CERTIFICATE 4 IN BUILDING BCGBC4004A. General Notes  Site clearing billed in m 2 & includes trees ≤0.5 m girth measured 0.5 m above ground  Tree removal.

Similar presentations


Presentation on theme: "CERTIFICATE 4 IN BUILDING BCGBC4004A. General Notes  Site clearing billed in m 2 & includes trees ≤0.5 m girth measured 0.5 m above ground  Tree removal."— Presentation transcript:

1 CERTIFICATE 4 IN BUILDING BCGBC4004A

2

3 General Notes  Site clearing billed in m 2 & includes trees ≤0.5 m girth measured 0.5 m above ground  Tree removal billed starting at >0.5 m ≥1m girth and every 0.5 m girth thereafter  Surface excavation is billed in m³ with the area stated in m 2  Differing widths of trench excavation may be billed as one item starting at ≤ 1 m deep and 1 m increments thereafter  Pier holes are billed in m with the volume stated in m 3

4

5

6 Page 19&20

7

8

9 Page 16

10 Y=3.4 X=0.3 X=3.1 Y=3.4 OR 16.00 + X/Y x rise =16.00 + 0.3/3.4 x rise =16.03 Page 17

11

12 Page 18

13 Page 22&23 A B 12 43 5 6 7

14

15


Download ppt "CERTIFICATE 4 IN BUILDING BCGBC4004A. General Notes  Site clearing billed in m 2 & includes trees ≤0.5 m girth measured 0.5 m above ground  Tree removal."