Presentation is loading. Please wait.

Presentation is loading. Please wait.

Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab.

Similar presentations


Presentation on theme: "Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab."— Presentation transcript:

1 Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab

2 2 Outline Two IR Access configurations being considered for Kitakami site Baseline HT (Horizontal Tunnel) to Large IR Hall Hybrid VS (Vertical Shaft) + HT (small diameter) to Smaller IR Hall Realization that more discussion and SiD input needed on Assembly area requirements Central campus requirements Detector assembly model - Is “CMS” model “agreement” still valid or useful Consequences if beam commissioning required before detector can be on beamline Practical details: Maximum size & weight of truck delivered loads - Yoke sections for SiD - ILD Coil Manufacturing

3 3 History & Context ILC RDR assumes HT access to underground hall for “Japanese Mountain Site” (either Kitakami or Sefuri candidate sites) with detectors assembled below ground By November 2013 Tokyo LCWS meeting, Kitakami site chosen and ILD colleagues note that site is not as mountainous as Sefuri and may accommodate a vertical shaft Site specific access study requested Series of CFS (Conv. Fac.), ADI (Accel. Design & Integration) and MDI CTG (Common Task Group, chaired by K. Buesser) meetings February-April with cost/schedule analysis by JPower firm Eliminate 5 shaft (ILC America’s Baseline) Vertical Access option Look at several Hybrid VS/HT variants CFS/ADI/MDICTG/ILC Mgmt meeting at U. Tokyo (& site visit) 7-10 April 2014 Urgency for decision: Order bore samples, impact on global ILC design, land acquisition … Decision is to go forward with scheme that has 18m shaft over the IP, minimal hall & underground crane size, 10m elevator/utility shaft, 8m diameter 10% grade tunnel (to be optimized), assembly hall and tunnel entrance over the shaft

4 Case Outlines HT access (baseline)VS accessHT & VS access 1 HT (Large size 7% grad tunnel) Detector assembling is inside of DH 5 VS Detector assembling is on-ground. 1 HT (mid size tunnel) and 2 VSs Detector assembling is on-ground. DH size is larger Vol:175,000m3 L144m H42m W25m with Alcoves DH size is smaller Vol:143,000m3 Z-shape DH size is smaller Vol:128,000m3 L108m H40m W25m with Alcoves Heavy lowering system is unnecessary Heavy lowering system is necessary same as on the left Location of DH and assembly yd. can be selected individually. Location of assembly yd. must be satisfied on ground social condition and underground geological condition. same as on the left Vehicles are used for personnel and machines entering and leaving. All of personnel and machines use lifting equipment. Both of vehicles and lifting equipment are available. Detector assembled after completion of DH civil work. Detector assembled in parallel with DH civil work. same as on the left Environmental impact will be smaller during construction. Noise reduction of explosion excavation. same as on the left. Evacuation ways are DH HT, and DR HT. Isolated shelters and shafts with elevators Tunnels and shafts are available for evacuation HT D11m Grad7% Assembly Yd DH Straight 5 SFTs 1 Main SFT 1 ILD SFT 1 SiD SFT 2 EV SFT Assembly Yd Upper A/T DH Z-shape DH Upper HT HT D8m Grad10% 2 SFTs 1 Main SFT 1 UT/EV SFT First JPower Study – February 2014

5 5 HT Site Details 200m 11m/7% grade tunnel with hairpin turn Large (TDR) hall volume for assembly “Natural” hall position 200m below surface

6 6 VS Site Details Move IR so vault is 90m below surface Cost/schedule analysis for 5 shaft design that was really optimized for Fermilab/CERN topography 90m

7 7 Hybrid Site (as of 2/25/14) Details 90m 8m/10% grade tunnel with 3 90° turns and an even tighter hairpin turn Assembly area of IR Hall removed Depth of hall under surface & hall position as for VS case Assumed (for SiD) that barrel & coil structure and doors use shaft

8 Schedule and Cost Summary HT access (baseline)VS accessHT & VS access Construction periods 45.7 months after land development46.4 months42.3 months Construction Costs 10012299 HT D11m Grad7% Assembly Yd DH Straight 5 SFTs 1 Main SFT 1 ILD SFT 1 SiD SFT 2 EV SFT Assembly Yd Upper A/T DH Z-shape DH Upper HT HT D8m Grad10% 2 SFTs 1 Main SFT 1 UT/EV SFT Estimated Cost is basis for dropping VS from further consideration

9 BaselineHybrid-AHybrid-BHybrid-C 1 HT (11x11m 7%grad) Detector assembling is inside of DH 1 HT (8.0x7.5m 10%gradl) 2 VS (D18m, D10m) Detectors assembling is on-ground. 1 HT (9.5x9.0m 7%gradl) 1 VS (D18m) ILD assembling on- ground SiD inside D/H 1 HT (11x11m 7%grad) 1 VS (D10m) Detector assembling is inside of DH UT lines in DR/AT UT lines in UT shaft UT lines in Main shaft UT lines in UT shaft DH 175,000m3 L144m H42m W25m DH 128,000m3 L108m H42m W25m DH 165,000m3 L134m H42m W25m DH 175,000m3 L144m H42m W25m Heavy lowering system non Heavy lowering system necessary Heavy lowering system non Location of DH and assembly yd. can be selected individually. Assembly hall is above D/H same as on the left Human pass way :car Machine and materials tunnel by vehicles Human pass way :elevator Machine and materials tunnel by vehicles Human pass way :elevator Machine and materials ILD:VS HT, SiD:HT Human pass way :elevator Machine and materials tunnel by vehicles Environmental impact will be smaller during construction. Noise reduction same as on the left Evacuation ways Main AT and DR HT. same as on the left Hybrid option case study: April 9 Main AT W11m Grad7% Assembly Yd D/ H Upper A/T D/ H Assembly Yd Main AT W8m Grad10% D/ H Assembly Yd Main AT W9.5m Grad7% D/ H Assembly Yd Main AT W11m Grad7%

10 10 Summary of changes HT Baseline: Slight change to tunnel path Diameter & grade unchanged Hall unchanged Hybrid A: As before, a shared 18m shaft over the IP (changing in shape from circle to ellipse with depth); minimal IR cavern New 10m elevator/utility shaft Re-optimized tunnel path: same 8m diameter & 10% grade

11 11 Summary of changes Hybrid B: Vertical 18m Shaft over ILD garage - with elevator & utilities embedded Tunnel diameter sized for SiD coil and SiD hall as for HT, same path as before (do not understand quoted grade of 7%) Assumes common location for ILD & SiD above ground assembly halls Hybrid C: Basically HT with a 10m elevator/utility shaft off to the side Utility shaft apparently decided location of assembly hall on top of elevator Again, do not understand quoted grade of tunnel as path is same as “A”

12 Summary of Cost and Schedule BaselineHybrid-AHybrid-BHybrid-C Construction periods after land development 61.7 months49.1 months58.1 months62.6 months Construction Costs 100%109%115%101% Main AT W11m Grad7% Assembly Yd D/H Upper A/T D/H Assembly Yd Main AT W8m Grad10% D/H Assembly Yd Main AT W9.5m Grad7% D/H Assembly Yd Main AT W11m Grad7% Was 45.7 in previous analysis?

13 13 Current ILD Position (from Karsten’s slides) ILD group supports to study the possible realisation of a hybrid VS+HT access in the Kitakami area Cons: Surface infrastructure potentially more complex: platform in assembly hall Assembly halls are geographically fixed directly above the experimental hall HT part might be compromised by not optimal paths Pros: ILD assembly much easier with VS Transportation system in HT is not defined and could be a major technical and safety headache; gantry crane for VS successfully done at CMS More space available for machine and detector service lines Less underground volume necessary Smaller crane (2x40t) instead of 250t in underground hall Time lines of both detector and machine installations are largely decoupled

14 14 Current SiD Position HT Pros: Enforces SiD desire for UG assembly 1x only No 4000T gantry / No 20m x 20m moveable platform on surface No transport up the hill only to lower again with gantry or crane No duplication of cryo infrastructure on surface for coil testing Minimizes surface assembly infrastructure HT Cons 210T crane underground w/larger ($) cavern Risk associated with not 4K testing coil before assembly ILD needs to re-evaluate assembly procedure Possibly later “beneficial occupancy” of IR Hall General Comments No input from SiD at design stage Many unanswered questions affect detailed design Not clear that any scheme in this down-select has been optimized SiD perspective filtered down in decision process

15 15 (from Karsten’s slides)

16 16 Adequate Surface Area for Storage, Assembly and Testing (example: Oriunno, Tokyo LCWS 2013) Assembly Hall #2 Assembly Hall #1 Offices Access Tunnel Site Entrance 200T Loading Station

17 17 Partial List of Open Questions Regardless of HT, VS, Hybrid A, B, C road transportation (and port) boundary conditions (loads, legal issues) geological issues (tunnel, shaft) environmental impact (land use, noise, etc.) transportation system in tunnel (truck or other) and shaft (gantry crane) optimisation of access paths (tunnel slope and curves) material flow through access paths realistic models and timelines for detector and machine assemblies using shared infrastructures services on and below surface: electrical, cooling, cryo, counting rooms, o ffi ce space, etc. service paths to underground area beam commissioning models with or w/o detectors role of ILC laboratory possible changes in detector models (from Karsten’s slides) Wed. 11am MDI/BDS/CFS

18 18 Watch “60 Minutes” ALMA segment

19 19 Mike Harrison’s April 10 Conclusion Post meeting discussions: Hybrid A solution with 7% grade must be found AWLC is venue for further discussion


Download ppt "Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab."

Similar presentations


Ads by Google