1 USACE TEAM APG APG/C4ISR BRAC UPDATE SAME-Regional Event LTC Thomas Tickner CPT BJ Kraemer

2 USACE TEAM APG Location: Aberdeen Scope: ~650,000 SF of new high-tech, electronics-communications R&D facility Delivery Method: DBB AE: Ewing Cole C2/CNT East CWE: $150-200M Advertise: 26 Jan 09 Bid Opening: 7 Apr 09 Award: 21 Apr 09 Status: Advertised. Building turnover 31 Dec 10, site work complete Aug 11. Early Site Package awarded 3 Feb 09 for $2M and Magazine Road awarded 27 Feb 09 for $0.4M to clear C2/CNT East footprint. C4ISR Phase 2 – C2/CNT East

3 USACE TEAM APG Location: Aberdeen Scope: ~140,000 SF of new integration, fabrication and research and development facility Delivery Method: DBB AE: Jacobs Consolidated North CWE: $40-60M Advertise: 11 Jun 09 Bid Opening: 24 Jul 09 Award: 7 Aug 09 Status: 95% Design due 30 Apr 09. Building turnover 31 Dec 10. Consolidated North

4 USACE TEAM APG Location: Aberdeen Scope: ~109,000 SF of adaptive re-use space for integration, fabrication and research and development facility Delivery Method: DBB AE: Jacobs Bldg 5100 CWE: $15-30M Advertise: 18 Jun 09 Bid Opening: 31 Jul 09 Award: 14 Aug 09 Status: 95% Design due 7 May 09. OCS footprint clears 30 Sep 09. Building turnover 31 Dec 10. Building 5100

5 USACE TEAM APG Location: Aberdeen Scope: ~98,000 SF of satellite engineering and research and development facility Delivery Method: DBB AE: USACE JSEC CWE: $30-50M Advertise: 2 Jul 09 Bid Opening: 14 Aug 09 Award: 28 Aug 09 Status: 95% Design due 21 May 09. Building turnover 31 Dec 10. JSEC (Joint Satellite Engineering Center)

6 USACE TEAM APG Location: Aberdeen Scope: ~85,000 SF of new integration and fabrication facility Delivery Method: DBB AE: Jacobs Integration Facility CWE: $5-15M Advertise: 15 Dec 09 Bid Opening: 15 Feb 10 Award: 15 Apr 10 Status: 35% Design received 25 Mar 09. OCS footprint clears 30 Sep 10. Building turnover 30 Jun 11. Integration Facility

7 USACE TEAM APG Location: Aberdeen Scope: Electrical Distribution & Substation, Water & Sewer and Roadway/Intersection Improvements within the Phase 2 footprint Delivery Method: DBB AE: Jacobs Site/Utilities CWE: $15-30M Status: Multiple solicitation packages. Electrical Substation & Distribution 95% Design due 1 Jun 09. Water & Sewer 95% Design due 24 Apr 09. Roadway improvements within Phase 2 project area 95% design due 25 May 09. C4ISR Phase 2 – Site/Utilities