EnPro Restricted 1 Fukushima FLEX Considerations Ted Stevenson Manager, Nuclear Sales.

Similar presentations


Presentation on theme: "EnPro Restricted 1 Fukushima FLEX Considerations Ted Stevenson Manager, Nuclear Sales."— Presentation transcript:

1 EnPro Restricted 1 Fukushima FLEX Considerations Ted Stevenson Manager, Nuclear Sales

2 EnPro Restricted Fukushima FLEX Considerations What is FLEX ? In the wake of Fukushima, NRC established the need for DIVERSE AND FLEXIBLE COPING STATEGIES (FLEX) NEI (Nuclear Energy Institute) created IMPLEMENTATION GUIDE 12-06

3 EnPro Restricted Fukushima FLEX Considerations

4 EnPro Restricted Fukushima FLEX Considerations

5 EnPro Restricted Fukushima FLEX Considerations

6 EnPro Restricted Fukushima FLEX Considerations

7 EnPro Restricted Fukushima FLEX Considerations

8 EnPro Restricted Fukushima FLEX Considerations FLEX CONSIDERATIONS - need water - need electricity - need portability FLEX SPECIFICATIONS - in process (not yet finalized)

9 EnPro Restricted Fukushima FLEX Considerations EVOLUTION OF FLEX OFFERING BY FAIRBANKS MORSE

10 EnPro Restricted Brasil-Angra 1&2

11 EnPro Restricted Fukushima FLEX Considerations ANGRA 2 has been operating since 2000 and has has (4) EDG’s + (4) 870KW engine+generator+speed increaser+pump ANGRA 3 is under construction and needs the same

12 EnPro Restricted Fukushima FLEX Considerations

13 EnPro Restricted

14

15 Fukushima FLEX Considerations Existing Angra Unit 2 equipment is obsolete FM has been solicited to provide replacements for Angra Unit 3

16 EnPro Restricted Fukushima FLEX Considerations FM currently working on a government program that uses a 1MW genset that meets waterproof and high shock (70g) requirements

17 EnPro Restricted OP – 6 CYL – 1MW

18 EnPro Restricted Fukushima FLEX Considerations FM also working on commercial pumping project in South America that pumps crude oil over a mountain range to a sea port

19 EnPro Restricted Fukushima FLEX Considerations

20 EnPro Restricted Fukushima FLEX Considerations

21 EnPro Restricted Fukushima FLEX Considerations

22 EnPro Restricted Fukushima FLEX Considerations FM extended these basic arrangements to meet the Angra configuration requirements

23 EnPro Restricted

24

25

26 Fukushima FLEX Considerations ANGRA DESIGN CONSIDERATION Building designed to withstand flooding and has limited waterproof access openings (12’ x 12’)

27 EnPro Restricted Fukushima FLEX Considerations EQUIPMENT NEEDS TO GET SMALLER Answer - MODULARIZATION

28 EnPro Restricted Fukushima FLEX Considerations 6 cylinder OP (50 OP’s currently in nuclear service)

29 EnPro Restricted Fukushima FLEX Considerations

30 EnPro Restricted Fukushima FLEX Considerations 6 cylinder ALCO (30 ALCO’s currently in nuclear service)

31 EnPro Restricted Fukushima FLEX Considerations

32 EnPro Restricted Fukushima FLEX Considerations 8 cylinder ALCO (30 in nuclear service)

33 EnPro Restricted Fukushima FLEX Considerations

34 EnPro Restricted Fukushima FLEX Considerations

35 EnPro Restricted Fukushima FLEX Considerations

36 EnPro Restricted Fukushima FLEX Considerations

37 EnPro Restricted Fukushima FLEX Considerations Modular configuration allows ability to MIX-AND-MATCH as desired for: - type engine - size engine - size generator - size pump - auxiliary configuration

38 EnPro Restricted Fukushima FLEX Considerations Modular arrangement allows multiple configurations to suit varying demands at each site - engine+generator - engine+ pump - engine+generator+pump - 1MW-3MW

39 EnPro Restricted Fukushima FLEX Considerations

40 EnPro Restricted Fukushima FLEX Considerations In addition to modular capability, FM offering also provides the following: -QA (ISO or NQA-1) -Qualifications (seismic/shock) -Waterproof/Resistant

41 EnPro Restricted Fukushima FLEX Considerations FM will provide either an engineered package (to customer specs) or will provide a pre-engineered package (to FM specs)