D E P E N D A B L E N A T U R A L G A S Customer Webex July 25 th, 2013.

Similar presentations


Presentation on theme: "D E P E N D A B L E N A T U R A L G A S Customer Webex July 25 th, 2013."— Presentation transcript:

1 D E P E N D A B L E N A T U R A L G A S Customer Webex July 25 th, 2013

2 2 Review of Upcoming Outages August & September Q&A

3 3 Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

4 4 Scheduled dates are subject to change. Projects may be added, altered, delayed or cancelled. TGP will provide notice of such additions or changes via PASSKEY postings. Dates as posted on PASSKEY should be deemed correct in the event of conflicts between PASSKEY posted dates and dates within this presentation.

5 5 Green No Impact Anticipated Yellow Restrictions are possible, but not likely With extended duration, restrictions could be necessary from time to time (M) denotes that meter(s) may be impacted, refer to EBB posting Red Restrictions are probable

6 6 Div 5 & 6 – August Outages Cleaning Pig 409A-1101 to 409A-1102 (8/20/2013-8/21/2013) Hydrotest 40-3 to 41-3 (7/8/2013-8/27/2013) ILI Pigging 4-3 to 9-3S (8/6/2013-8/8/2013) ESD Test Sta. 409 ESD (8/6/2013-8/7/2013) Sta. 409A ESD (8/8/2013-8/9/2013 Class change 511-1 to 512-1 (7/15/2013-8/7/2013) Unit Maintenance Sta. 409A (8/14/2013-8/21/2013) ILI Pigging MLV 823-1 to 827-1 (8/6/2013)(M) Hot Tap (M) 8-1 to 9-1 (7/26/2013-7/27/2013)

7 7 2013 Outages – Offshore Outages Sta 523 – Unit Outage (4/11/2013-8/10/2013) 507F-100 (Grand Chenier) -- SAM Sale Outage (7/22/2013-7/31/2013) (M) Sta. 523 - Station & Line Tie-ins (7/24/2013-8/10/2013)(M) Sta. 523 (36") Line outage - SAM Sale Outage (6/22/2013-8/10/2013)(M)

8 8 Div 8 & 9 – August Outages Bi-Directional Operation Sta 555 (5/29/2013-8/13/2013) Hydrotest 109-3 to 110-3 (6/15/2013-8/15/2013) Purchase Power Upgrade Sta. 834 (7/15/2013-7/29/2013) Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 72-1 to 77-1A (7/8/2013-8/16/2013) Station Maintenance Sta. 843 (8/30/2013) Station Maintenance Sta. 834 (8/7/2013)

9 9 Div 10 (200 Line) – August Outages Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 208-2 to 209-2 (3/7/2012-8/15/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Station 219 Maintenance ESD (8/15/2013)

10 10 Div 10 (200 Line) – August Outages Unit Maintenance Sta 266A (8/13/2013-8/16/2013) Sta 266A (8/19/2013-8/23/2013) Anomaly Remediation 268A-101.1 to 268A-103 (Fitchburg) (7/15/2013-8/16/2013) 267-1 to 270C-101 (Beverly Salem) (8/12/2013-8/23/2013) 270B-101.1 to 270B-103 (Concord) - (6/17/2013-8/2/2013) Anomaly Remediation 256-3A to 257-3 (8/26/2013-8/30/2013) Station Maintenance Sta 267 (8/27/2013-8/28/2013)

11 11 Div 10 (300 Line) – August Outages Station 323A NEUP Station (8/5/2013-10/7/2013) 317-1 - Pig installation (8/19/2013-8/29/2013) NEUP Tie-Ins 322-2 (8/20/2013-8/30/2013) 325-2 (8/15/2013-8/21/2013) Station 313 MPP Station (8/12/2013-8/30/2013) Station 319 NEUP (8/15/2013-10/25/2013) Station 321 NEUP (7/15/2013-8/5/2013) Maintenance Pigs 321-1 to 325-1 (8/30/2013) Station Maintenance Sta 303 – MPP (8/5/2013-8/10/2013)

12 12 Div 5 & 6 – September Outages ILI Pigging 409A-1101 to 409A-1102 (9/24 /2013-9/26/2013) Station 40 Maintenance (9/2/2013-9/20/2013) ILI Pigging MLV 823-1 to 827-1 (9/10/2013)(M) Maintenance Pig Carthage Line (9/17/2013) (M) ILI Pigging MLV 507G-100 to 507G-109 (9/25/2013)(M)

13 13 Div 8 & 9 – September Outages Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 69-2 to 78-2 (9/23/2013-10/17/2013) ILI Pig 110-2 to 114-2S (9/1/2013-9/2/2013) (M) Pressure test 63-4 to 64-4 (9/1/2013-9/30/2013) (M)

14 14 Div 10 (200 Line) – September Outages Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 211-1 to 212-1(9/1/2013-9/15/2013) 211-2 to 212-2(9/15/2013-9/30/2013) Station 219 Maintenance MPP (9/8/2013-9/27/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Station 209 Maintenance MPP (9/4/2013-11/8/2013) Anomaly Remediation 219-2 to 307-1 (9/1/2013 - 12/1/2013) 219-3 to 307-2 (9/1/2013 - 12/1/2013)

15 15 Div 10 (200 Line) – September Outages Unit Maintenance Sta. 241 (9/9/2013-9/13/2013) Sta. 261 (9/5/2013 - 9/13/2013) Sta. 261 (9/16/2013 - 9/20/2013) Sta. 261 (9/3/2013 - 9/4/2013) Sta. 261 (9/30/2013- 10/4/2013) Sta. 264 (9/23/2013- 9/24/2013) Sta. 264 (9/25/2013- 9/26/2013) ESD Sta 230C (9/17/2013) Sta 237 (9/24/2013) Sta 266A (9/17/2013 - 9/18/2013) Class Change 230B-200 Niagara Spur Loop Line (9/16/2013-10/7/2013) Anomaly Remediation 248-2 to 249-2 (9/16/2013-10/5/2013) 258-1 to 259-1 (9/3/2013-9/13/2013) ILI pigging 261B-101.1 to 261B-102 (Springfield) (9/24/2013-9/25/2013) Station Maintenance Sta. 264 (9/30- 10/4) Line lowering 260A-100 (Northampton) (M) (9/3/2013-9/5/2013)

16 16 Div 10 (300 Line) – September Outages Station 323A NEUP Station (8/5/2013-10/7/2013) NEUP Tie-Ins Sta. 321 (9/16/2013-9/30/2013) 327-2(9/15/2013-9/21/2013) Station 319 NEUP (8/15/2013-10/25/2013) Maintenance Pigs 319-1 to 321-1 (9/15/2013) 319-1 to 321-1 (9/20/2013) 321-1 to 325-1 (9/30/2013) Meter Station Upgrade Meter 020207 (Mahwah) (9/2/2013-9/5/2013)

17 17 Suggestions for improvements to this meeting Are the meetings beneficial? Is additional information needed? Questions after the meeting? Other? Email to one of the following: Your scheduler PASSKEY Portal