Presentation is loading. Please wait.

Presentation is loading. Please wait.

A photographic history of our church. Concrete footings are poured in the ground underneath the floor of basement. They serve as the foundation of the.

Similar presentations


Presentation on theme: "A photographic history of our church. Concrete footings are poured in the ground underneath the floor of basement. They serve as the foundation of the."— Presentation transcript:

1 A photographic history of our church

2

3 Concrete footings are poured in the ground underneath the floor of basement. They serve as the foundation of the foundation. Seen from the east end, the footings trace the “footprint” of the lower level.

4 To strengthen the footings, metal rebar is placed inside the concrete as it is poured. The orange plastic caps are placed on the ends of the rebar to prevent injuries to workers on site.

5 This interior footing has four bolts placed within it. The base of a support column will later be placed atop these bolts. The nuts will then be adjusted to level the base so the column is perfectly vertical.

6 Concrete will be poured into these forms to create the walls of the lower level. The metal rebar provides interior strength to the concrete; the walls will also be buttressed with steel beams on the inside.

7

8 The outlines of the circle drive and the upper lot are seen in this photo, taken from the site of the future front door of the church. This arrangement will allow folks to be dropped off right at the front door.

9 This is the upper lot seen from the west end, facing the front of the church. The forms for the basement stand just beyond the lot’s edge. The black plastic on the right prevents erosion of the exposed soil.

10 The south terrace, viewed from the southwest. The lower level– which houses the future classrooms, parish hall, and offices— opens directly into this area. The Prius, trailer, and outhouse will be removed prior to occupancy!

11 This lot sets directly south of the church. It provides convenient access for entry to the lower level of the church where the future offices, classrooms, and fellowship hall will be located.

12 The future church will accommodate over 400 people, so it is necessary to provide adequate fire protection. These hydrants will be installed near the south side of the church to facilitate fire control.

13 This is a view of the lower level of the church from the northeast corner. Due to the height of the walls, scaffolding is required just to install the forms. Concrete will soon be poured into these forms to make the outside walls.

14 This is the electricity meter for the new facility. Since the church sets back several hundred feet from the road, it is necessary to run as much electrical line to bring power to it. The extensive power requirements of our church, necessitated by the high demands for heating and cooling a large volume of space, also require specially designed power distribution systems.

15

16 The walls in the lower level continue to be erected. Some have already been built, as seen on the left; the forms of others have been built, but concrete will be poured later; finally, some of the forms, shown in center, still await assembly.

17 These vertical white pipes are for plumbing.

18 The walls shown here will eventually be buried underground.

19 These curbs show the outlines of the roundabout and driveway out to Humphrey’s Road.

20 The impermeable surfaces of the parking lot and driveway create large amounts of runoff water. This storm sewer conducts the water to a detention pond which delays its entry into the drainage ditch and thereby prevents flooding.

21 The high amount of traffic entering and leaving the campus at Mass times will affect traffic flow on Humphrey’s Road. In order to lessen the impact, we are required to add an extra lane along the frontage of our property.

22 In order to get water to the building, 1800 feet of pipe was run from the intersection of N Hwy to the parish campus. Here the valve connecting the main to the campus is shown. The concrete vault on the left will contain the water meter and pump.

23 Electricity to the campus is now hooked up. The three strips of conduit on the left of the power pole contain the wiring which carry power to the building. Power is already needed for lighting the trailer and running other construction equipment.

24

25 The floor in the lower level is seen in this photo. The concrete was just poured this week. The concrete slab is sawed into square sections to prevent unwanted cracking.

26 The pillars supporting the upper level floor will rest directly on the footings below the basement floor, hence forms were placed around the bases for the pillars.

27 Due to cost limitations, the proposed kitchen cannot be built in the first phase of construction. To facilitate later construction, this section of the floor is deliberately left unfinished. The doorway will provide easy access to the kitchen from the outside.

28 The black material on the exterior of the wall is waterproofing. The blue Styrofoam insulates the wall to prevent water condensation on the interior wall during cool weather.

29 The exterior of the walls is backfilled with gravel rather than dirt. The gravel makes it easier for water to drain away and thereby reduces strain on the exterior due to water pressure and freezing.

30 Prior to the paving of the driveway, a base layer of gravel is placed on the driveways and parking lots.

31 This photo shows the water line connection near the church. The yellow caution tape warns onlookers—both Anglo and Latino-- that falling into a hole may cause serious injury. The contractor is not responsible for harm suffered by illiterates.

32

33 The structural steel framework supports the floor of the upper level and buttresses the lower level walls too. The concrete piers will support the exterior pilasters in the finished church. The remaining lower level walls will be made of wood rather than concrete.

34 This steel frame is the structural support for the bell tower. Due to budget constraints, no bell will be installed in the tower at first. Eventually, a carillon (electronic) bell system will be installed.

35 The stairway on the right provides access from the lower to the upper levels of the building. The square hole on the left is the base of the elevator shaft. Due to budgetary constraints, the elevator will not be installed in the first stage of construction.

36 These concrete piers mark the main entrance of the church. They will support the overhang structure at the front door that will shield worshipers entering the church from inclement weather.

37 These steel posts frame the side entrance of the church. This entrance will be situated near a circle drive. It will allow for people to be dropped off near the church. Eventually the section of the drive near this entrance will be covered.

38 Is this the work of a gigantic mutant mole? Not exactly. This lengthy mound of dirt traces the waste disposal line which runs from the north side of the building to the northwest corner of the campus where the septic system has been installed.

39 The facility’s waste will be disposed of in a septic system on the northwest corner of the campus. The white pipes indicate the site of lateral lines of the plumbing network. After the county sewer line is built to the north, the waste line will be connected to it.

40

41 The lower walls on the south and east sides of the structure are made of wood. The studs and other support elements are shown here. The doorways and windows can be seen from this view from the south.

42 This is a view from the east. The doorway into the lower level can be seen on the left. This end of the lower level will eventually be turned into administrative offices for the parish.

43 This is a view from the inside of the lower level looking outside towards the southwest. A doorway and window openings can be seen.

44 The base for one of the parking lot lights is shown here. Coincidentally, there are twelve poles in the lots, corresponding to the twelve apostles. As the Lord told them in the Sermon on the Mount: You are the light of the world!

45 These concrete covers grant access to the septic tanks so that they can be serviced as needed. The tanks are located to the east of the church.

46 These steel beams will support the overhang above the front entrance into the church.

47 A change in the construction plans was recently made. It was decided to finish paving all the parking lots. So additional preparation work is being done to complete this easternmost section of the lower parking lot.

48 It is said that all dogs go to heaven. We hope they all don’t go here! In fact, this fire hydrant is located near the front entrance to ensure adequate emergency water service in the event of a fire.

49

50 The lower level walls are being installed. The outlines of doorways and windows can be seen in this photo taken of the east end of the building.

51 This view of the south side of the lower level shows the outlines of the windows and doorways. The lower level will house the classrooms, fellowship hall, and parish offices.

52 The outlines of the walkway from the parking lot to the lower level are traced by the gravel path. A sidewalk will be installed here later.

53 This is a view from the interior of the south doorway. The gravel path leads to the parking lot.

54 These wooden floor joists are known as “TJIs.” They provide support for the upper level floor.

55 Plywood is being placed on the floor joists to serve as the base for the rest of the upper level flooring.

56 The kitchen will eventually be installed in the northeast corner of the lower level, so this area was left open for the installation of the necessary equipment in the future. The pipes connecting to the future drains and sewers can just barely be seen.

57 ... But you’ll have to take the stairs! This square opening is the base of the shaft of the future elevator. It will be covered with a temporary floor at first; this floor section will then be removed when the elevator is installed.

58 This photo shows the plywood being affixed to the top of the floor joists.

59 This photo shows the main entry of the church. The approximate level of the floor is now beginning to appear.

60 It was a cloudy day for the Age of Aquarius. Nonetheless, by leaving the southwest corner of the flooring until last, workers were able to make use of natural illumination. A set of TJIs rests just inside the side entry from the north.

61 The concrete has been poured at the entry of the driveway. The asphalt paving of the rest of the drive should begin soon. In the meantime, traffic is entering from a temporary driveway on the east end of the frontage.

62

63 Glulam is shorthand for Glued Laminated Timber. These are supporting elements that support the roof and upper walls of the church. A pair of the glulams are being installed here.

64 Glulams are actually composite beams made of numerous wooden beams (approximately 1” x 4”) which are bent and then glued together and laminated.

65 The glulams are erected in pairs. The two glulams are connected at top by several bolts which are run through these pre-drilled holes.

66 The metal bracket at the base of this glulam is called a “shoe.” The shoe joins the glulam base to the steel frame below.

67 Yes, those who work for the Church work in “high places,” but we usually speak in figurative terms. Not so here! Due to the high of the glulams, scaffolding must be erected to enable workers to fasten the beams together at top.

68 Once the glulams are in place, the wooden decking shown here (wrapped in protective plastic) will be ready to install. This decking will be fastened to the top of the glulams and will constitute the church ceiling.

69 Getting material into place for assembly is a job in itself! The orange forklift in front is used to lift the material from the ground to the floor of the church for assembly. The wooden frame for one of the dormers on the south side has just been installed in the center.

70 Two cranes are used to raise the glulams into place. Wind has proved to be a significant challenge due to the high elevation of the site and the height of the glulams. The glulams are fastened to one another and also attached by cables to the floor for stability.

71 The protective plastic and other materials are used to shield the glulams from damage during assembly.

72 The asphalt surfacing has made the trip up the driveway a little shorter, or at least, a bit smoother.

73 The asphalt has also been laid down on the parking lots.

74 This orange instrument is used by a worker on the floor to steady the glulam while it is being hoisted by the crane.

75 This photo is taken from the vicinity of the future choir area in the north transept, looking into the main nave. It gives some idea of how the structure will appear when finished. Worshipers will not be required to wear hardhats!

76 Temporary safety railing is erected around the floor during construction to prevent workers and authorized visitors from falling off.

77 At this stage of construction, the glulams must be kept stable using cables attached to the floor as well as by fastening them to each other.

78 This is the wooden frame, partially assembled, for one of the dormers which run along the sides of the church. The frames are assembled on the floor and then raised into place along the walls.

79 This photo from the west gives the viewer a sense of the how the outline of the east side of the church will appear. The steeple of the bell tower will rise slightly higher than the top of the crane on the right.

80

81

82 These diagonal beams in the bell tower denote shear walls. The shear walls help reinforce the structure against the stresses induced by high winds.

83 This pair of smaller glulams in the foreground gives the observer a sense of the narthex, that is, the gathering area at the front of the church. It has a lower roof that segregates it from the nave, that is, the main body of the church.

84

85 ... but not too much! This temporary lighting in the lower level allows work to continue downstairs even during inclement weather.

86 This is the gas line coming from the east. Natural gas will be used to heat the church.

87 This light pole still needs to be attached to its base on the edge of the upper parking lot.

88

89

90 The light poles have now been erected. They provide illumination to the upper and lower parking lots.

91 This circuit box has been installed in the lower level. It contains the circuit breakers and power switches which regulate electricity coming into the building.

92

93

94 Although the bright red fire hydrants are hard to miss, it can be done! So this long beam has been attached to one in a high traffic area to alert operators of man-lifts, forklifts, etc.


Download ppt "A photographic history of our church. Concrete footings are poured in the ground underneath the floor of basement. They serve as the foundation of the."

Similar presentations


Ads by Google