1 I-39, CTH B Interchange Village of Plover Portage County Project ID July 30, 2013

2 Your Presenters NAMEROLEEXPERIENCE Phil Roberts, PEEngineering Div. Manager28 years Dave Gale, PEProject Manager30 years Judy Wilson, PEStructural Engr.__ years Chris Nies, PETraffic Staging Engr.11 years Carrie Bristoll-Groll, PEStormwater Engr.19 years

3 Describe your team’s makeup, roles, and relative experience; and how sub- consultants fit into the project team. QUESTION 2 (Question 1 to follow)

4 2. Your Project Team BOLES WARNER TITLE, INC.

5 2. Project Team Roles I-39, CTH B Project Team

6 2. Project Team Roles & Experience

7  OMNNI - Project Manager: Dave Gale, PE  Responsible for coordinating project, scope, budget and timeframes  30 years of experience in all aspects of projects  Completed projects in all WisDOT regions  Relevant experience – USH 45/CTH T Interchange and I-39 Projects  Structure project experience  Experience with multi-discipline projects 2. Project Team Roles & Experience

8  OMNNI - Structural Design: Judy Wilson, PE  Responsible for structure design, SSR’s, and coordination with Bureau of Structures  __ years of PM and structure design experience  Relevant experience – I-39/Reserve St. and _____________  As PM, understands the project development process. 2. Project Team Roles & Experience

9

10  CORRE - Traffic Control Engineers: Dennis Olson & Chris Nies, PE  Combined 45 years of experience  WisDOT SW Region Traffic Management specialist  Developed and reviewed traffic control/construction staging plans  Relevant experience in interstate traffic phasing – I-39 at STH 153, I-39 at Patton Road, USH 12  Experience with TMP’s, IMP’s, etc. 2. Project Team Roles & Experience

11

12  Stormwater Solutions Engineering – Stormwater Management: Carrie Bristoll-Groll & Gretchen Galstad, PE  Combined 38 years of experience  Specialized in stormwater management  Experience in SE and NE Regions  Relevant stormwater experience I-94 N/S Team, US-41 Brown Co 2. Project Team Roles & Experience

13

14 BOWLES WARNER TITLE INC.

15  Experienced Staff - 8 to 34 years  Full-Service Capabilities  Experienced with multi-disciplined projects  Relevant experience  Experience taking 30% plans completion  Fully understand the project 2. Project Team Roles & Experience

16 Describe your teams qualifications, experience with similar projects, and familiarity with the design and traffic staging criteria of this project. QUESTION 1

17  Similar Projects 1. Qualifications & Experience USH 45 & CTH T Interchange I-39/ Reserve St. USH 53 & CTH B Interchange STH 22/54 & USH 10 Interchange USH 41 (Mason, Morris, Lombardi) I-39 (STH 54 – N. 2 nd St.) STH 29 Beam Guard

18  Similar Projects 1. Qualifications & Experience I-94 N/S Freeway USH 41 (Memorial to Lineville) I-39/ STH 153 I-39/ Patton Road USH 12/ Fish Hatchery Road STH 241 Lighting Hoan Bridge Lighting STH 32 RR Coordination

19  USH 45/ CTH T Interchange – NE Region New Interchange - Master Contract w/ NE Region - 40% plan PS&E - New interchange of CTH T over USH 45 - New ramps tying into existing USH 45 - Expansion of CTH T to 4-lanes - Environmental document re-evaluation - Fast Track 1. Qualifications & Experience

20  I-39/ STH 153 Interchange – NC Region Interchange Reconstr.- Staging - Replacement of concrete decks - Deck widening - Temporary construction - Developed 7 alternatives Key Staff Similarities with this project 1. Qualifications & Experience

21  I-94 N/S Freeway – SE Region Freeway Reconstr.- Stormwater Mgmt. - Drainage design engineer for the corridor - 3 interchanges - 9 detention/retention pond designs - Use of native landscaping 1. Qualifications & Experience

22  I-39 Corridor Study  Identified operational and safety concerns on the corridor  Identify, develop, and design freeway and interchange enhancements  Freeway improvements  Bridge rehab and replacement  Interchange reconfigurations 1. Project Understanding

23  CTH B Interchange Improvements Purpose and Need  Crash history on NB ramp at I-39 merge  Steep NB entrance ramp grade  I-39 clearance issues over CTH B  Ramp terminal capacity and traffic control improvements req’d to meet future LOS 1. Project Understanding

24  CTH B Interchange Improvements Concept  Utilize the current study information to develop the proposed improvements  Develop the 30% plans final PS&E  Supplement the environmental document as required (similar to USH 45)  Design to satisfy the purpose and need 1. Project Understanding

25  Project Understanding  Multi-disciplined Project: 1. Project Understanding Freeway DesignIntersection Design Urban Roadway DesignPublic Involvement Rural Roadway DesignSurvey Structure DesignTPP’s EnvironmentalTraffic Signals Hazardous MaterialsLighting WetlandsGeotechnical Stormwater ManagementCSD Traffic Control/StagingRailroad

26  Overall concept  Reconfigure to a loop ramp  Use new ramps for traffic control during I-39 construction  Construct new structures w/ adequate clearance  Evaluate impacts to I-39 and CTH B and develop plans accordingly (env. doc. dependent) 1. Project Understanding

27  Overall concept  Design new ramp termini with traffic signals  Accommodate stormwater effectively  Provide street lighting  Profile/ project extent 1. Project Understanding

28  Structures  Ramp structures  Clearance  Etc. 1. Project Understanding Judy- Delete this slide??

29 1. Project Understanding - Structures  Existing Bridge – I39 over CTH B  45” PPC Girders + 7” Slab  Desired Vertical Clearance  16’3”  Need 16” additional clearance  OPTION 1 - Propose 2 spans with 36W” Girders – gain 6” clearance  OPTION 2 - Propose 2 spans with 28” Girders & MSE abutments – gain 14” clearance  Steel Girders L/D ratio; Need 36” steel girder for 90’ span

30 1. Project Understanding  Existing Bridge – I 39 over CN RR 36” PPC Girders + 7” Slab  Existing Vertical Clearance – 23’-1”  New Ramp Bridge spans 49.5 – 70’ – 49.5  OPTION W” PPC girders  OPTION 2 – Concrete Slab Span  OPTION 3 – Steel Girders

31 1. Project Understanding

32 Possible reconstruction of NB & SB Mainline Bridges over CN RR Construct New Entrance Ramp Bridges to Accommodate 2 Lanes Reconstruct NB & SB Mainline Bridges over CTH B

33  Traffic Control and Construction Staging  Staging Concept  Maintain 2-lanes  I-39 Concept  Alternatives  Issue Areas  Ramp closures  Ramp conflict areas  Construction staging area and access issues 1. Project Understanding CORRE to modify this slode??

34  Stormwater Management  Large basin size  Etc. 1. Project Understanding To be developed by Carrie- Monday

35  Ramp Termini  Reconfigure ramp termini to current standards  Add signals  Impact to DelMonte  Drive location  Site circulation  FE access to the south 1. Project Understanding

36  CTH B Construction  Impacts & limits defined by structure clearance  Accommodate Trans 75 thru MSE walls/abutments?  Coordinate with local government officials regarding lighting and CSD items to match those on the west side  Impacts to local businesses 1. Project Understanding

37  Miscellaneous Issues  Railroad Coordination  Spur track to DelMonte  Clearance during construction  Railroad Crossing Report  Tomorrow River Bike Trail accommodations 1. Project Understanding

38 Describe your teams project management and quality control methods. QUESTION 3

39  Five key elements to Project Management  Initiate  Plan  Execute  Monitor and Control  Close 3. Project Management/QC

40  Five key elements to Project Management  Project Charter  Initiate  Plan  Execute  Monitor and Control  Close 3. Project Management/QC

41  Five key elements to Project Management  Project Charter  Initiate  Plan  Execute  Project Quality Plan  Monitor and Control  Close 3. Project Management/QC

42 Add info Need anything else????

43 Describe your teams public involvement experience and those involved in the process. QUESTION 4

44  Build upon WisDOT’s process to-date  Study concept, timeframe, initial public input  Develop a sound design that analyzes issues and develops credible solutions  Evaluate impacts to businesses & public  Present information appropriately 4. Public Involvement

45  Present information appropriately  Competent team  Present to appropriate people, at appropriate time and format  Develop consensus based on both project and community needs: State and Local OfficialsAgencies BusinessesLandowners  Listen, empathy, & build trust  Open to public concerns  Design adjustments 4. Public Involvement

46 Describe any other expertise or assets pertinent to the success of this project. QUESTION 5

47  Team members have experience in most phases of improvement projects  Geotechnical Expertise  Experience working with drillers (GDC)  Materials Testing Lab  Experienced Geotechnical Engineers  Real Estate Capabilities  5 negotiators and 2 appraisers on-staff and available  Helps to address irrigation and other issues 5. Other Expertise

48  Quality Assurance/Control  Experienced with the NC Region Review Process  Regular team member meetings  Weekly staff meetings  PM Review  Quality Control Reviews  Constructability Reviews 5. Other Expertise

49  Experience 30% plan PS&E  Experience + Mentoring = NC Region Success 5. Other Expertise USH 45/CTH TCTH G STH 17I-94 N/S Freeway Lawe StreetUSH 12 Greenway Blvd Int. STH 116 Wolf River Bridge & Approaches

50  Experience  Staff  Similar Projects  Availability  Civil 3D Ready  We would like to work with you on this project!! Why Select the OMNNI Team?