Team Hotel: Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala Advisors: Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept.

Similar presentations


Presentation on theme: "Team Hotel: Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala Advisors: Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept."— Presentation transcript:

1 Team Hotel: Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala Advisors: Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept. Of Chemical Engineering April 5, 2011 1

2  What we are doing?  Producing syngas from petcoke  Using entrained flow gasifier  Implementing a rigorous syngas cleaning  Why we are doing this?  Making syngas for acetic acid production  Chemical production team specs ▪ CO to H2 molar ratio of 0.409 ▪ CO2 and N2 mixed in 2 http://coalgasificationnews.com/tag/petcoke- gasification/ 4/5/2011

3 3

4  Discussed Our Aspen Simulation  Gasifier  Sulfur Removal  Water Gas Shift  CO2 Removal  Claus Process  Heat Loads  Optimization  Equipment Costs and Sizes  Individual Economics  Sensitivity Analysis  Location 4 4/5/2011

5  PFD  Initial Control Scheme  Plant Layout (General Arrangement)  Calculations  Refined Economics 5 4/5/2011

6 6

7 7

8 8

9 9

10 10 4/5/2011

11 11 4/5/2011

12 12

13 4/5/2011 13

14 14 4/5/2011

15 15

16 16 4/5/2011

17 17

18 4/5/2011 18

19 4/5/2011 19

20 4/5/2011 20

21 21

22 4/5/2011 22

23 4/5/2011 23

24 1 st year2 nd Year3 Rd year4 th year19 th Year Revenue $ - $ 129,570,000 $ 240,352,994 Cap. Cost$ 25,546,569 $ 104,011,033 $ 72,990,199 $ 20,072,305 $ - Op. Cost $ - $ 111,070,226 $ 242,943,820 Total Expense $ 25,546,569 $ 104,011,033 $ 72,990,199 $ 151,307,886 $ 281,203,980 Income tax 40% $ - $ 13,144,845 $ 83,909,549 Income After Tax $ - $ 19,717,268 $125,864,323 Cumulative Cash Flow $ 25,546,569 $129,557,602 $202,547,801 $ 168,810,442 $1,540,424,893 NPV $89,282,710 IRR N/A Interest 8% 24

25 4/5/2011 25

26 4/5/2011 26

27 4/5/2011 27

28 4/5/2011 28

29 4/5/2011 29

30  PFD  Control Schemes  Plant Layout  Calculations  Refined Economics 4/5/2011 30

31  Revise report 4/5/2011 31

32 4/5/2011 32

33  Richard Parkinson. “Where Does It Go? An Introduction to the Placement of Process Equipment.” UOP PowerPoint. 2009. 2 April 2011. 4/5/2011 33

34  Final Report:  Executive SummaryIP  DiscussionIP  Recommendations IP  Appendices  Design Basis: Done  Block Flow Diagram: Done  Process Flow Showing Major Equip.: Done 34 4/5/2011

35  Appendices (Continued)  Material and Energy Balances:Done  Calculations: IP  Annotated Equip. List: Done  Econ. Eval. Factored from Equip. Costs: Done  Utilities: IP  Conceptual Control Scheme: Done  Major Equipment Layout: Done 35 4/5/2011

36  Appendices (Continued)  Distribution and End-use Issues:IP  Constraints Review: IP  Applicable Standards: IP  Project Communications File: IP  Information Sources and References:IP 36 4/5/2011

37 37

38 4/5/201138

39 4/5/201139

40 4/5/201140

41 4/5/201141

42 Inlet Fraction Clean Syngas Component Flow for WGS Reactor(lbmoles/hr) for WGSCp (btu/lbmole* F) Outlet Syngas Comp (lbmole/hr) from (WGS) CO4946.2337.118123.395 H2O6424.68815.3671601.850 N2199.9547.158199.954 H2*2960.1686.9487783.006 CO2469.21110.5595292.049 CH4*0.255 12.4320.255 H2S0.000 COS0.000 Total15000.509 42 4/5/2011

43 Gasifier EquipmentHeat Load (MMBtu/hr) Gasifier-34.7 HP Steam Heat Exchanger139.0 MP Steam Heat Exchanger281 Cooler-106.8 Flash2.99 Sulfur Clean Up EquipmentHeat Load (MMBtu/hr) Sulfur Stripper Reboiler57.0 Sulfur Stripper Cooler-200.0 Selexol Cooler-40.7 Rich / Lean Heat Exchanger274.9 4/5/2011 43

44  CO2 in our syngas is absorbed on Selexol to be selectively removed  Delete only one CO2 slide. 444/5/2011

45 45 http://fossil.energy.gov/images/programs/sequestration/what_sequestration _lg.jpg 4/5/2011


Download ppt "Team Hotel: Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala Advisors: Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept."

Similar presentations


Ads by Google