Presentation Outline 1.Building Overview 2.BIM Ex Plan Overview 3.BIM Goals Overview a)BIM Goals b)BIM Uses 4.BIM Goal/Use Analysis a)Process Maps b)Information Exchange 5.Project Deliverables a)Scheduling and Formats 6.Next Step
3
General Building Information 1.Owner 1.The Pennsylvania State University 2.Description 1.276,000 SF Research Facility housing the Material and Life Sciences 2.LEED Certification 3.Location a)PSU University Park Campus, University Park, PA 4.Total Cost a)Approximately $215 million 5.Unique Features 1.150-foot Cantilever 2.Vivarium Space 3.Quiet Labs 4.Nano-Clean Rooms Building Overview
4
Integrative Project Delivery Mutual agreement/contract Need proper foundation BIM Processes Information Exchange Collaboration Techniques Project Deliverables Execution of Group BIM Goals PSU BIM Ex Planning Guide- CIC Research Organization: Goal – Use – Process BIM GOALS and USES ANALYSIS added BIM Execution Plan Overview
5
BIM Goals Overview
6
BIM Uses
7
BIM Goal-Use-Process Analysis Example Life Cycle Cost/Value Engineering Utilize engineering design to select the best integrated design that provides MSC with life cycle and value effective building solutions
8
CM Life Cycle Cost Overview Overview of Goal Produce a more efficient building through integrated design with a lower overall cost to the owner Why Life Cycle Cost? Value Engineering to produce a lower overall cost Upfront Cost vs. Life Cycle Cost Construction Management Contribution Upfront Cost Estimation Current Design and Redesign Value Engineering Input BIM Uses Quantity Take-Offs Autodesk QTO Autodesk Revit
9
CM Life Cycle Cost Overview
10
Structural Contribution Material and Construction Costs Materials, Labor, Schedule BIM USES 1.Existing Conditions Modeling 2.Structural Analysis/Modeling 3.Building Systems Analysis
12
Mechanical Contribution Up-front vs. Operational Cost Savings System Performance Comparisons Integrated Iterations BIM USES 1.Existing Conditions Modeling 2.Mechanical Analysis/Modeling 3.Building Systems Analysis 4.Design Reviews
14
Lighting/Electrical Contribution Material Costs Fixture Control, Glazing material BIM USES 1.Existing Conditions Modeling 2.Building Systems Analysis
16
Project Deliverables INFORMATION EXCHANGE FILE SENDER FILE RECIEVER FREQUENCYDUE DATE MODEL FILE MODEL SOFTWARE NATIVE FILE TYPE FILE EXCHANGE TYPE MEP COORDINATION MODEL TEAM MONTHLYAPRIL.rvt.nwdPERIODICWEEKLY.rvt ENERGY ANALYSIS REPORTS ME,LE WEEKLYAPRIL.trc.heaPERIODICWEEKLY.trc,.hea STRUCTURAL ANALYSIS REPORTS SECMWEEKLYFEB.EDPPERIODICWEEKLY.EDP DESIGN PROGRESS TEAM WEEKLYCONT..doc.xlsPERIODICWEEKLY.doc.xls BIM SUBMITTAL ITEM STAGEAPPROX. DUE DATEFORMATNOTES FAÇADE MODEL DD,CDApril 2011REVIT ENERGY ANALYSIS REPORT DD,CDApril 2011TRACE DAYLIGHTING REPORT DD,CDJanuary-February 2011DAYSIM, AGi32 STRUCTURAL REPORTS DD,CDJanuary-February 2011ETABS COST ESTIMATION DD,CDFebruary-March 2011EXCEL 4D MODELCDApril 2011NAVISWORKS 3D COLLISION MODEL CDApril 2011NAVISWORKS LIGHTING DESIGN MODEL DD,CDApril 2011AGi32, 3ds Max Design
17
Next Step Revision of Alternative Redesigns Incorporation of BimEx Plan Semester Proposal
18
Thank you for listening Can we answer any questions?
19
Appendices
20
BIM GOALDESCRIPTIONCOMPLETE Life Cycle Cost/ Value Engineer All Design Decisions Utilize engineering design to select the best integrated design that provides MSC with life cycle and value effective building solutions no Optimize Building PerformanceUse integrated design to enhance the operation of all building systemsno Eliminate Field Conflicts Collaboratively design the plenum to best take advantage of the vertical dimension of the ceiling plenum no Improve Energy EfficiencyCreate energy savings based on the existing design modelno Improve Daylighting Optimize the building’s daylighting system with respect to cost and increased envelope loads. no Optimize Sequence and ScheduleCreate an efficient sequence of trades to properly construct a redesigned buildingno
21
BIM USECOMPANY NUMBER OF TOTAL STAFF FOR BIM USE ESTIMATED WORKER HOURS LEAD CONTACT SITE ANALYSISBIMception2TBD Chris Russell Alex Stough EXISTING CONDITIONS MODELING BIMception4TBD Chris Russell Alex Stough Steve Pfund Tom Villacampa DESIGN AUTHORINGBIMception3TBD Chris Russell Alex Stough Steve Pfund DESIGN REVIEWSBIMception4TBD Chris Russell Alex Stough Steve Pfund Tom Villacampa STRUCTURAL ANALYSISBIMception1TBDSteve Pfund LIGHTING ANALYSISBIMception1TBDChris Russell ENERGY ANALYSISBIMception1TBDAlex Stough MECHANICAL ANALYSISBIMception1TBDAlex Stough 4D MODELING (DESIGN)BIMception1TBDTom Villacampa COST ESTIMATION (DESIGN) BIMception1TBDTom Villacampa 3D COORDINATIONBIMception4TBD Chris Russell Alex Stough Steve Pfund Tom Villacampa 4D MODELING (CONSTRUCT) BIMception1TBDTom Villacampa COST ESTIMATION (CONSTRUCT) BIMception1TBDTom Villacampa BUILDING SYSTEM ANALYSIS BIMception3TBD Chris Russell Alex Stough Steve Pfund COST ESTIMATION (OPERATE) BIMception2TBD Alex Stough Tom Villacampa
22
MEETING TYPEPHASEFREQUENCYPARTICIPANTSLOCATION 3D MEP COORDINATIONCONSTRUCTIONMONTHLYALLBIM ROOM DESIGN REVIEWDESIGNWEEKLYALLBIM ROOM COST ANALYSISDESIGNTRI-WEEKLYALLBIM ROOM ENERGY ANALYSISDESIGNTRI-WEEKLYALLBIM ROOM INFORMATION EXCHANGE FILE SENDER FILE RECIEVER FREQUENCYDUE DATE MODEL FILE MODEL SOFTWARE NATIVE FILE TYPE FILE EXCHANGE TYPE MEP COORDINATION MODEL TEAM MONTHLYAPRIL.rvt.nwdPERIODICWEEKLY.rvt ENERGY ANALYSIS REPORTS ME,LE WEEKLYAPRIL.trc.heaPERIODICWEEKLY.trc,.hea STRUCTURAL ANALYSIS REPORTS SECMWEEKLYFEB.EDPPERIODICWEEKLY.EDP DESIGN PROGRESS TEAM WEEKLYCONT..doc.xlsPERIODICWEEKLY.doc.xls
23
BIM USE DISCIPLINE (if applicable) SOFTWAREVERSION DESIGN AUTHORINGALLRevit2010 ENERGY ANALYSISMEPTrane Trace, Excel, Daysim 3D COORDINATIONCM, MECHNavisWorks Manage2011 4D MODELINGCMNavisWorks Manage2011 STRUCTURAL ANALYSISSTRUCTETABS9 LIGHTING ANALYSISL/EAGi32, 3ds Max Design, AutoCAD BIM SUBMITTAL ITEM STAGEAPPROX. DUE DATEFORMATNOTES FAÇADE MODELDD,CDApril 2011REVIT ENERGY ANALYSIS REPORT DD,CDApril 2011TRACE DAYLIGHTING REPORT DD,CDJanuary-February 2011DAYSIM, AGi32 STRUCTURAL REPORTS DD,CDJanuary-February 2011ETABS COST ESTIMATION DD,CDFebruary-March 2011EXCEL 4D MODELCDApril 2011NAVISWORKS 3D COLLISION MODEL CDApril 2011NAVISWORKS LIGHTING DESIGN MODEL DD,CDApril 2011AGi32, 3ds Max Design