Presentation is loading. Please wait.

Presentation is loading. Please wait.

SEEM 35301 Project Budgeting and Resource Management Budget setting approaches Presenting the budget Project management Slack management Crashing Resource.

Similar presentations


Presentation on theme: "SEEM 35301 Project Budgeting and Resource Management Budget setting approaches Presenting the budget Project management Slack management Crashing Resource."— Presentation transcript:

1 SEEM 35301 Project Budgeting and Resource Management Budget setting approaches Presenting the budget Project management Slack management Crashing Resource levelling Resource allocation

2 SEEM 35302 Introduction  Project Budget specifies the activities and their costs so as to achieve its objective and fulfill all requirements to complete the project.  Three tiers of budgets:  Long-range, organization-level  Midrange, functional unit  Operational, project based.

3 SEEM 35303 Top-down Budgeting Approach Long-range budget is developed by the top management, and then passed to the functional managers and project managers who will develop the functional and operational budgets. Top-down approach to budget preparation: StepOrganizational levelBudget prepared at each step Step Organizational levelBudget prepared at each step 1Top managementStrategic budget based on organizational goals, constraints, and policies 2Functional managementTactical budget for each functional unit 3Project managersDetailed budgets for each project, including the cost of labour, material, subcontracting, overhead, etc.

4 SEEM 35304 Bottom-up budgeting  Project managers prepare his/her budget proposal that supports efficient and on-schedule project execution.  Functional managers prepare the budgets for their units, considering the resources required in each period of time.  To management streamlines and integrates the budgets from the low levels into a strategic long-range organizational budget. Bottom-up approach to budget preparation Step Organization level Budget prepared at each step 1Top managementSetting goals and selection of projects (a framework for budget) 2Project managementDetailed budget proposals for projects including costs of material, labor, subcontracting, etc. 3Functional managementMidrange budget for each functional unit 4Top managementAdjustments and approval of the aggregate long plan budget resulting from the process

5 SEEM 35305 Iterative budgeting  A combination of top-down and bottom-up budgeting

6 SEEM 35306 Presenting the budget zThe budget generated is easier to understand and use if it is presented clearly and concisely.  The following recommendations can be adopted when preparing and presenting a project ’ s project yIncorporate a schedule showing the time that expenditure and revenues (if any) are expected to be realised. yPresent the budget in quantitative, measurable units such as dollars or man-hours. yDefine milestones in terms of achievements of goals and expenditures/revenues. yUse the budget as the baseline for progress monitoring & control. yThe budget should translate short-term objectives into work orders, purchasing orders, etc. yBreakdown the budget to individual units responsible.

7 SEEM 35307 Budget Management  The budget of a project specifies the scheduled expenditures and scheduled revenue as a function of time.  Two approaches are used to manage the project to meet budget constraints:  Slack management -- An approach that utilizes the slacks of activities to meet the organizational budget requirements.  Crashing -- An approach that attempts to shorten an activity duration by adding more resource, so as to achieve a trade-off between cost and time.

8 SEEM 35308 Slack management  Development of the budget of a project includes the derivation of the scheduled expenditures and the scheduled revenue as a function of time, subject to the time constraint and the total investment limit.  The approach of slack management attempts to utilize the slacks of the activities to re-schedule the project, so that the time and monetary constraints are satisfied.

9 SEEM 35309 Slack management  The process of selecting activities to re- schedule the project will follow the following priority:  Non-critical activities that have free slack are the first candidates to be re-scheduled.  Non-critical activities that have total slack are the next candidates to be re-scheduled.  Finally, the critical activities are considered. Overall, our goal is to make the whole project to meet the time constraint while the monetary limit is satisfied.

10 SEEM 353010 Slack management -Example Consider the example project, with the activities, durations and costs given below: ActivityDuration (weeks) Cost ($1,000) A51.5 B33.0 C83.3 D74.2 E75.7 F46.1 G57.2 Total = 31.0

11 SEEM 353011 Slack management We have found that (A,C,F,G) is the critical path, which has a length 22 weeks. The critical activities are A, C, F, and G, while activities B, E, and D have either free or total slack that can be used for budget planning.

12 SEEM 353012 Cash Flow  Let ’ s look at this project ’ s cash flow, assuming that, for budgeting purposes, the cost of each activity is evenly distributed throughout its duration.  In the next two tables, we look at the cash flow scenario for:  Early start schedule – Any activity will be started at its earliest start time. (Table 8-4)  Late start schedule – Any activity will be started at its latest start time. (Table 8-5)

13 SEEM 353013

14 SEEM 353014

15 SEEM 353015 Slack management  Figure 8.1 below depicts the cash flows for the early start and late start schedules.  Figure 8.2 below depicts their cumulative cash flows.

16 SEEM 353016

17 SEEM 353017

18 SEEM 353018 Slack management  From Figure 8-2 we can see that, if the total money allocated to the project is only $4,913 for weeks 1 through 6, then during this period only a late start schedule is feasible.  Also, if the total allocation to the project is increased to $10,398 for the first 6 weeks, then an early start schedule will become feasible.  Any allocation between $4,913 and $10,398 will force a delay of certain non-critical activities.

19 SEEM 353019 Slack management  The approach of slack management is to properly adjust the timing for non-critical activities so that the limit of total monetary allocation is satisfied, while the project is not delayed.  An early start schedule will result in relatively high expenditures in the project ’ s earlier stages, while a late start schedule will result in relatively high expenditures in the project ’ s later stages.

20 SEEM 353020 Risk vs. Capital Commitment Note that the choice between an early and a late start schedule affects the risk level associated with the project ’ s on-time completion.  Using a late start schedule means that all activities are started as late as possible without any slack to buffer against any uncertainty, increasing the probability of delays.  On the other hand, using an early start schedule requires an early commitment of money, which will mean additional cost if interest rate is taken into account.

21 SEEM 353021 Tradeoff Between Cost and Time  The approach of crashing is to reduce the duration of an activity by adding more resource, so as to achieve an optimal trade-off between cost and time.  Normally, for each activity, there is a time-cost curve, which represents the relationship between the time to complete the task and the associated cost.

22 SEEM 353022 Crashing

23 SEEM 353023 Crashing  The normal point gives the cost and the time involved when the task is performed in the normal way without extra resources such as overtime, special materials, or enhanced machine capacities to speed up the processing of the task.  The crash point gives the time and cost when the task is fully expedited; that is, no cost is spared to reduce its duration as much as possible.

24 SEEM 353024 Crashing  The time-cost curve may not be necessarily linear; it can take any form, even being a set of discrete points such as (L1, c1), (L2, c2), …, (Lm, cm).  Nevertheless, as an approximation, we sometimes assume that all intermediate time- cost trade-offs are possible and that they lie on the line segment between the normal point and the crash point (that is, the time-cost curve is approximated as a continuous linear function).  With such an approximation, we need only estimate the normal point and the crash point to build the time-cost curve.

25 SEEM 353025 The Crashing Process (1) Apply CPM to derive the normal schedule of the project, where each activity is performed at its lowest cost and at a normal duration. (2) Identify the critical path, and select the critical activity that is least expensive for crashing. If more than one critical path exist, then a least expensive activity on each path should be selected for crashing so that all the critical paths will be shortened. (3) Apply CPM again to derive the schedule of the project, where each activity is performed at the crashed cost and the crashed time as obtained in step 2 (if it has not been crashed, using its normal cost and time). (4) Repeat Steps 2 and 3, until no more crashing to reduce the current critical path(s) can be performed.

26 SEEM 353026 Crashing - Example

27 SEEM 353027 Crashing Results

28 SEEM 353028 Crashing  The crashing process can continue until a 14-week span is obtained. At this point, two critical paths emerge: A-C-F- G, and B-D-F-G.  The path B-D-F-G can be further shortened by crashing the activity B. But the path A-C-F-G can not be crashed any more.  Thus, the shortest possible duration of the whole project is 14 weeks.

29 SEEM 353029 Crashing – Cost vs. time tradeoff The crashing process has revealed a relationship between the cost and the schedule of the project, which allows us to prepare our budget by considering the possible trade- offs between cost and time.

30 SEEM 353030 Crashing - Example Suppose that a fixed overhead of $500 per week is charged during the project ’ s duration. Further, assume that the project is due in 18 weeks and that a penalty of $1,000 per week is imposed starting from the 19 th week. The problem now is how to generate the best budget for the project so that the overall cost is minimal. Table 8-8 below summarizes the cost-time function.

31 SEEM 353031 Crashing Example – Project costs 10,000 10,500

32 SEEM 353032 Crashing From Table 8-8, we can see that the minimum cost occurs at the project length of 19 weeks. That is, it is more economical to pay for a penalty of $1,000 and an overhead of $500 for a one-week delay than to pay $2,000 to crash the activity F to get an on-time schedule. Based on this result (a 19-week schedule), we can generate the budget for the project (including the costs for all activities and the schedules to pay for these costs). Figure 8-4 below graphically depicts the different cost components and the total cost as a function of its duration. Again, we can see that the 19-week schedule is the one with the lowest total cost.

33 SEEM 353033 Crashing

34 SEEM 353034 Resource Management z Resource leveling subject to project due date constraints z Resource allocation subject to resource availability constraints

35 SEEM 353035 Resource Management  Depletable resources -- Resources that are used up over time (e.g., a lump sum of money, raw materials, … etc.)  Renewable resources -- Resources that are available at the same level every time period (e.g., people, machines, … etc.) zEarlier, we mainly deal with budgeting and planning of depletable resources. Here we will consider the resource allocation problem with renewable resources. zResource allocation for a project concerns with the trade-off between the cost of using resources, and the project schedule.

36 SEEM 353036 Example zConsider the example project as given in the Table below:

37 SEEM 353037 Renewable Resource Usage  Consider the “ renewable ” resource (labor) used to perform the activities of the project. Table 9-1 gives the resource requirements: 196

38 SEEM 353038 Tracking Resource Usage zGantt Chart -- A graph that depicts the activities performed on the vertical axis and their corresponding durations on the horizontal axis (a technique developed by Henry L. Gantt). zThe Gantt chart for the early start schedule of the example project is shown in Figure 9-2a. The corresponding resource requirements are given in Figure 9-2b.

39 SEEM 353039 Gantt Chart and Resource Profile - Early Start Schedule

40 SEEM 353040 Fluctuation in Resource Usage Level The early schedule requires a high level of resource at the early stages. The requirement during the first 3 weeks is 17/5=3.4 person-days per day. The highest resource requirement is 17 person days per week, while the lowest resource requirement is 3 person days per week. The fluctuation is 14 person-days.

41 SEEM 353041 Gantt Chart and Resource Profile - Late Start Schedule

42 SEEM 353042 Resource Usage Levels – Late Start Schedule The late schedule moves the high level of resource requirement from weeks 1 through 3 to weeks 3 through 5. The highest resource requirement is 12 person days per week, while the lowest resource requirement is 3 person days per week. The fluctuation is 9 person days.

43 SEEM 353043 Resource levelling zResource levelling is defined as the re-allocation of total or free slack in activities so as to minimize the fluctuations in the resource requirement profile. zWhen the total resource requirement for the project is fixed, a minimum fluctuation tends to reduce the peak resource requirement, and thus leads to more balanced requirements over all periods. zFor renewable resource, a balanced resource requirement is the desirable solution. yFor labor, this means a fairer working load distribution; This also means a lower costs for hire, fire, and training. yFor materials, this means less effort in material planning and control, and also lower cost in inventory.

44 SEEM 353044 General Resource Levelling Procedure zCalculate the average number of resource-days per period required by the project. (In the example, a total of 196 person-days are required. The average = 196/22 = 8.9, or about 9 person-days per week, since the project duration = 22 weeks). zWith reference to the early start schedule and non- critical activities, gradually delay activities one at a time, starting with those activities that have the largest free slack. zSelect the schedule that minimizes the resource fluctuation (which has daily resource requirements close to the calculated average).

45 SEEM 353045 Resource levelling - Example Apply the procedure of resource-levelling to the example project. Recall the results we have obtained by project scheduling (see the table below). We can see that activity E has the largest free slack (6 weeks).

46 SEEM 353046 Resource levelling - Example zThe early start schedule is shown below. zThe first step is to delay the start of E by 3 weeks until the end of activity B. This reduces the resource requirements from weeks 1 through 3 by 5 units. The resource profile is shown in the Table next.

47 SEEM 353047 Resource levelling - Example zThe profile has a maximum of 13 person-days per week. Since the maximum occurs in weeks 4 and 5 and activity E can be delayed further, consider a schedule E starts after A is finished (after week 5). The resource requirement profile in this case is shown in the Table next.

48 SEEM 353048 Resource levelling - Example zNow the profile has a maximum of 12 person-days per week. The minimum is still 3, given a fluctuation of 12-3=9.

49 SEEM 353049 Resource levelling - Example zThe next candidate for adjustment is activity B, with a free slack of 2 weeks. However, delaying B by 1 or 2 weeks will only increase the load in weeks 4 and 5, resulting in a net gain zero. zTherefore, we proceed to the last activity with a positive free slack - activity D, which is scheduled to start at week 5. Delaying D by 1 week results in the following resource requirement profile.

50 SEEM 353050 Resource levelling – Example Minimum Fluctuation Schedule zNow the corresponding schedule is shown in Figure 9-4. Note now the fluctuation of person-days is 12-5 = 7, which is smaller than other schedules including the early start and the late start schedules.

51 SEEM 353051 Resource leveling subject to project due date constraints zRemarks yFor small projects, the foregoing procedure works well but still cannot guarantee to find the optimal profile (solution). yTo improve on the results, a similar procedure can be activated by starting with the late start schedule and checking the effect of moving activities with slack back to the start of the project. yTo obtain better solutions, a number of iterations (a loop of forward procedure and backward procedure) may be used.

52 SEEM 353052 §12.2 Resource leveling subject to project due date constraints

53 SEEM 353053 Resource leve/ling vs. Resource Limits zIn some projects, it may be necessary to keep the maximum resource consumption below a certain ceiling (constraint) rather than merely leveling the resources (goal). zIf a feasible schedule cannot be found by re-scheduling the non-critical activities, one or more critical activities would have to be re-scheduled to reduce the daily resource consumption to within limits.

54 SEEM 353054 Resource allocation subject to resource availability constraints zMany projects are subject to resource availability constraints. zFor the example, if 17 or more person-days are available every week, then an early start schedule can be used to complete the project within 22 weeks. zIf 12 person-days are available, then the project can still be completed in 22 weeks (by a late start schedule). zHowever, if the available person-days are 11 or less, then the completion of the project may have to be delayed. zHow to minimize the project delay subject to the resource availability constraints is the concern of optimal resource allocation.

55 SEEM 353055 Resource allocation subject to resource availability constraints zTo avoid a project delay in a low resource availability, the following techniques may be considered: (1) Performing activities at a lower rate using available resource levels. Assume 11 person-days are available for A and B per week, and the critical activity A requires 8 person-days while the non-critical activity B requires normally 4 person-days. Let A use 8 person-days, and then only 3 person-days left for B. Since B needs (3 weeks) x (4 person-days per week) = 12 person-days in total, it may be possible to schedule B to have (3 person-days a week) for 4 weeks, which also equals 12 person-days in total.

56 SEEM 353056 Resource allocation subject to resource availability constraints (2) Activity splitting It might be possible to split some activities into sub- activities without altering the original precedence relations. Then, complete some sub-activities first, and delay other sub-activities to later times when sufficient resource available. (3) Modifying the network Consider whether some precedence relations can be modified, so that conflicts in using resources are resolved. (4) Use of alternative resource Consider subcontractors. zIf the above techniques cannot solve the problem, then one or more critical activities will have to be delayed, causing a delay in the completion of the project.

57 SEEM 353057 Resource allocation subject to resource availability constraints zTo illustrate, consider the example project under a resource constraint of 11 person-days per week. Because A requires 8 person days, activity B can start only when A finishes. The precedence relations force delays of D, as well as F and G. The new solution is shown below.

58 SEEM 353058 Resource allocation subject to resource availability constraints zIt is interesting to note that when the maximum available resource reduces from 11 to 10 would not change the solution above. zIf the maximum available resource further reduces to 9, the new solution is shown below (where C, D and E cannot be concurrently performed since they require a total of 10 person-days).

59 SEEM 353059 Resource Utilization zResource utilization is defined as the proportion of availability that a resource is used. zFor instance, in the example project, if 12 person-days are available each week and the total duration of the project is 22 weeks, then a total of 12 x 22 = 254 person-days are available. But only 196 person-days are used for the project, thus the resource utilization in this example is 196/254 = 0.74 = 74 %. zResource leveling and resource allocation techniques can be used to achieve a higher level of resource utilization.

60 SEEM 353060 Multiple Resources zThe analysis of resource allocation becomes much more complicated when several types of resources are used, the number of activities is large, and several projects compete for the same resources. zIn real-life applications, the problem is usually solved with heuristics, using priority rules to make the allocations among activities.

61 SEEM 353061 Resource allocation heuristic z(1) First, a simple CPM analysis is used, assuming unlimited resource availability. z(2) Then, a check is made to see if the schedule generated is infeasible (the schedule is infeasible if its resource requirement exceeds its availability at any point of time). z(3) Infeasibilities are addressed one at a time, starting with the first activity in project network, and making a forward pass toward the last. z(4) A priority measure is calculated for each activity competing for the same resource. The activity with the lowest priority is delayed until sufficient resources become available. z(5) The steps (3)-(4) above are repeated, until all infeasibilities are resolved.

62 SEEM 353062 Priority rules for resource allocation In the procedure above, a very important operation is the use of priority rules to determine the activities that should be delayed. How to design the priority rules depend on the situations and the experience and judgement of the decision maker.

63 SEEM 353063 Some common priority rules for resource allocation zActivity with the smallest slack. zActivity with minimum late finish time (as determined by CPM analysis). ygives high priority to activities that should start early in the project. zActivity that requires the greatest number of resource units. ygives the highest priority to the activity that requires the maximum use of resource. zActivity that requires the smallest number of resource units. zShortest activities. zLongest activities. zHybrid : weighted sum of other priorities.

64 SEEM 353064 Summary zProject Management ySlack management yCrashing (Time vs. Cost tradeoff) yResource levelling yResource allocation


Download ppt "SEEM 35301 Project Budgeting and Resource Management Budget setting approaches Presenting the budget Project management Slack management Crashing Resource."

Similar presentations


Ads by Google