective Major emphasis on predictive maintenance, especially on non-conventional equipment (e.g. receiver, salt pumps, etc.) Annual plant inspection (scheduled corrective maintenance) with a duration of 3-4 weeks Turbine has shown no signs of degradation, performing substantially better than in other CSP plants No perceived degradation on Receiver No special maintenance activities on salt system (no corrosion noted) Exceptions: valves (salt system) and kettle

11 Lahmeyer International 2013 Gemasolar: O&M Personnel 11 Operation (on site): – Around 20 employees which include supervisors, EHS, process engineers and operators, divided into 5 shifts Maintenance: – Around 30 employees which include supervisors, electromechanical technicians, chemical engineer and cleaning crews

12 Lahmeyer International 2013 Gemasolar: O&M Costs 12

13 Lahmeyer International 2013 Trough Technology 13 Brief facts on the current status: Around 3 GW installed worldwide Large commercial projects still announced Almost 30 years of operational track record (SEGS I built on 1984) Relatively mature O&M experience

14 Lahmeyer International 2013 Trough Project Focus: Typical 50 MW installation with TES (Spain) 14 Source: Torresol

15 Lahmeyer International 2013 Trough Case Study: Key Data 15 Source: Torresol

16 Lahmeyer International 2013 Trough Case Study: Typical Plant Layout 16 Source: Torresol

17 Lahmeyer International 2013 Trough Case Study: Plant behaviour (clear and cloudy days) 17 Source: Torresol Stored EnergyGas HeaterTurbine Output

18 Lahmeyer International 2013 Trough Case Study: O&M Results - Spain 18 Performance results are not similar/homogeneous within the plants installed recently (last 5 years) in Spain Some plants register 15 to 20% higher annual performance compared to expected values Experience from SEGS plants allowed optimization of O&M e.g. high performance, effective maintenance (predictive) and cost reduction Major O&M incidents relate to HTF leakages (e.g. ball joints, flexible hoses), HTF pumps failure, HTF filtration into water/steam cycle, broken absorber tubes There are no major incidents with the operation of the TES reported

19 Lahmeyer International 2013 Conclusions & Lessons learned 19 Operation with molten salt systems as HTF is more delicate on changing weather conditions (e.g. cloud passages) Decoupled systems with TES allow reduction and/or elimination of weather disturbances on the solar field (e.g. cloud passages), allowing a better operation of the turbine No special events detected on the operation of molten salt storage systems O&M cost reductions on existing plants are very unlikely without losing plant performance Increasing project size or multiproject development might be the only way to reduce O&M costs CSP integration to existing thermal power plants represent a significant reduction on O&M costs for the solar part (e.g. almost no additional labor)

20 Lahmeyer International 2013 Thank you for your Attention Questions? 20


Download ppt "Lahmeyer International 2013 Lahmeyer International GmbH Engineering and Consulting Services Energy Division; Business Unit Renewables and Economics Initial."

Similar presentations


Ads by Google