6 th Street Water Main And Street Reconstruction 2013.

Similar presentations


Presentation on theme: "6 th Street Water Main And Street Reconstruction 2013."— Presentation transcript:

1 6 th Street Water Main And Street Reconstruction 2013

2 th Street Reconstruction Contacts City of Jesup – Chris Even, Public Works City of Jesup – Chris Even, Public Works Dick Quackenbush, Mayor Dick Quackenbush, Mayor LeAnn Even, City Clerk LeAnn Even, City Clerk AECOM – Mark Durbahn, Engineer AECOM – Mark Durbahn, Engineer Questions or concerns, please call city hall at Questions or concerns, please call city hall at

3 th Street Reconstruction What’s Included Remove and replace existing 6 th Street surface from Hawley Street to Prospect Street with new 8” concrete. Remove and replace existing 6 th Street surface from Hawley Street to Prospect Street with new 8” concrete. Widen 6 th Street from 27 feet to 40 feet from Hawley Street to Prospect Street. Widen 6 th Street from 27 feet to 40 feet from Hawley Street to Prospect Street. Install new 8” water main on 6 th Street from Hawley Street to Church Street. Install new 8” water main on 6 th Street from Hawley Street to Church Street. Install new storm sewer intakes at 6 th Street and Hawley Street intersection Install new storm sewer intakes at 6 th Street and Hawley Street intersection

4 th Street Reconstruction What’s Included Connect water customers to new larger mains on 6 th Street from Hawley Street to th Street and on Hawley Street from 5 th Street to 7 th Street. Connect water customers to new larger mains on 6 th Street from Hawley Street to th Street and on Hawley Street from 5 th Street to 7 th Street. Install new sidewalks and driveway approaches. Install new sidewalks and driveway approaches. Install sump pump connections to subdrain for each residence. Install sump pump connections to subdrain for each residence.

5 th Street Reconstruction What’s Included Relocate utility poles on east side of 6 th Street further away from the street Relocate utility poles on east side of 6 th Street further away from the street Remove four trees in city parking on west side of 6 th Street. Remove four trees in city parking on west side of 6 th Street. Temporarily relocate mail boxes. Temporarily relocate mail boxes. Hydro-seed disturbed areas Hydro-seed disturbed areas

6 th Street Reconstruction Provided by AECOM

7 th Street Reconstruction Provided by AECOM

8 th Street Reconstruction Provided by AECOM

9 th Street Reconstruction Provided by AECOM

10 th Street Reconstruction Provided by AECOM

11 th Street Reconstruction Provided by AECOM

12 6 th Street Reconstruction Schedule February 26 – Bid Opening February 26 – Bid Opening March 5 – Award Contract March 5 – Award Contract April/May – Anticipated Start Date April/May – Anticipated Start Date May 22 – 1 st Day to Close Prospect Street May 22 – 1 st Day to Close Prospect Street August 9 – Substantial Completion Date August 9 – Substantial Completion Date September 30 – Final Completion Date September 30 – Final Completion Date

13 th Street Reconstruction Detour South to North: 6 th Street to 6 th Street to Douglas Street to Douglas Street to Main Street to Main Street to County V62 County V62 North to South: County V62 to County V62 to Main Street to Main Street to Douglas Street to Douglas Street to 6 th Street 6 th Street

14 th Street Reconstruction Access 6 th Street Water Main Construction 6th Street closed to through traffic, open to local traffic 6th Street closed to through traffic, open to local traffic Driveways temporarily unavailable Driveways temporarily unavailable 6 th Street Road Construction: 6th Street closed to all traffic 6th Street closed to all traffic Alleys available Alleys available Temporary drive constructed west side from Hawley to th St. Temporary drive constructed west side from Hawley to th St.

15 th Street Reconstruction Access Sidewalk & Driveway Construction 6 th Street closed to through traffic, open to local traffic 6 th Street closed to through traffic, open to local traffic Temporary drive removed Temporary drive removed Parking available on street Parking available on street

16 th Street Reconstruction Subdrain Connections What’s Allowed: –Sump pumps, buried drainage tiles What’s Not Allowed: –Downspouts, surface drain Provided by AECOM

17 6 th Street Reconstruction Temporary Easements 5 to 15 feet across front yard 5 to 15 feet across front yard All improvements within city right of way All improvements within city right of way Water service connection, sidewalk and driveway construction, ingress/egress Water service connection, sidewalk and driveway construction, ingress/egress Terminate upon completion of project Terminate upon completion of project

18 6 th Street Reconstruction Questions or Comments?

19 6 th Street Reconstruction Chris Even City Hall Phone: City Hall Phone: Cell Phone: Cell Phone: Also keep up to date on the city’s website: Also keep up to date on the city’s website: –Look under the “News” Tab


Download ppt "6 th Street Water Main And Street Reconstruction 2013."

Similar presentations