BURIED FLEXIBLE PIPELINES BURIED FLEXIBLE PIPELINES The Design Process- Boundary Conditions Design Fundamentals-AS2566.1 Materials Installation AS 2566.2.

Similar presentations


Presentation on theme: "BURIED FLEXIBLE PIPELINES BURIED FLEXIBLE PIPELINES The Design Process- Boundary Conditions Design Fundamentals-AS2566.1 Materials Installation AS 2566.2."— Presentation transcript:

1 BURIED FLEXIBLE PIPELINES BURIED FLEXIBLE PIPELINES The Design Process- Boundary Conditions Design Fundamentals-AS Materials Installation AS Tips, Tricks & Traps Presented by Geoffrey D Stone C.Eng FIMechE; CP Eng FIEAust RPEQ Principal Blenray Pty Ltd ( Design Detail & Development)

2 THE DESIGN PROCESS Boundary Conditions Soils & Soil Data Trench Width & Depth Structural Response to Loading Trench Details Stiffness Thrust Blocks Structural Interfaces Water Table Design Loads Trench & Embankment Fill Superimposed Live Loads Other Superimposed Loads

3 Soils & Soils Data Native Soil –Classify –Modulus Bedding –Type Embedment –Material –Compaction –Geo-textile –Water Table Backfill –Type –Compaction Piles Testing –Field –Laboratory

4

5 Trench Width & Depth AS Minimum Embedment or Embankment Shape of trench

6 Trench Dimensions

7 Structural Response to Loading

8 Stiffness AS year values of pipe stiffness suitable for good soils 50 year values of pipe stiffness should be used for poor soils, uncontrolled installations or other higher risk applications

9 Stiffness AS

10 Thrust Blocks Not required for fully welded systems as in ABS, PP, PVC-U, PB or PE Required for rubber ring systems as used for DICL, MSCL, GRP & PVC-U/O/M Design basis –Steady state pressure –Unsteady state pressure spikes –Hydrostatic test pressure

11 Structures Interfaces Differential Settlement Soil swelling Water Retaining Shear Loading Thermal Loading Chaffing Water seal in concrete

12 Water Table Water hydrostatic level applies load onto pipe-refer AS2566 Rising water applies uneven load onto pipe and the pipe may buckle or exceed its strain limit Water may cause flotation of empty pipe and special embedment may be necessary High water table increases construction difficulty –Safety –Dewatering –Quality

13 Loading Design loads due to trench & embankment fill External hydrostatic loads Internal pressure Superimposed dead loads Superimposed live loads Other unsustained loads

14 Design Loads due to Trench & Embankment Fill

15 Superimposed Live Loads

16

17 Other Unsustained Loads 1. Specialist Engineering 2. National Codes 3. Local Conditions 4. Risk Likelihood Consequences Responsibility Safeguarding Earthquake Vibration/Shock Differential Settlement Thermal Strain Subsidence Airport runways Railways

18 DESIGN FUNDAMENTALS AS Buried Flexible Pipelines-Design Deflection Strength Internal Pressure Combined Loading Buckling Hoop Stress Ring Bending Strain Creep Temperature Other Considerations

19 Deflection Short term Long term Vertical & Horizontal –Considered equal –Effect of excess side compaction Modulus to use Acceptance criteria Measurement during installation

20 Strength Loads cause strain in pipe wall Ring compression strains << ring bending strains AS predicts maximum tensile ring bending strains A Shape Factor adjusts strain values –True Ellipse Shape Factor D f =3.0 –Δ horizontal 3.0

21 Internal Pressure Steady State Unsteady State –AS Requirements 1.25 –AS 2885 Requirement 1.10 –Other codes requirements

22 Combined Loading Combined external load and internal pressure Re rounding effect

23 Buckling Ovalization Buckling External Pressure No substantial soil support-Timoshenko Substantial soil support –I.D. Moore

24 Hoop Stress Stress in the wall due to pressure Only criteria used for pipe class selection Does not take into account other stresses Basis of the Pipe Class System Relaxes with time for thermoplastic pipes Never Constant

25 Ring Bending Strain Importance of Strain Comparison of allowable strain in materials 1. ABS 1% 2. GRP 0.18 to 0.6 % 3. PE 4.0% 4. PVC-U 1% 5. PVC-M 1% 6. PVC-O 1.3%

26 Creep Variation of Properties in Time Long term loading/Stress relaxation Reverse loading/Stress magnitude Repetitive loading/Fatigue

27 Temperature The design temperature may vary due to:- Ambient diurnal temperature variations Flow rate Fluid temperature range Process conditions Installation ambient temperature Wall thickness

28 Other Considerations Anchor forces Differential Settlement Earthquake Subsidence Testing conditions Corrosion Mass of pipe contents Thermal Strain Local buckling Fatigue Pavement settlement

29 Materials Selection Types Costs Class Characteristics Fittings & Valves Modulus GRP Modulus Thermoplastic Pipes

30 Materials - Types GRP ABS PE PVC-U, PVC-M, PVC-O DICL MSCL

31 Materials Selection Costs – Supply 1.Pipe 2.Fittings 3.Supports Costs – Installation 1.Standard of trades 2.Equipment 3.Jointing 4.Access 5.Testing Costs - Whole of Life 1.Safety 2.Availability 3.Maintenance 4.Energy 5.Risks Costs - Standards 1.Authority 2.Industry 3.Acts

32 Selection of Pipe Class Design Pressure Steady State Design Pressure Unsteady State Vacuum Conditions Industry Application & Environment Soil/Pipe Structure Design Standardization Risk –Likelihood –Consequences –Responsibilit y

33 Typical Material Characteristics

34 Fittings & Valves Valve classes do not meet all pipe classes Injection moulded fittings- Size Limitation Manufactured fittings-Larger Sizes –Tees –Bends Jointing Gaskets Expansion Bellows Saddles Valves –Isolation –Check –Air release –Control

35 Modulus-GRP Pipes Manufacturers establish values by test & calculation Axial & longitudinal modulus differs Values at various temperatures required for design Strain rate changes values Standards such as ISO 14692

36 Modulus-Thermoplastic Pipes Published figures normally are strain rate at 20ºC Value determined by ASTM test –Standard dog bone test specimen –Fixed strain rate Values at various temperatures required for design Strain rate changes values

37 INSTALLATION Trench Excavation Trench Shields Laying & Jointing Embedment & Compaction Thrust Blocks Hydrostatic Testing

38 Trench Excavation Excavator bucket width Excavated depth Soil removal, testing and stockpile Shape of trench Pockets for pipeline projections Thrust block preparation Dewatering Welding machine access Adjacent pipes

39 Trench Shields When to use Remove in stages Affect on compaction Geotextile fabric Over excavation Wide trench

40 Trench Shields

41 Laying and Jointing Join on the bank and lay Lay in trench and join Rubber ring joints PVC- U, PVC-M, PVC-O, GRP, DICL & MSCL Solvent welded joints- ABS, PVC-U & PVC-M Fusion butt weld-PE, PB & PP Electro-fusion couplings-PE Wrapped joints-GRP Welded joints-steel Flanges & Mechanical Joints-All Alignment & Bending Adjacent parallel pipes Crossing Pipelines Removal of temporary pegs and supports

42 Embedment & Compaction Materials Dewatering Bedding Side Support Overlay Migration of fines Pipeline Protection Prevention of floatation Compaction trials Compaction controls Deflection controls Gauging

43 Thrust Blocks

44 Hydro-testing Establish test pressure Test standard Prepare test equipment Prepare ITP’s Prepare test points Source of test water Disposal of test water Selection of test lengths Owner’s witness Records

45 Hydrotest Methods Constant pressure test (No water loss) – DICL, MSCL, GRP & PVC Constant pressure test (water loss) – PE, ABS, PP & PB Pressure decay – PE & PB Pressure rebound- DN ≤ DN315 ABS, PB & PE

46 Tips, Tricks & Traps Design Installation Testing Product quality Completion In Service leaks

47 Tips, Tricks & Traps - Design Design pressure may not include surge Temperature profile not defined Pipeline route/soils not adequately surveyed Consultant expects sub contractor or material supplier to do the detail design Lower pipe class than necessary specified Temporary facilities not designed

48 Tips, Tricks & Traps - Installation Variations from design not engineered Surfaces not cleaned Aged solvent cement Pipe ends bevelled Damaged pipe UV degradation Physical damage Solvent damage to internal surface Use of incorrect solvent Incorrect slings Foreign matter not removed from trench

49 Tips, Tricks & Traps - Installation No detail drawings Insufficient joints for erection Incomplete insertion in joints Inadequate time for welds or lay ups Differential settlement Resources Poor trench conditions Poor native soil Soil properties not measured routinely Inadequate access Water ingress Cleanliness

50 Tips, Tricks & Traps -Testing Lack of planning & procedure Standard provisions not understood Inexperienced testers Test pressure unknown Equipment not isolated Procedure not agreed beforehand Records of test not prepared Person to witness test not available Resources not available –Water supply –Pump –Gauges –Data logger –Temperature instrument –Trained personnel

51 Tips, Tricks & Traps - Product Quality – Inspection or QA Non conformance with drawings Pipe ovality Lining thickness Socket dimensions Surface defects Fabricated fittings –Cracks at weld –Dimensions –Orientation

52 Tips, Tricks & Traps -Completion Resources & budget Site clean up Reinstatement Handover to owner Records Work as Executed Drawings Quality Assurance Sign-Off Certificate of Practical Completion

53 Tips, Tricks & Traps - In Service Leaks & Failures Pipe burst Flanged joints leak Solvent welds leak Rubber ring joints leak Fusion welds leak Fittings Buckling of thin wall pipe Thrust blocks Waterhammer Over pressure Pipe shear Fatigue & vibration

54 Questions 1. Is AS 2566 mandatory? 2. Can AWWA M45 be used? 3. Is FEA a viable alternative? 4. Who designs pipelines Civil, structural or mechanical engineers?