GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS NATIONAL HIGHWAY AUTHORITY BRIEF ON CONSTRUCTION WING PROJECTS Islamabad, Jan 10, 2014.

Similar presentations


Presentation on theme: "GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS NATIONAL HIGHWAY AUTHORITY BRIEF ON CONSTRUCTION WING PROJECTS Islamabad, Jan 10, 2014."— Presentation transcript:

1 GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS NATIONAL HIGHWAY AUTHORITY BRIEF ON CONSTRUCTION WING PROJECTS Islamabad, Jan 10, 2014

2 Road/ River Construction ProjectKm PC-1 Cost StartContractor Contract Cost PSDP 2013-14 Status OriginalRevised 1Indus *Larkana Khairpur Bridge (5 Packs) 57483111588 May-07 Sachal SMADB SMC MB: 1444 PI: 4016 PII: 1422 PIII: 1634 PIV: 148 500 Subst. Completed Except 6 Km Asphalt on Approach road Larkana side. 2N-105 Rehabilitation of Larkana- Naudero Lahki Road (2 Packs) 6119254000 Apr-09 Zarghoon SMADB PI: 1263 PII: 1383 201.6 Subst. Completed 3N-305 Dualization of Sakrand – Benazirabad Road (2 Packs) 20 11291419 Oct-09 NAK USMANI PI: 942 PII: 598 33.6 Subst. Completed 4N-655 Rehabilitation of Ratodero Naudero Road 15 612847 Sep-09 Sachal 794 1 Subst. Completed 5DW Hyderabad- Badin Road to Mir Wah- Sanjar Chang Road 2(Packs) 528801794 Jun-10 Maqbool SARCO PI: 802 PII: 656 168 Subst. Completed 6M-10 Karachi Northern Bypass (Including collapsed segment) 5729285224 Apr-02 NLC Usmani P1: 2405 P2: 793 CS : 434 67.2 Completed Rs in Million COMPLETED DEVELOPMENT PROJECTS SINDH

3 Road/ River Construction ProjectKm PC-1 Cost StartContractor Contract Cost PSDP 2013-14 Progress Exp Comp OriginalRevised 1LEPLyari Expressway32508110443 May-02 FWO 8554 60080% Dec-14 2N-455Kamber – Shahdadkot 29 9661050 Sep-09 RMC 1043 33646% Jun-14 3Indus Qazi Ahmed - Amri Bridge (4 Packs) 1836837292 Mar-10 Sachal SMADB 2017 (P1) 1714 (P2) 63877% Sep-14 4N-110 *Gharo-Keti Bunder (3 Packs) 8430363300 Sep-09 QKC MAJ&FE Zarghoon 776 (P1) 1292 (P2) 957 (P3) 497.6774% Jun-14 5N-255 *Larkana-Nasirabad (Rehab) 341214 Jul-10 Lilley 1587 374.144% Jun-14 6N-155 **Larkana- Mohenjodaro upto Airport (2 Packs) 2819313041 May-09 SMC 1529 (P1) 1533 (P2) 16883% Dec-14 7N-455**Larkana – Kamber 20 608855 Sep-09 Al-Mehran 845 177% Dec-14 Rs in Million ONGOING DEVELOPMENT PROJECTS SINDH

4 COMPLETED PROJECTS BALOCHISTAN PSDP No Road/ Bridge Project/ Section Km PC-1 Cost Todate Expenditure Sep-13 Contractor Contract Cost PSDP 2013-14 OriginalRevised 1102MCHP Makran Coastal Road 653 150101726215,189 FWO AL-Khan Nazir (JV) SMADB PI: 4880 PII: 820 PIII: 825 PIV: 1050 PV: 2656 PVI: 2487 PVII: 1166 300 290N-65 Improvement of N - 65, Nutal - Sibi – Dhadar Section ( 3 x Packs) 106 226632622070 FWO AGHA PI: 1575 PII: 452 PIII: 180 50 3113N-65 Realignment near Jacobabad & Dera Allah 27 478671629 MAB 526 46.6 Rs in Million

5 ONGOING DEVELOPMENT PROJECTS BALOCHISTAN Road / Bridg e Project/ Section Km PC-1 Cost Contractor Contract Cost PSDP 2013- 14 Prog Start Exp Comp OriginalRevised 1M-8 Gwadar - Turbat- Hoshab (3 Packs) 193 5687.4 18379 Left over work to be awarded 2494(S-1, P IIA) 3687(S-1, P IIB) 3166(S-2, P IIA) 3,433 68% Sep- 04 18 Months after re- tenderin g 2M-8 Khuzdar- Ratodero (3 Packs) 143 4010 6672 AMCC SMADB FWO 2207(S-IV, P-IV) 1908(S-IV, P-III) 2306 (S-IV, P-V) 73% Oct- 04 Dec-14 3N-85 Hoshab- Basima - Sorab 454 22412 FWO 14,452) 5,000 22% Sep- 07 Dec-16 4N-70 Waigum Rud - Khajuri 132 2841 3473 FWO1331 599 50% Sep- 07 Mar-14 5N-65 Kolpur Bypass 5.7 639.24 1065 Sapna696 172 55% Dec- 10 Jun-14 Rs in Million

6 Sr PSDP # Road/ Bridge Project/SectionKm PC-1 (Orig / Rev) Contract Cost PSDP 2013-14 StartCompletionStatus 166Sutlej Moosa Pak Shaheed Bridge 0.621301616201.6Jul-09May-11 Completed 262 Chenab Chund Bridge0.791086805.1919.03Jan-08Feb-11 3 65Chenab Head Muhammadwala Bridge 12508 712 (P1) 405 (P2) 970 (P3) 16.8Jun-09Dec-11 482N-5 Jinnah Chowk - Bahawalpur Chowk 81078 234 (P1) 532 (P2) 134.4Jul-08May-11 567N-5 Wah Gate Underpass at Taxila 1.279938737Dec-08Oct-11 691IMDC Islamabad Murree Dual Cariageway 4213,6003414134.4Sep-99Apr-11 7106N-115 Nag Shah Chowk Flyover (4-Lane) 11530835266.27Jul-10Jul-13 Substantially Completed 896 Link to BZU Khanewal- Multan Inter District Road (Bosan Road) (2x Packs) 7.54570 461 (P1) 531 (P2) 450Mar-11Aug-13 9104 Link to Jinnah Chowk Multan Inner City Ring Road Multan -- 7846.35 / 10,918 1204 (P1) 1202 (P2) 1596 (P3) 400Feb-10Jan-13 1088M-2 Hiran Minar Interchange 0.5 260 / 730 (Under process) 234150Jul-11Dec-12 Rs in Million RECENTLY COMPLETED DEVELOPMENT PROJECTS PUNJAB

7 PSDP # Road/ River Project/Section Km PC-1 (Orig / Rev) Contract Cost PSDP 2013- 14 Progress Start Expected Completion Remarks 1 117N-115 Tri District Link (Jalalpur Pirwala - Uch Sharif) (Pkg-3) 27 3171 (Global) 1566 (Pack-3) 350 (Global) 44%Dec-09Jun-14 Work in progress 2 68Chenab Sultan Bahoo Bridge (Shorkot - Garh Maharaja) Main Bridge 0.85 1603 (Global) / 4,354 (under process) 770 403.2 (Global) 84%Jun-10Jun-14 Garh Maharaja Side Approach Road 3.267855%Sep-10Jun-14 Shorkot Side Approach Road 4.0957268%Sep-11Jun-14 Flood Protection Bund on Garh Maharaja Side 81476.18%Dec-12Jun-14 J-Spur at Garh Maharaja side1.72204--Jun-13Jun-14 J-Spur & raising of Existing Dyke on Shorkot Side 1.629615.5%Jun-13Jun-14 Rs in Million ONGOING DEVELOPMENT PROJECTS PUNJAB

8 PSDP # Road/ River Project / Section Km PC-I (Orig / Rev) Contract Cost PSDP 2013-14 Progress Start Expected Completion Remarks 359Indus Nishtar Ghat Bridge (Shaheed Benazir Bhutto) Main Bridge 1.2 5459 (Global) 929 658 51%Feb-12Jul-14 Work in progress Approach Road Zahir Pir To Chachran Sharif 12.2459443%Nov-11Jul-14 470Ravi Syedwala Bridge --1164829268.87%Oct-12Apr-14 564 Link to Northern bypass Multan Gillani Road (Khad Factory to Pul Khadal) Multan (5.6 Km) 5.06809211201.613%Oct-12Jul-14 6100N-115 6 Lane Highway from Double Phatak – Chowk Naagshah (Old Shujabad Road) 84028144030026%Jan-13Jun-14 761Sutlej Baba Farid Bridge 0.57 + 8 1108 913.46 8 67.269%Feb-08 9 months from resumption of work Work suspended Rs in Million ONGOING DEVELOPMENT PROJECTS PUNJAB

9 Rs in Million COMPLETED DEVELOPMENT PROJECTS (GOP) KHYBER PAKHTUNKHWA PSDP RoadProject Km PC-1 Cost PSDP 2013-14 Contract Cost StartCompletionRemarks OrigRev 1103N-15 Mansehra Naran Jalkhad road 43.35125.65350.6501369May-02Dec-08 Completed 278N-55 CRBC-Sara-e- Gambila 70158519031831126Feb-07Dec-09 389N-45 Takht Bhari – Shergarh – Daregai 30 2399 (Global) 3405 (Global) (under process) 101917Aug-10Dec-12

10 Rs in Million ONGOING DEVELOPMENT PROJECTS (GOP) KHYBER PAKHTUNKHWA PSDPRoadProjectKm PC-1 Cost PSDP 2013- 14 Contract Cost ProgressStart Expected Completion Remarks OrigRev 197N-80 Khushalgarh Bridge (Pack-1, 2 Bridge & Kohat side approach) 0.35 + 2.4 1538 3108 (under process in CDWP) 336 100893%Oct-11Jun-2014 Work in progress Jand Side Approach Road & Over Head Bridge 1.2316550%Mar-13Mar-2014 2.92N-15 Jhalkhad - Babusar Top 28.5 4017--336 120668.4% Oct-04Dec-2014 Babusar Top - Chillas 381313 82.5% Jan-05Jun-2014 398N-45Lowari Tunnel 8.5 + 1.9 798418,1321000604740%Sep-05Oct-2017 4109E-2 Peshawar Northern Bypass (Pack-I) 7.6 9003 (Global) -- 1458 221970%Feb-10Apr-2014 Pack IIIA 5.415457%Jul-13Oct-2014 589N-45 Takht Bhai Flyover on Noshera Chakdara Dir Road (N-45) 0.22 Bridge + 0.89 Approach 2399 (Global) 3405 (Global) (under process) 1015825%Feb-13Aug-14 6--KKH Shatial Thor Nala Bypass 373844--WAPDA35183%Sep-12Sep-14 7-- Torkham Jalalabad Road Afghanistan (ACW) 734341-- 434158%Jan-07 FWO Demobilized on Aug-08 Work suspended