1 Mission for a Slum Free India
RAJIV AWAS YOJANA Government of Chhattisgarh Department of Urban Administration and Development Mission for a Slum Free India SLUM FREE CITY PLAN OF ACTION Municipal Corporation Korba Submitted to- MoHUPA, GoI CONSULTANCY BY- STESALIT LIMITED KOLKATA SLNA: STATE URBAN DEVELOPMENT AGENCY, RAIPUR, CHHATTISGARH

2 Within Municipal Boundary
INTRODUCTION TO KORBA KORBA PLANNING AREA= sq.km. Korba Municipal Corporation: 6 zones & 58 wards Balco Zone, Banki Zone, Darri Zone, Korba Zone, Kosabari Zone Transport Nagar Zone AREA JURISDICTION NO. OF SLUMS STATUS Within Municipal Boundary 62 Notified by Municipal Corporation 41 Not notified but listed by Municipal Corporation 13 Neither notified Nor listed by Municipal Corporation but identified during Survey for the current project Total number of Slums to be considered in the Project 116 KORBA CITY AREA= SQKM* KORBA CITY POPULATION= 3,65,073** KORBA CITY HOUSEHOLD= ** *Source: Master Plan, Korba ** Source: Census 2011 NO. OF SLUMS IN KORBA= 116 KORBA AREA UNDER SLUMS= 13.2 SQKM KORBA SLUM POPULATION= 1,75,927 KORBA SLUM HOUSEHOLD= 44,674 Source: Primary Survey, Stesalit Limited, Thus per cent slum population and per cent slum household is spread in only 6.2 per cent of land area in Korba city.

3 SFCPoA Summary Note DOCUMENT TITLE 1 Name of State Chhattisgarh 2
Name of City, Population Korba (3,65,073) 3 Name of ULB Korba Municipal Corporation 4 Name of SLNA State Urban Development Agency 5 Name of Consultant, if any Stesalit Limited 1 PROFILE a Number of Identified Slums 116 i Notified 62 ii Non Notified 54 b Slum Population, % of total 1,75,927 (48.18%) c Slum Households 44,674 2 CURATIVE STRATEGY a Tenable Slums 67 b Untenable Slums 18 c Semi Tenable Slums 31 Total d Development Options Mix 1 In-situ Redevelopment 65 In-situ Up-gradation 30 3 Relocation De Delist 116

4 Total Cost (C ) = (A) + (B)
SFCPoA Summary Note Investment Required and Phasing for Curative (Rs. in crores) Particulars 1st Phase ( ) 2nd Phase ( ) 3rd Phase ( ) 4th Phase ( ) 5th Phase ( ) Total Rs. Number of Slums 20 26 32 16 19 113 Housing (Amount) in crores 225.08 269.93 320.66 172.26 227.33 Physical Infrastructure 66.57 71.83 86.04 48.78 47.84 321.07 Social Infrastructure 7.93 7.92 11.01 8.32 8.45 43.64 Total (Housing + Infrastructure) : (A) 299.59 349.69 417.71 229.37 283.63 O & M Cost, DPR, PMC, Community mobilisation & (B) 26.96 31.47 37.59 20.64 25.53 142.20 Total Cost (C ) = (A) + (B) 326.55 381.16 455.30 250.01 309.16

5 SFCPoA Summary Note Investment Required and Phasing for Preventive
3 PREVENTIVE STRATEGY  Projected Housing Shortage for Urban Poor (15 years) 27110 Investment Required and Phasing for Preventive (Rs. in crores) Particulars 1st Phase ( ) 2nd Phase ( ) 3rd Phase ( ) 4th Phase ( ) 5th Phase ( ) Total Rs. Housing (Amount) in crores 256.48 284.57 284.62 Physical Infrastructure 25.56 28.36 28.37 139.01 Social Infrastructure 21.31 23.65 115.91 Total (Housing + Infrastructure) : (A) 303.35 336.58 336.64 O & M Cost, DPR, PMC, Community mobilisation & 9%: (B) 27.30 30.29 30.30 148.48 Total Cost (C )= (A) + (B) 330.66 366.87 366.94

6 SFCPoA Summary Note Investment Details (Figures in Crores) Particulars
Strategy Number of Units Housing Cost: (A) Physical and Social Infrastructure Cost: (B) Total Cost (C) = (A)+(B) O & M Cost, DPR, PMC, Community mobilisation & (D) Total Cost : (D) + (C ) Curative (new + up- gradation) 44674 364.71 142.20 Preventive 27110 254.93 148.48 Total 71784 619.64 290.68 Particulars Total Base Cost: (A) O & M Cost, DPR, PMC, Community mobilisation & (B) Total Funding Requirement (D) = (A) + (B) Housing 234.91 Infrastructure Requirement 619.64 55.77 675.41 Total 290.67

7 SFCPoA Summary Note Sharing Pattern
Sharing Pattern (In Percentage terms) Component MoHUPA State Government ULB Beneficiary Housing (Curative Strategy- Existing Slums) 75% 15% 0% 10% Infrastructure (Curative Strategy - Existing Slums) Housing (Preventive) Infrastructure (Preventive) Sharing Cost for the Curative & Preventive Strategy (in Rs. Crore) MoHUPA State Government ULB Beneficiary Total Housing 391.51 261.01   Infrastructure 464.73 92.95 61.96 619.63 O & M 4% 96.89 19.38 12.92 129.19 DPR, PMC & Community 3% 72.67 24.22 2% 48.45 16.15 64.59 576.51 91.03

8 METHODO-LOGY

9 TASK SCHEDULE SL NO TASK STATUS 1 IDENTIFICATION OF SLUMS Completed 2
PLOTTING OF SLUM BOUNDARIES 3 AUTHORISATION OF BOUNDARIES 4 PREPARATION OF GRID AND NO 5 PREPARATION OF SLUM CODE 6 GENERAL SLUM SURVEY/PROFILING 7 GIS MAPS FOR SLUMS 8 BASE MAP OF CITY 9 INCEPTION REPORT 10 SOCIO-ECONOMIC SURVEY OF SLUMS 11 DATA ENTRY ONLINE 12 DRAFT SFCPoA REPORT 13 PUBLIC PARTICIPATORY WORKSHOPS 14 FINAL SFCPoA REPORT

10 ENVIRONMENT BUILDING -“REACHING THE UNREACHED”.
Environment building through Workshops ULB Consultations Ward Representative Consultations ULB Participation in Capacity Building onsite at Slum Locations Ward Representative Participations General Meeting with majority dwellers- Focus Group Discussions Identification of CBO in slums Mapping Existing Slum Situations and Survey with the help of Community dwellers SLUM LEVEL WARD LEVEL

11 ENVIRONMENT BUILDING HANDOUTS FOR AWARENESS GENERATION
FOCUS GROUP DISCUSSIONS FOR SFCPOA, THE HANDOUTS SHALL BE PREPARED IN LOCAL LANGUAGE COMMUNITY PARTICIPATION IN SLUM MAPPING “People were assured that there would be no eviction”

12 CITY BASE MAP OF KORBA

13 SLUM SURVEY SLUM MAP – SANJAYNAGAR SLUM MAP – FIRE COLONY
The survey of slums can be broadly categorized into :- Spatial Survey - Identification, profiling Non-Spatial Survey - Socio-Economic Slum Mapping - Detailed slum map Spatial Survey- Slums Identification of Slums-Notified, Non notified and additional Slum boundary demarcation Slum profiling Field Survey to generate contours at 0.5 m interval Non Spatial Survey Socio Economic Survey Livelihood Survey GIS Participatory Survey Photographing each property Videography of Survey Slum Mapping Creation of a detailed Slum Map Integrating with GIS Inventory of Slums and Open areas Creation of Slum Redevelopment Plan

14 DIFFERENT TYPE OF REPORTS
GIS Mapping & Integration with MIS MIS HOMEPAGE SLUM WISE REPORT The MIS application and the GIS would be integrated using a unique house numbering system. Each house will be numbered as per the numbering convention below SLUM CODES For example Generation of unique ID for property will be done as under: Cities will be divided into 500x500 Grid. Grid number will be 0001,0002,0003……N Formula for UID: State ID + City Id + Grid No + Parcel No + Property No 2 Digit + 4 Digit + 4 Digit + 4 Digit + 3 Digit = 17 Digit Unique ID Ex. : = DIFFERENT TYPE OF REPORTS CITY LEVEL SLUM REPORT

15 City Level Maps Ward wise population Map Other maps prepared :- Existing Mode of Water Supply with respect to Location of Slums Primary Source of Water Supply in Korba with respect to Location of slum : Secondary source of Water Supply in Korba city with respect to location of Slums Sewerage disposal mechanism for Korba with respect to the location of Slums Open areas of the city where Sewage is disposed with respect to the location of Slums Existing and Proposed Sewerage system of Korba city with respect to location of slums Existing Storm water drainage of Korba city with respect to location of slums Flood prone areas of city with respect to location of Slums Open areas of the city where Solid waste is dumped with respect to the location of the Slums Existing Solid waste disposal mechanism in Korba city with respect to the location of Slums Access to Sanitation in Urban Poor Settlements of Korba city with respect to the location of Slums Areas used for Open Defecation in the city with respect to location of slums Land Value Maps

16 ZONE LEVEL ANALYSIS HH DENSITY IN KORBA SLUMS
HOUSES BY MATERIAL OF STRUCTURE SLUM HHs BY PRIMARY SOURCE OF WATER SUPPLY SLUM HHs BY AVAILABILITY OF TYPE OF TOILETS

17 CATEGORISATION OF SLUMS
Categorization of slums TENABILITY TENURE STATUS OF HHs LAND OWNERSHIP OF SLUMS DENSITY OF SLUMS LAND VALUE 3X3X3 MATRIX Tenability Analysis SL NO. TENABILITY NO. OF SLUMS 1 Tenable slums 67 2 Semi tenable slums 31 3 Untenable slums 18 Total 116 Land Ownership Analysis Population Density Analysis LAND OWNERSHIP STATUS OF SLUMS SL.NO SLUMS PUBLIC PRIVATE PSU Mixed land ownership (State/Railways/ Pvt./PSU) 1 NOTIFIED 29 8 25 2 NON NOTIFIED 23 3 12 NEWLY IDENTIFIED 5 7 TOTAL 53 11 42 10 SLUMS IN TERMS OF POPULATION DENSITY SL.NO POPULATION DENSITY NOTIFIED NON NOTIFIED NEWLY IDENTIFIED 1 0-500 33 20 10 2 26 21 3 TOTAL 62 41 13

18 INFRASTRUCTURE CONDITION SOCIO-ECONOMIC CONDITION
3X3X3 MATRIX ANALYSIS STEP 2 3X3X3 MATRIX: 3 PARAMETERS HOUSING CONDITION INFRASTRUCTURE CONDITION SOCIO-ECONOMIC CONDITION The 3X3X3 matrix is arrived at 3 stages EVALUATION OF PRIMARY SLUM SURVEY & SOCIO-ECONOMIC DATA STEP 1 WEIGHTAGES OF INDICATORS GENEARTION OF INDEX BASED ON EVALUATION OF PRIMARY SURVEY DATA Each Indicator has been assigned a weightage as per their priority. The weightages of the individual categories shall sum up to 100%

19 PRELIMINARY DEVELOPMENT OPTIONS
3X3X3 MATRIX ANALYSIS SL.NO CODES NO. OF SLUMS INFERENCE PRELIMINARY DEVELOPMENT OPTIONS 1 111 2 Sound in all condition Partial Infrastructure (Pucca drains) 211 7 Medium in Housing & Sound in others Housing & Infrastructure (Pucca drains) 3 112 Medium in Poverty & Sound in others Partial Infrastructure (Sanitation) 4 121 Medium in Infrastructure & Sound in others 5 212 6 Sound in Infrastructure & Medium in others 221 12 Sound in Poverty & Medium in others 122 13 Sound in Housing & Medium in others 8 323 Vulnerable in Housing & Poverty & Medium in Infrastructure Housing & Infrastructure (Sanitation) 9 113 Vulnerable in Poverty & Sound in others Partial Infrastructure (Water supply) 10 131 Vulnerable in Infrastructure & Sound in others Infrastructure (Water supply) 11 312 Vulnerable in Housing, Sound in Infrastructure & Medium in Poverty 321 Vulnerable in Housing, Medium in Infrastructure & Sound in Poverty Housing & Infrastructure (Water supply) 14 222 Medium in all Infrastructure (Sanitation) 15 123 Sound in Housing, Medium in Infrastructure & Vulnerable in Poverty 16 231 Medium in Housing, Vulnerable in Infrastructure & Sound in Poverty 17 132 Sound in Housing, Vulnerable in Infrastructure & Medium in Poverty 18 322 Vulnerable in Housing & Medium in others 21 313 Sound in Infrastructure & Vulnerable in others 22 331 Sound in Poverty & Vulnerable in others 23 233 Medium in Housing & Vulnerable in others 24 332 Vulnerable in Housing & Infrastructure & Medium in poverty 25 232 Medium in Housing & poverty & Vulnerable in infrastructure 26 333 Vulnerable in all TOTAL 26 codes 116 STEP 3 Weightage of indicators is multiplied by the index to generate final score SIMILAR EXERCISE HAS BEEN CONDUCTED FOR INFRASTRUCTURE AND SOCIO-ECONOMIC Range code 1 = Sound Condition Range code 2 = Medium Condition Range code 3 = Vulnerable Condition

20 SLUM LEVEL ANALYSIS Slum pockets with % of Kutcha stock
Slum with % of people engaged in Open defecation Slum with % of HHs having household monthly income less than Rs. 3000 Slum Pockets with % of BPL HHs

21 CENTRAL GOVERNMENT SUPPORT
PHASING & DEVELOPMENT MODELS PROPOSED DEVELOPMENT MODELS PHASING FOR IMPLEMENTATION PRIORITY In situ Slum Upgradation and Improvement (UP) = 30 SLUMS Slum Redevelopment (RD) = 65 SLUMS Slum Relocation and Resettlement (RR) = 18 SLUMS SL NO PHASING NO. OF SLUMS 1 FIRST ( ) 20 2 SECOND ( ) 26 3 THIRD ( ) 32 4 FOURTH ( ) 16 5 FIFTH ( ) 19 TOTAL 113 3 SLUMS: Parshabhata, Prem Nagar and Narai Bodh= PROPOSED TO BE DELISTED TYPE NO OF SLUMS TENABILITY OWNERSHIP SLUM TYPE ACTION AGENCY CENTRAL GOVERNMENT SUPPORT State/ ULB SUPPORT BENEFICIARY RR1 Partially Untenable Public Slums which are un tenable & may be relocated within zone on Redevelopment sites or Existing vacant affordable housing Provision of Housing & basic services to all households up to permissible density 50% Share in Housing & Infrastructure Cost 40% (20+20)Share in Housing & Infrastructure Cost 10% Contribution in housing Cost RR2 14 Untenable Slums which are un teneble & need to be relocated to Newly identified resettlement site within zone. Provision of Housing & basic services to all households & additional households from other untenable slums up to permissible density

22 CENTRAL GOVERNMENT SUPPORT
In-situ Upgradation & improvement Models TYPE NO. OF SLUMS TENABILITY OWNERSHIP SLUM TYPE ACTION AGENCY CENTRAL GOVERNMENT SUPPORT STATE/ ULB SUPPORT BENEFICIARY UP 1 15 Tenable & Partially Tenable Public Slums with predominantly pucca DU's & poor infrastructure Provision of Basic service to all Tenable Households, Gap Filling Housing for Kutcha Tenable Dwelling Units & Relocation for untenable Households 75% Share in infrastructure Cost & 75% interest subsidy on housing loan for upgradation of remaining kutcha/Semi pucca DU'S (15%+10%)Share in Infrastructure Cost Subsidised loan for incremental housing for remaining Semi pucca DU's, 10% share in Gap filling housing UP 2 Slums with predominantly pucca DU's & average infrastructure Subsidized loan for incremental housing for remaining Kutcha/Semi pucca DU's, 10% share in Gap filling housing

23 CENTRAL GOVERNMENT SUPPORT PRIVATE DEVELOPER ROLE
In-situ Redevelopment Models RD 4 1 Tenable & Partially Tenable High Public Slum with Predominantly Kutcha DU'S & Poor and average Infrastructure Provision of Housing & Basic Service to all Households, Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only. The Rest of the FAR up to permissible Density may be provided to Private partner for sale in open Market in the form of Built-up or TDR PPP Viability Gap Funding Land Availability, Zoning/FSI Incentives including TDR Bid based on No. of Free Houses(Owners hip/Rental) offered & benefit to private owner 10% Contribution in Housing & Infrastructure cost RD 5 2 Low & Medium Private Slum with Predominantly Kutcha DU'S & Poor and averageInfrastructure Provision of Housing & Basic Service to all Households,Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only.The Rest of the FAR up to permissible Density may be provided to Private partner for sale in open Market in the form of Built-up or TDR Land Availability,Zoning/FSI Incentives including TDR 10% Contribution in Housing & Infrastructure cost RD 6 Low Provision of Housing & Basic Service to all Households,Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only. 75% Share in housing & infrastructure cost 15% Share in housing & infrastructure cost 10% Contribution in Housing cost TYPE NO OF SLUM TENABILITY DENSITY LAND VALUE OWNERSHIP SLUM TYPE ACTION AGENCY CENTRAL GOVERNMENT SUPPORT State/ ULB SUPPORT PRIVATE DEVELOPER ROLE BENEFICIARY RD 1 50 Tenable & Partially Tenable Low & Medium Public Slum with Predominantly Kutcha DU'S & Poor and average Infrastructure Provision of Housing & Basic Service to all Households up to Permissible Density rest Households may be relocated. Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only 75% Share in housing & infrastructure cost 15% Share in housing & infrastructure cost 10% Contribution in Housing & Infrastructure cost RD 2 10 Medium High Slum with Predominantly Kutcha DU'S & Poor and averageInfrastructure Provision of Housing & Basic Service to all Households,Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only.The Rest of the FAR up to permissible Density may be provided to Private partner for sale in open Market in the form of Built-up or TDR PPP Viability Gap Funding Land Availability,Zoning/FSI Incentives including TDR Bid based on No. of Free Houses(Owners hip/Rental) offered 10% Contribution in Housing & Infrastructure cost RD 3 2 Provision of Housing & Basic Service to all Households up to Permisible Density rest Households may be relocated. Where more than 25% of Households or 50 Households(which ever is low)are living in Pucca Households For which pucca Tenable DU,S will be provided with basic services only

24 TOTAL VALUE OF RECLAIMED LAND = 373.17 Crores
Strategies for slums on Central Govt. Land The land owning agencies will have the discretion to prepare DPR on its own or in partnership with Central government, State and KMC. In case, DPR is prepared by the land owning agency on its own and no State share is envisaged, then DPR may be directly submitted for consideration to the Ministry. Funding pattern and process involved would be similar to those applicable for the State under RAY. For development of slums on Railway, NTPC and SECL land, needs co-ordination of Central government i.e. MoHUPA. For slums on CSEB, State government will be the facilitator and For Balco, coordinated activity required among Central govt, State govt and Vedanta group. Korba Municipal Corporation will be the prime facilitator for coordination among the various authorities. The total number of slums in PSU land in Korba is 42, out of which 28 are on SECL Land, 9 on CSEB land and 5 slums are on Balco land. TOTAL LAND THAT CAN BE RECLAIMED BY PSUs FROM REDEVELOPING SLUMS = Hectares TOTAL VALUE OF RECLAIMED LAND = Crores

25 HOUSING SCENARIO Estimation of existing housing shortage
Projection of Housing shortage YEAR HOUSING SHORTAGE INCREMENT 1991 11065 2001 26354 -15289 2011 22118 4236 TOTAL INCREMENT -11053 HOUSING SHORTAGE=HOUSING NEED 80% OF TOTAL HOUSING SHORTAGE LIES IN EWS & LIG CATEGORY (Assumed) As 70% of the total household of Korba is Slum household. 12710 HHs are Kutcha stock under Curative strategy Pn= P1 + n X (-5527) P 2021 = 16591 P 2031 = 11064 Projected Housing need for ESW/LIG YEAR 2011 2021 2031 PROJECTED HOUSING NEED FOR EWS/LIG (Dwelling Units) 17695 13273 8852

26 Preventive strategy Arrest the formation of Slums in the future.
HOUSING NEED / SHORTAGE YEAR 2015 2021 2031 PROJECTED HOUSING NEED FOR EWS/LIG (DU) ( )=4985 13273 8852 LAND REQUIREMENT (Hectares) 8.34 22.12 14.75 IDENTIFIED VACANT LAND AFFORDABLE HOUSING OPTIONS P1- Creation of Affordable housing stock for the urban poor by increasing the supply of housing based on the housing need of EWS and LIG through Public housing schemes. P2- Modifications in Town Planning Regulations Inclusion of Pro poor policies in Master Plan or Development Plan. Special Norms and standards for plots and DU Size, Density, FAR, Ground Coverage, etc Review and Modification of Bhumi Vikas Niyam of 1984. Special Building Byelaws for Low income Housing to be formulated. Every new housing project in the city will have reservation of 15% of residential F.A.R or 35% of dwelling units for EWS/LIG whichever is higher with a system of cross subsidisation. Proper formulation and monitoring of the disposal policy of Public Housing Scheme to ensure proper disposal to the target group (EWS and LIG). P3- Implementation of Legislation like introduction of TDR in State Housing Policy, Social Rental Housing policy, amendment in existing Rent Control Act etc. Parcel 1: Transport nagar zone with an area of 5.91 Hectares Parcel 2: Transport nagar main road with an area of Hectares Parcel 3: along Korba-Rajgamar road in Kosabari zone with an area of Hectares

27 Preventive strategy Income-Expenditure Profile of Urban Poor
 [M1]Point 5 Income-Expenditure Profile of Urban Poor SL NO CATEGORY (in Rs.) Total No.of Households <2000 >8000 1 Average Monthly Income of slum Household 7174 17220 4453 3840 1269 2377 36505 20% 47% 12% 11% 3% 7% 100% 2 Average Monthly Expenditure of slum Household 8789 17675 3531 2106 2052 2180 24% 48% 10% 6% Assessment of Affordability of Urban Poor SOCIO ECONOMIC STATUS AMOUNT REMARKS % HHs Avg. Monthly Income Rs 3500 33 Avg. min. Monthly Expenditure Rs 2800 78 Avg. expenditure on maintenance of house(annually) Rs 1500 Excluding property tax and rent, including repair, maintenance, etc Avg. rent Rs 500 Varies as per the location of the slum AVG. BPL POPULATION IN SLUMS 35% Unable to afford Housing 33% of slum households has an average monthly income of Rs 3500 whereas 78% households has average monthly expenditure of Rs Thus the affordability of people is an average of Rs per monthly towards minimum formal housing.

28 Preventive strategy Future Affordable Housing Supply
Central support = Rs 75,000 per EWS/LIG DUs of size upto 40 sqm for housing and internal development components A project size of minimum 250 dwelling units will be considered under the scheme. The DUs would be a mix of EWS/LIG-A/LIG-B/Higher Categories/Commercial of which at least 60 percent of the FAR/ FSI will be used for dwelling units of carpet area of not more than 60 sqm. Currently, the average subsidized cost of a 25 sqm carpet area, DU for the EWS in Korba is around 3.50 lakhs. The carpet area of the LIG has been proposed as 40 sqm and the cost is around 7 lakhs. COSTING & PRICING OF DWELLING UNITS UNDER AFFPRDABLE HOUSING EWS LIG Cost of DU (Rs) 350000 700000 Price of DU (Rs) 500000 900000 Central Govt. share (Rs) 75000 Beneficiary share (Rs) 425000 825000 Implementing agency State Housing Board & ULB Mode of Implementation PPP Beneficiary share Subsidised Loan under RRY

29 Number of Years of Stay in this Town/City
Preventive strategy Social Rental Housing EXISTING TREND IN RENTAL HOUSING AS PER MIGRATION PATTERN Sl.No Total no.of Households Total no. of Rental HHs Number of Years of Stay in this Town/City 0-1 1 to 3 3 to 5 > 5 years 1 36505 8488 337 323 241 7587 23% 4% 3% 89% 2 Place of Migration Pattern of Migration Rural to Urban Urban to Urban Others Seasonal Permanent NO. OF HHs 4276 2611 1601 699 6188 % of Total Rental HHs 50% 31% 19% 8% 73% PROPOSED O&M MODELS PROPOSED LEGAL FRAMEWORK Surplus model: Management companies will bid competitively to maintain rental homes. The company that offers the highest share of their revenue to KMC will win. Lease model: Rental management companies lease the properties from KMC for 99 years for a lease premium. License model: In this model, rental management companies pay a license fee to manage the rental housing for 9-10 years. Introduction of Social Rental Housing into the Chhattisgarh State Housing Policy Amendment of Rent Control Act and Municipal Act. Introduction of a new state level institution in the form of Chhattisgarh Social Housing Corporation (CSHC) to be established who will regulate and monitor the Social Housing schemes in various cities of the State. The Municipal Corporation can tackle the challenge of raising funds for provision of Social Rental Housing by using the revenues from the sale of upmarket houses as an investment in a rental housing project. Cross subsidisation, has been proposed for the implementation of this project.

30 EXISTING POPULATION DENSITY (PPh)
Preventive strategy Social Rental Housing WARDS IDENTIFIED FOR PROVISION OF FUTURE RENTAL HOUISNG SL NO. WARD NO. WARD NAME AREA (ha) POPULATION EXISTING POPULATION DENSITY (PPh) 1 6 Bhilai Khurde Imli Duggi 1738 6974 4 2 11 Chhattisgarh Rajya Vidyut Mandal 1 329 4849 15 3 17 Maharana Pratap Nagar 180 5857 33 20 S.E.C.L. Colony 211 5246 25 5 29 Balko Nagar No. 2 47 4237 90 Lalghat 612 6744 7 40 Jaminipali 1298 6936 8 44 Darrikhar 720 7902 9 45 Sarvamangla Nagar 805 6606 One Special Purpose Vehicle (SPV) to be formed in association with Private or Government or Semi Government along with Korba Municipal Corporation.

31 Supply & Demand side Constraints
SUPPLY SIDE CONSTRAINT To increase Land Supply and Availability- (i) Creation of Land Banks / Land sharing through TP schemes (ii) Monitoring mechanisms for 20-25% land reservation for EWS/LIG (iii)Relaxation of Building regulations in the Master Plan To ease approval processes -Fast Track layout approval systems for slum DPRs and affordable housing projects (within 30 days) and ease in Building Plan sanction for EWS/LIG projects. To ease Building Rules and increase Rental Housing Supply -Optimize building rules: IS8888 for buildings and National Building Code 2005 & Rental Housing Reforms as per National Housing and Habitat Policy, 2007/Reduced property taxes, for rental housing for the urban poor, higher FSI for rental housing projects and PPP Projects. DEMAND SIDE CONSTRAINT Increasing affordability and accessibility, Encourage MFIs, Ease credit linkages

32 Proposed Investment under SFCPoA
SL NO PHASING IN YEARS CURATIVE: COST REQUIREMENT FOR EXISITNG SLUMS(Rs) HOUSING (A) PHYSICAL INFRASTRUCTURE (B) SOCIAL INFRASTRUCTURE © TOTAL COST X= (A+B+C) DPR & PMC, Community TOTAL PROJECT COST W 1 First 225.08 66.57 7.93 299.59 11.98 8.99 5.99 326.55 2 Second 269.93 71.83 7.92 349.69 13.99 10.49 6.99 381.16 3 Third 320.66 86.04 11.01 417.71 16.71 12.53 8.35 455.30 4 Fourth 172.26 48.78 8.32 229.37 9.17 6.88 4.59 250.01 5 Fifth 227.33 47.84 8.45 283.63 11.35 8.51 5.67 309.16 TOTAL 321.07 43.64 63.20 47.40 31.60 PREVENTIVE: COST REQUIREMENT FOR AFFORDABLE HOUSING (Rs) HOUSING (A') PHYSICAL INFRASTRUCTURE (B') SOCIAL INFRASTRUCTURE (C') TOTAL COST X'= (A'+B'+C') TOTAL PROJECT COST W' 256.48 25.56 21.31 303.35 12.13 9.10 6.07 330.66 284.57 28.36 23.65 336.58 13.46 10.10 6.73 366.87 284.62 28.37 336.64 13.47 366.94 139.01 115.91 65.99 49.49 32.99 TOTAL PROJECT COST UNDER SFCPoA (W+W')=

33 FINANCIAL BREAKUP OF PROJECT COST
PROPOSED FINANCING PLAN FINANCIAL BREAKUP OF PROJECT COST Centre(%) State(%) ULB(%) Beneficiary (%) Housing 75 15 10 Infrastructure Central Govt. Share: 75% on Housing, Infrastructure, DPR preparation, O&M & Consultancy fees State Govt. Share: 15% on Housing, 15% for Infrastructure ULB Share: 15% on Infrastructure Beneficiary Contribution: 10% on Housing. For slums on PSU Land, PSU has to prepare and submit a proposal for DPR as per SFCPOA recommendations and submit it to Central Govt, where share of fund to be decided among PSU & Central Govt. PROPOSED O&M PLAN RWAs and CBOs has been formed from each slums through Microplanning conducted in each slum will be responsible for effective Operation and Maintenance of created assests.

34 INVESTMENT REQUIREMENT (Rs)
Proposed Financing Plan SL NO PHASING IN YEARS INVESTMENT REQUIREMENT (Rs) TOTAL HOUSING INFRASTRUCTURE (PHYSICAL+SOCIAL) Central Govt State Govt ULB Beneficiary 75% 15% 0% 10% 1 FIRST 361.17 72.23 0.00 48.16 481.56 91.03 18.21 12.14 121.38 2 SECOND 415.88 83.18 55.45 554.50 98.83 19.77 13.18 131.77 3 THIRD 453.92 90.78 60.52 605.23 111.79 22.36 14.91 149.06 4 FOURTH 342.63 68.53 45.68 456.83 81.84 16.37 10.91 109.11 5 FIFTH 383.97 76.79 51.20 511.96 81.24 16.25 10.83 108.31 TOTAL SHARE 391.51 261.01 464.73 92.95 61.96 619.63 O&M DPR & PMC & Community Mobilisation 25% 18.09 3.62 2.41 24.12 13.57 4.52 20.59 4.12 2.75 27.45 15.44 5.15 22.63 4.53 3.02 30.17 16.97 5.66 16.98 3.40 2.26 22.64 12.73 4.24 18.61 3.72 2.48 24.81 13.96 4.65 96.89 19.38 12.92 129.19 72.67 24.22 A&OE 9.04 3.01 12.06 10.29 3.43 13.73 11.31 3.77 15.09 8.49 2.83 11.32 9.30 3.10 12.41 48.45 16.15 64.59

35 Proposed Credit Plan Credit Plan has been formulated based on two options Loans from Formal Institutes at 10% interest rate and Availing subsidized loan under RRY & CRGF. COST OF DWELLING UNIT Current HH Monthly income = Rs Cost of DU = Rs. 3,50,000/- Central Govt. share = Rs. 2,62,500 State Govt. share = Rs. 52,500 Beneficiary contribution = Rs. 35,000 CALCULATION OF EMI IN CASE OF BANK FINANCE PROPOSED CREDIT PLAN Compound interest method of calculating the EMI for the housing loan repayment option, at a 10% interest rate for loan tenure of 5 years or 60 months, the monthly EMI is calculated as Rs. 744. The total interest payable is Rs which is 21.56% of the total payment to be made. The Principle loan amount of Rs. 35,000 makes for the rest of the 78.44% of the total payable amount for the bank which is calculated to be Rs. 44,619. Year Principal (A) Interest (B) Total Payment (A+B) Balance Loan Paid to Date EMI Y 1 5679 3244 8923 29321 16% 744 Y 2 6274 2650 8924 23047 18% Y 3 6931 1993 16116 20% Y 4 7657 1267 8459 22% Y 5 465 24%

36 Reform Matrix MANDATORY REFORMS SL NO REFORMS YEAR 1 (2013- 2014)
Commitment and willingness to assign mortgageable and renewable long term (15 years) inheritable lease rights to slum dwellers who have been a resident of the slum for more than 5 years 2 Reservation of 15% of residential FAR/FSI or 35% of dwelling units for EWS/LIG whichever is higher with a system of cross subsidisation in all future housing projects. 3 A non-lapsable earmarking of 25% of the budget of the Municipality to provide basic services to the urban poor 4 Creating and establishing municipal cadre for social/community development and urban poverty alleviation during the plan period.

37 Reform Matrix OPTIONAL REFORMS SL NO REFORMS YEAR 1 (2013- 2014)
Formulation of State Policy for Affordability Housing 2 Amendments of Master Plan to provide for inclusive growth through inclusionary zoning and other measures for inclusive development 3 Simplification of the processes and procedures of sanctioning buildings and building byelaws concerning development and housing projects to provide single window based quick approvals in order to reduce transaction costs 4 Amendments in the Rent Control Act balancing the interest of landlords and tenants

38 Proposed Responsibility Matrix

39 Proposed Institutional Framework
STATE LEVEL: SUDA ULB LEVEL: KMC

40 CAPACITY BUILDING PLAN
COMMUNITY LEVEL CAPACITY BUILDING PLAN Government of Chhattisgarh has planned a Capacity Building Program named National Institution of Urban Management to impart skill training to the various public agencies and authorities towards successful implementation of RAY Slum level Associations have been identified during SFCPoA preparation from each slum having atleast 10 people needs to be registered. The lead members of these Associations will then collectively form a Federation or Community Based Organisation In order to enhance the capacity of these Associations and Organisations planned outdoor visits have to be arranged to showcase best practices in Community participation for Slum development like in Chennai, Madurai, Mumbai etc.

41 Thank You