WER Clarity Migration Plan As of 11/14/2011 Doug Smith.

Similar presentations


Presentation on theme: "WER Clarity Migration Plan As of 11/14/2011 Doug Smith."— Presentation transcript:

1 WER Clarity Migration Plan As of 11/14/2011 Doug Smith

2 Overview of the Four Phases WER Dev Refresh completes 11/22/2011 Migration WER Dev to CSIT/UAT 1/10/2012 Production 1 (inactive data) 1/19/2012 Production 2 (active data) 2/14/2012 Staff is committed part time as available and daily production responsibilities will have priority

3 Refresh WER Dev Refresh Dev from WER Prod with comparison of MSP, financials and reports Testing includes the rebuilding of the “stored” MS project plans Completes on 11/22/2011

4 WER Dev migration to CSIT Staging Assumptions: Dev refresh testing completes on 11/22 Thanksgiving blackout 11/23 to 11/27- no work Migration 11/28-12/8, UAT 12/8-12/16 resuming 1/2/2012-1/10/2012

5 WER UAT Details After data is moved to CSIT staging, WER UAT proceeds UAT stops 12/16 when resources go on PTO and restarts in 1/2 and completes 1/10

6 Production Phase 1 – inactive data No outage is involved Migration of inactive data

7 Production Phase 2 –active data The Production migration of active data has a 3 day outage on 2/9 – 2/11 for both WER and WWC environments Validation to be performed by all Business Unit Clarity Functional admins on 2/12 In service Monday 2/13

8 Final day activities - details By 3pm on 2/12 production validation starts for validation WER, WHG and WVO By 8pm on 2/12 final go/no go

9 Proprietary Content Proprietary Content Omitted