1 ENTSO-E Transparency Stakeholder Expert Group Meeting 2 28 February 2013

2 2 Agenda 10:30 – 10:40Welcome and Introduction Alain Taccoen WGMIT Convenor 10:40 – 10:50Terms of Reference Approval Peter Campbell ENTSO-E Transparency Advisor 10:50 – 11:20 Draft Manual of Procedures – overview, scope, aims & readership Andy Spiceley IT Project manager 11:20 – 12:30 Comments on detailed descriptions - Load, Generation Alain Taccoen WGMIT Convenor 12:30 – 13:30Lunch 13:30 – 14:30 Comments on detailed descriptions continued… Transmission, Balancing Alain Taccoen WGMIT Convenor 14:30 – 14:50 Feedback on data provider technical & operational criteria and Local Project Monitoring Andy Spiceley/Dalius Sulga IT Project manager/Platform senior advisor 14:50 – 15:05 Coffee Break 15:05 – 15:25Feedback on Production types Peter Campbell ENTSO-E Transparency Advisor 15:25 – 15:45Conclusions, Actions and Next steps Alain Taccoen WGMIT Convenor 15:45– 16:00A.O.BAll 16:00End of Meeting

3 3 TSEG meeting 1 follow up….. Sent on 4 Feb: The draft minutes comment before Wednesday 13 February. (see next slide) The draft detailed descriptions and comment sheet The updated ToR as discussed for final approval. Asked for proposals for: Art.5-1-c,“Technical and operational criteria which data providers would need to fulfil when providing data to the central information transparency platform” Art.5-1-d,”Appropriate classification of production types”. We would like to ask for you to return your comments in the Excel sheet and proposals before 22nd February, 12 noon to which will then be consolidated and discussed at the next TSEG meeting on 28th February in Brussels. Input received after 22 February will not be All documentation will be published at https://www.entsoe.eu/data/entso-e-transparency- platform/https://www.entsoe.eu/data/entso-e-transparency- platform/

4 Terms of Reference

5 5 Manual of Procedures: Terms of Reference ENTSO-E asks for approval of the ToR Jean-Noel MARQUET (EDF) Concerning the 1st TSEG meeting draft minutes, I suggest to add these items (§4) : "In the morning, the Convenor has mentioned the possibility to disclosure additional information using "free text" : that is a interesting idea". "It is useful to have a cost/benefit approach to any further specification" Marcus Mittendorf (EEX) (Group comments) add: No requirement to send older data before EMFIP is established A list on the ENTSO-E transparency platform of who complies with the data provider requirements (including TSOs) should be made to have the same level playing field for everybody, Modify the sentence: “ENTSO-E remains the sole party responsible for the development of the central information transparency platform and manual of procedures and shall not be bound to accept all suggestions provided by stakeholders. If a suggestion is rejected, ENTSO-E shall endeavor to provide an explanation.”

6 Draft Manual of Procedures Overview, scope, aims and readership

7 Overview Readership: Data owners Data providers Data consumers Purpose: To provide, either directly or by reference: All information that would be required for a data provider to develop & operate a system to submit data to the platform in accordance with the legislation and with ENTSO-E system definitions All information that would be required to develop & operate a system to extract data from the platform 7

8 In scope: “details and format of the data to be published…” per Art 4 of the regulation Anything that a 3rd party would need to know to submit or extract such data to or from the platform Not in scope: Matters internal to ENTSO-E or its suppliers Material that would be considered confidential to ENTSO- E or its members Scope of the manual of procedures 8

9 The aim is that the handbook does not duplicate material published elsewhere. If such material is required it is included by reference only. For example reference to definitions in the Regulation on submission and publication of data in electricity markets and in Network Codes, existing standards documentation. The handbook will be constructed as an on-line resource (which facilitates the cross-referencing of material) but a pdf reference version can be exported for download. Only the on-line copy will be definitive. Structure 9

10 Article 5 requirements: “ENTSO-E shall develop a manual specifying” Details and format of the submission of data Standardised ways and formats of data communication and exchange between concerned parties Technical and operational criteria for providing dataAppropriate classification of production types To be developed under open and transparent consultation with stakeholders To be made available to the public To be updated when necessary To be submitted to ACER who will provide an opinion To be developed under open and transparent consultation with stakeholders To be made available to the public To be updated when necessary To be submitted to ACER who will provide an opinion 10

11 Detailed data descriptions (next topic for today) Implementation Guides: to be produced for each business domain under the Regulation (Load, Generation etc.) Implementation Guides Provide XML schemas for encoding of the data Are developed by the ENTSO-E WG EDI already in existence for the present platformwww.entsoe.net Currently published through the EDI library on Details and format of the submission of data 11

12 Connection and submission methods: Web Services Market Data Exchange System (MADES) Secure ftp Payload expected to be XML documents compliant with the XML schemas of the relevant Implementation Guide Standardised ways and formats of data communication and exchange… 12

13 Management of standing (reference and master) data Establish data ownership & accountabilities Devolve responsibility and control as far as possible to data owners Establish clear procedures for distribution of updates to standing data Support routes (resolution of technical and business queries) Other topics 13

14 Comments on detailed descriptions

15 15 Load Total load per bidding zone per market time unit (6.1.a, 6.2.a) “Actual” total load Net generation: Net or gross: net is suitable but use gross if high accuracy Real-time measures (SCADA) + estimated dispersed generation Real-time measurements are enough. No additional measures after H+1 Storage resources: Only significant storage resources to be provided H+1 is obliged by the Regulation. In case of absence of measures, estimation is needed.

16 16 Load Day-ahead forecast of the total load per market time unit (6.1.b, 6.2.b) Market time unit harmonization not needed as data is per bidding zone Replacement: “The total load refers to the same definition as in Article 6.1.a.”; by “The day-ahead forecast is calculated (estimated) on the historic load profile on similar days, taking into account the variables that affect electricity demand, such as weather conditions, climate and socioeconomic factors” Need for national agreements between TSOs and DSOs regarding procurement of information to perform the forecast by TSOs. Forecasts can be updated is weather conditions changes.

17 17 Load Week-ahead total load forecast per day (6.1.c, 6.2.c) Replacement: “The total load refers to the same definition as in Article 6.1.a.”; by “The week-ahead forecast is calculated (estimated) on the historic load profile on similar days, taking into account the variables that affect electricity demand, such as weather conditions, climate and socioeconomic factors” Need for national agreements between TSOs and DSOs regarding procurement of information to perform the forecast by TSOs. Forecasts can be updated is weather conditions changes.

18 18 Load Month-ahead total load forecast per week (6.1.d, 6.2.d) Replacement: “The total load refers to the same definition as in Article 6.1.a.”; by “The month-ahead forecast is calculated (estimated) on the historic load profile on similar days.” Need for national agreements between TSOs and DSOs regarding procurement of information to perform the forecast by TSOs. Forecasts are not influenced by weather conditions as it is long- term forecast.

19 19 Load Year-ahead total load forecast per week (6.1.e, 6.2.e) Replacement: “The total load refers to the same definition as in Article 6.1.a.”; by “The year-ahead forecast is calculated (estimated) on the historic load profile on similar days.” “Rolling year” consistency. Need for national agreements between TSOs and DSOs regarding procurement of information to perform the forecast by TSOs. Forecasts are not influenced by weather conditions as it is long- term forecast.

20 20 Load Planned unavailability of consumption units and Actual availability of consumption units (7.1.a,b, 7.2, 7.3) Reason for the unavailability have to be clearly defined. To be checked with generation unavailability. Decision time reporting seems to be needed for monitoring purposes under Transparency Regulation and REMIT. Replacement of “DP” by “Data Provider” Need for national agreements between TSOs, DSOs and consumers to report unavailability. Immediately publication: EMFIP will support it, being “immediately” understood in terms of information systems (probably seconds).

21 21 Load Year-ahead forecast margin (8.1, 8.2) Deletion of "Total load is defined as in Section 2.“ Only one value will be provided per year. TSOs are also Primary Owner of the “calculated” data. Updates of this data: not clear. To be discussed. No, as it is a year-ahead forecast (recommended). Yes, as it can change during the year.

22 22 Generation - Objective of the document Main points raised in the comments received need to be discussed General comments UMM and unavailabilities Production type Criteria for data provider Master data Kind of filing rate of water reservoir and hydro storage plant to be reported

23 23 Generation – General Comments Comments on the content and the wording of the regulation No modification of the regulation is possible. All the comments made on the regulation are rejected. Location 2 kind of proposal for describing the location: -GPS coordinates -Country, Town … : lower level of precision 2 questions to define the relevant level of description: -What is the additional value for the market to know exactly the location of the generation/production unit? -Is there strategic defence restriction which apply for this information ? =>To be discussed

24 24 Generation - UMM and Unavailabilities List of reason for unavailabilities A Predefined was first drafted in the data description: maintenance failure (permitted for changes in actual availability only) shutdown (permitted for Consumption, Generation and Production Units only) other Additional list suggested: Outage, External factors, redispatch to be completed => to be discussed Change in actual availabilities and unplanned unavailabilities in the same document In the data description ENTSO-E already suggested to have only one document. If the actual unavailability have been planned and already reported with the correct available capacity, it’s not necessary to deliver again the data. But it is still in discussion inside ENTSO-E => To be discussed

25 25 Generation – UMM and Unavailabilities Free Text for UMM 2 different requirement for the UMM : REMIT and the draft Transparency regulation 2 proposal on 2 different levels could be used for publishing open comments 1) On the unavalaibilities required by the regulation: The text is related to an outage with a specific period covered 2) Outside any outage The text is an open comment not linked directly with an outage. =>To be discussed No aggregation for unavailabilities It was suggested to make aggregation on the unavailabilities (per control area or per production type) This aggregation is not required by the regulation. => Comment rejected

26 26 Generation - UMM and Unavailabilities Decision taken to be defined? In the regulation a planned unavailability is published as soon as possible, but no later than one hour after the decision regarding the planned unavailability is made.” Some comments suggested to define the decision Is it necessary to define clearly what is a decision? =>To be discussed Example of interval pattern mode In the data description it is mentioned that In some cases, if an unavailability is repeated several times it could be described with an interval pattern mode. For an outage on a generation unit which is unavailable every Friday for one year, This outage could be described in only one document, The period covered by the document will be one year, and the unavailability of every friday will be described. It will be clearly explained in the BRS and IG. =>To be discussion when the BRS will be presented

27 27 Production Type Proposal to replace production type by fuel type: rejected No modification of the regulation is possible. All the comments made on the regulation are rejected. Proposal received for the production types To be discussed Primary owner of data Owner of production units or operators of production units? =>To be discussed

28 28 Criteria for being data provider Question raised in the comment Data provider have to belong to the area of the data concerned => to be discussed

29 29 Master Data Which master data to be used in EMFIP One comment raised that the production name, the install capacity for a generation unit… is not needed to be reported each time if it is a master data This question is still open in ENTSO-E. It involves lots of questions: - legal issues : who is responsible for the data, What kind of validation is required from EMFIP - how to manage the data, - if some master data are not previously recorded in EMFIP, some data sent could be rejected -… To be discussed when the BRS will be introduced

30 30 Kind of filing rate of water reservoir and hydro storage plant to be reported Question raised in the comment What kind of water reservoir and hydro storage to be reported Proposal from Eurelectric: refer to UNIPED definition

31 31 Transmission section ArticleCommentsAnswers from experts Group General general comment: The used term definition in the Entso-e network code should be as well the basis for this term definition OK we will align the data description with Network code as much as possible terms Status of unavailability of transmission assets The note in the definition is not clear. What does it mean? Another status, for instance “forced” could be added. It is meant here the status of the information/message and not the status of the unavailability. => definition will be clarified terms For all articles referring to reason for the unavailability (i.e. consumption, generation), the same list should be used. => to be clarified ok it will be done terms to add in the terms section Remedial actions: As defined in the draft CACM NC: “means a measure activated by SOs, manually or automatically, that relieves or can relieve Physical Congestions. They can be applied pre-fault or post- fault and may involve costs.” ok it will be done

32 32 Transmission section ArticleCommentsAnswers from experts Group 10.1 a,b,c Unavailability of transmission infrastructure In order to follow that the requirement to publish within one hour is fulfilled, the decision time and publication time must be submitted. The publication time will be published but decision time has low added value for the market. Data provider is responsible to deliver the information on time. Statistics could be calculated on a year basis about the level playing field of data providers Planned unavailability of offshore grid infrastructure is missing in the Regulation requirements !? Yes, not required by the regulation 10.1 As set in the terms part that will work only for NTC capacity calculation approach. How the FB calculation would be impacted? For the time being It was decided to wait regarding the FB publications as there are no current implementation in Europe 10.1 a,b,c reasons for the unavailability Are the reasons the ones that are set in the term part "Reason for planned unavailability or change in actual availability"? Reference to "terms" part should be added. ok it will be done

33 33 Transmission section ArticleCommentsAnswers from experts Group 10.1.b Note: in case of unplanned outage, there cannot be status “canceled” The definition of "status of unavailability of transmission asset should foreseen a status for this unplanned outage. Why not using the term "forced? No, it is not the meaning of the "status“. The status related to the information/message and not the status of the unavailability 11.1 If due to the technical reasons a transfer capacity for a given bidding zone is calculated for the whole technical profile of this bidding zone, then the transfer capacity between bidding zones means the transfer capacity on the technical profile Not sure the meaning is clear here. TSO has to provide the NTC available per border and per direction. There are two options for TSOs either NTC values or technical profiles 11.2 submission of the data can be done with smaller granularity What does that mean? NTC variation within a month? And/or specifying value for base peak off peak product? The term granularity should be explained. A smaller granularity means that the submission could be done with a more accurate information, f.i. a value per day even if it is request per week We will align the wording.

34 34 Transmission section ArticleCommentsAnswers from experts Group 11.2BRS should be defined BRS = Business Requirements Specifications for the transparency platform (EMFIP). It will be removed from the doc A yearly offered capacity may include some sub periods where the value may differ. To what the term "sub periods" is referring to? The sub period should be explained. A sub-period is a time interval within the whole period (Eg a month is a sub-period in a year) 11.3 intraday transfer limits To be defined in the "terms"section intraday capacity limit value taking into account the technical capacity of the interconnector and the security constraints of the grid. It will be added in the document 11.3 ASAP without undue delay. The regulation foreseen "not later than one hour"" Is this wording foreseen an improvement? Regulation has been modified several times. It will be changed Market Committee to decide on the way of creating/publishing this report Which market committee? The report should be publicly available. internal ENTSOE comment, it will be removed

35 35 Transmission section ArticleCommentsAnswers from experts Group 11.4 all possible measures that could be implemented to increase the offered transfer capacity, together with their estimated costs of all possible measures. The detailed descriptions should develop on what are the possible measures. There is no harmonization on that topic 12.1.b Total capacity nominated means aggregated capacity nominated,by market participants from time horizons (Y, M, W, D, ID) corresponding to explicit allocations, agreed between the TSOs (i.e. where a TSO-TSO matching process applies) and confirmed to the market. TSO-TSO matching process should be explained It should be specified as soon as the nomination has been approved/validated by both TSO? ok we will remove the “TSO common wording” and the text will be clarified

36 36 Transmission section ArticleCommentsAnswers from experts Group 12.1.b Amount of MW nominated capacity per border and direction This option “per border” should be used, more useful information. CACM network code foresees both options (per border or in net position) 12.1.d The regulation as well as the data description states that the information on Day-Ahead Prices should be published no later than one hour after gate closure. The gate closure is a set time but the publication time for the outcome of price calculation is not. In some rare situations the price calculation may take longer time than expected and this will affect the time for when it’s sent to the platform. This should be taken in to account in the restrictions of publication deadline for ENTSO-E. When a publication deadline is reached it will not block a publication afterwards. The publication deadline is a monitoring feature which will send alarms to the data provider if the deadline is passed 12.1.g Is operational period the same as operating period? This period should be defined in the "terms" section ok it will be done

37 37 Transmission section ArticleCommentsAnswers from experts Group 13.1.b Information relating to countertrading per market time unit, specifying: -comments Comment should specify the period of countertrading action? The comments field should not be used for duration. A Period could be added 13.1.c For their control areas TSOs shall provide to ENTSO-E for publication a monthly summary report detailing the costs incurred to them separately for measures taken as referred to in paragraph 1(a), paragraph 1(b) and any other remedial action. Is an explanation on how these costs are calculated will be provided? An explanation on the methodology to calculate the cost should be published in the summary report. An Explanation on the costs will be given but not a specific methodology 13.1.c Publication in M+3 The regulation foreseen a publication no later than on month after the end of the referred month Regulation has been modified several times. It will be changed

38 38 Balancing Finalised Balancing Network Code will be used as basis for terms and definition. Rules on balancing should be published by TSOs. All balancing data should be sent by TSOs or Market Operators (primary owners). Market participants (generators, consumers) don’t have to send such data. Bilateral balancing contracts should be handled the same way as other balancing contracts. According to the regulation, cross control area balancing and international assistance between TSOs shouldn’t be distinguished only under point 17.1.j and 17.2.i

39 Coffee time

40 Feedback on data provider technical and operational criteria

41 41 Feedback on data provider technical and operational criteria (1) Technical criteria for data providers: Communication shall be done by using MADES, web services, SFTP (reference to the detail descriptions) Information exchange must be done in accordance with formats defined in Implementation Guide (EDI library) Data provider should be capable to resend data

42 42 Feedback on data provider technical and operational criteria (1) Operational criteria for data providers: Approval by local TSO is needed Prequalification period is recommended. Prequalification should be done by using EMFIP test platform Audit by local TSO Communication in English Data providers and TSOs should nominate Single Point of Contact (SPoC) for all data related issues. Market participants should collaborate with TSO in defining data providers for EMFIP in a way to ensure cost efficiency, optimize data flow, avoid duplication of tasks and data flows. Data providers should provide data for substantial (not less than1/3) part of the local market. The number of data providers for EMFIP should not exceed 200 (this 200 should be proved in “The Proposal concerning the operation of the central information transparency platform and the associated costs”). Generation units, production units and consumption units should send data to the EMFIP via the local TSO or other data provider approved by the local TSO. The number of data providers to the EMFIP shall be limited and optimised.

43 ENTSO-E collects information about Local Projects via TSOs Local projects – on Data provider side Local Monitoring Dashboard (LMD): Identified Data providers for each Data item; Status of the project on Data provider side; Date, when data is expected to be ready for submission SPOCs of TSOs (TPCs) provide necessary info for LMD; Close dialog between TSO and Data provider is needed Information flow from Data owner to the New TP has to be defined 43 Monitoring of Local Projects Aggregators TSOs Aggregators PXs, AOs, CAs Aggregators DSOs Aggregators GenCo’s New TP

44 Coffee time

45 45 Feedback on Production types Required in the manual of procedure To be specified by ENTSO-E Reviewed by ACER ENTSO-E approach: Our goal is to keep it simple The information must be useful for the market (fuel type vs technology type) Possible use of existing lists or for coherency in other reporting (e.g. statistical reporting, REMIT…) List to be clarified and discussed in further meetings EC Should not be too detailed but also not too simplistic. Reasonable mixture between generation technology and fuel. E.g. It is not enough to determine that it is a thermal generation. People would want to know whether it is lignite fired, coal fired or gas fired or fuel oil fired. This would have to be combined with the technologies used. Combined cycle, open cycle, boiler, etc. An additional indication of CHP may also be interesting

46 46 What do existing ENTSO-E publications have? Existing data in ENTSO-E statistical publications Thermal Nuclear Fossil Lignite Hard coal Gas Oil Mixed fuel Hydro Run of River Storage and pump storage Renewable Non Renewable Other Renewable Wind onshore Wind offshore Solar Biomass Not identifiable Not detailed enough??

47 47 What standards are already published? EECS Rules Fact Sheet 5 TYPES OF ENERGY INPUTS AND TECHNOLOGIES: Technology TECHNOLOGY Level 1Level 2Level 3 Description SolarUnspecified PhotovoltaicUnspecified Classic silicon Thin film ConcentrationUnspecified WindUnspecified Onshore Offshore Hydro-electric head installations Unspecified Run-of-river head installationUnspecified Storage head installationUnspecified Pure pumped storage head installation Unspecified Mixed pumped storage headUnspecified MarineUnspecified TidalUnspecified Onshore Offshore WaveUnspecified Onshore Offshore CurrentsUnspecified PressureUnspecified TECHNOLOGY Level 1Level 2Level 3 ThermalUnspecified Combined cycle gas turbine with heat recoveryUnspecified Non CHP CHP Steam turbine with back-pressure turbine (open cycle)Unspecified Non CHP CHP Steam turbine with condensation turbine (closed cycle)Unspecified Non CHP CHP Gas turbine with heat recoveryUnspecified Non CHP CHP Internal combustion engineUnspecified Non CHP CHP Micro-turbineUnspecified Non CHP CHP Stirling engineUnspecified Non CHP CHP Fuel cellUnspecified Non CHP CHP Steam engineUnspecified Non CHP CHP Organic rankine cycleUnspecified Non CHP CHP NuclearUnspecified Heavy-water reactorUnspecified Light water reactorUnspecified BreederUnspecified Graphite reactorUnspecified OtherUnspecified Too detailed?

48 48 What standards are already published? EECS Rules Fact Sheet 5 TYPES OF ENERGY INPUTS AND TECHNOLOGIES: Fuel Type Too detailed? FUEL (or heat source) Level 1Level 2Level 3 Description Unspecified RenewableUnspecified SolidMunicipal waste Industrial and commercial waste Wood Animal fats Biomass from agriculture LiquidUnspecified Municipal biodegradable waste Black liquor Pure plant oil Waste plant oil Refined vegetable oil GaseousUnspecified Landfill gas Sewage gas Agricultural gas Gas from organic waste digestion Process gas HeatSolar Geothermal Aerothermal Hydrothermal Process heat Mechanical source or otherUnspecified Wind Hydro & marine Unspecified FUEL (or heat source) Level 1Level 2Level 3 FossilSolidUnspecified Hard coal Brown coal Peat Municipal waste Industrial and commercial waste 0 LiquidUnspecified Crude oil Natural gas liquids (NGL) Petroleum products GaseousUnspecified Natural gas Coal-derived gas Petroleum products Municipal gas plant Process gas HeatUnspecified Process heat NuclearSolidRadioactive fuel

49 49 What is required under REMIT? What will be the requirements under REMIT for UMM (outages)? The ACER Guidance notes (2 nd edition, 28 Sept) include the following Annex:

50 50 A balanced approach Unspecified RenewableUnspecified SolarUnspecified PhotovoltaicUnspecified Classic silicon Thin film Concentration WindUnspecified Onshore Offshore Hydro-electric head installations Unspecified Run-of-river head installation Storage head installation Pure pumped storage head installation Mixed pumped storage head MarineUnspecified TidalUnspecified Onshore Offshore WaveUnspecified Onshore Offshore Currents Pressure Geothermal Aerothermal Hydrothermal Biomass Fuel type 1Fuel type 2 Biomass ThermalUnspecified Combined cycle gas turbine with heat recovery Unspecified Non CHP CHP Steam turbine with back- pressure turbine (open cycle) Unspecified Non CHP CHP Steam turbine with condensation turbine (closed cycle) Unspecified Non CHP CHP Gas turbine with heat recoveryUnspecified Non CHP CHP Internal combustion engineUnspecified Non CHP CHP Micro-turbineUnspecified Non CHP CHP Stirling engineUnspecified Non CHP CHP Fuel cellUnspecified Non CHP CHP Steam engineUnspecified Non CHP CHP Organic rankine cycleUnspecified Non CHP CHP Process heat Unspecified Heavy-water reactor Light water reactor Breeder Graphite reactor Fuel Type SolidUnspecified Hard coal Brown coal/Lignite Peat Municipal waste Industrial and commercial waste LiquidUnspecified Crude oil Natural gas liquids (NGL) Petroleum products GaseousUnspecified Natural gas Coal-derived gas Petroleum products Municipal gas plant Process gas HeatUnspecified Process heat SolidMunicipal waste Industrial and commercial waste Wood Animal fats Biomass from agriculture LiquidUnspecified Municipal biodegradable waste Black liquor Pure plant oil Waste plant oil Refined vegetable oil GaseousUnspecified Landfill gas Sewage gas Agricultural gas Gas from organic waste digestion

51 Conclusions, actions and next steps

52 52 Next Steps (Tentative Agenda) 22 FebCollect feedback 28 FebTSEG 2 meeting – identify most important comments on detailed definition descriptions 12 MarConsolidate, reject/accept comments and incorporate final TSO comments 13 Mar WGMIT meeting for approval of BRS including detailed descriptions 18 MarNew BRS version by secretariat 21 Mar TSEG 3 meeting presentation of BRS and initial IGs 25 Mar send BRS to all stakeholders for review (in parallel with ENTSO-E) 23 Apr TSEG 4 meeting to finalise review of BRS & IGs. End Apr Consolidate final version of BRS 15 May WGMIT meeting approval of complete MoP (consultation draft) End MayMC written approval of complete MoP (including BRS & IGs) Jun Public consultation (following the publication of the regulation) Duration ≈1 month Jul – AugConsolidation of responses & draft for final comments and WGMIT approval Sept MC and Assembly approval Send draft to ACER (within 4 months of entry into force) Feedback and amendment before publishing

53 53 Next Steps Topics for discussion in TSEG 3 (21 March) ENTSO-E to send proposals on (14 th March 2013) Criteria for being data provider List of production types  Comments awaited by 19/3 end of day ENTSO-E to send a new version of Detailed Data Description (frozen version until the Public Consultation) just before the next meeting. ENTSO-E presentation of BRS and IG for TSEG consultation before 4 th TSEG (23/4).

54 Questions?

55 End of Meeting, Thank You! DateLocation Meeting 1 31 JanuaryBrussels Meeting 2 28 FebruaryBrussels Meeting 3 21 MarchBrussels Meeting 423 April Brussels