Presentation is loading. Please wait.

Presentation is loading. Please wait.

Central Coalfields Limited

Similar presentations


Presentation on theme: "Central Coalfields Limited"— Presentation transcript:

1 Central Coalfields Limited

2 1 BILLION TON PRODUCTION PLAN
BE PROPOSED CAGR (%) COAL INDIA 507 1000 14.55 % CCL 55 140 20.54 % = 158.9 24 % (Actual CAGR) 18.9 MT Coal production from Piparwar, Selected Dhori (Q3) and Kalyani will be lost due to reserve depletion in these mines.

3 Production Plan (MT)

4 GREENFIELD PROJECTS A. Already commissioned:
AMRAPALI OC ( 12 MTY)-Feb’14 MAGADH OC (20 MTY)-Oct’14 KONAR OC (3.50 MTY) – Jan’14 SAWANG ‘C’ UG (0.15 MTY)-Dec’14 PURNADIH OC (QUARRY 1 )-Aug’2013 NORTH URIMARI OC (QUARRY 2 )-Oct’13

5 GREENFIELD PROJECTS Pachra OC (15 MTY)
B. To be commissioned: Sanghamitra OC (20 MTY) Pachra OC (15 MTY) Chatti-Baratu,Kerandari OC (13 MTY)-To be handed over to CCL.

6 Production and Dispatch Plan (MT)

7 Future projects up to 2019-20 Name Capacity Greenfields projects
Production in FY2020 Start of Production Pachra OC 15.00 Sanghamitra OC 20.00 Chatti- Bariatu, Kerandari OC 15.0 13.00 Pichri OC 1.20 Kalyani OC 2.00 1.50 Piparwar – Mangardaha UG 1.38 0.205 Total 54.58 50.905

8 Plan for 140 MT of Coal by CCL in 2019-20 towards 1 BT
A. GROUP-WISE GROUP ( Actual) Plan for Projection Existing Mines 5.24 3.865 2.46 0.47 Completed Projects 14.49 14.036 14.66 15.47 16.315 17.10 18.47 On-going Projects 30.30 37.099 43.39 50.82 56.633 66.41 70.16 Future Projects 0.25 6.582 20.025 50.905 Total 50.02 55.0 60.50 67.0 80.0 104.0 140.0 Growth in absolute term 5.5 6.5 13.0 24.0 36.0 Growth in % 10% 11% 19% 30% 35%

9 Projects requiring Tori - Shivpur – Kathutia Railline
for Evacuation Name Capacity Production in FY2020 Start of Production Amrapali OC 12.0 Magadh OC 20.0 20.00 Pachra OC 15.00 Sanghamitra OC Chatti- Bariatu, Kerandari OC 15.0 13.00 Total 82.00 80.00

10 TORI – SHIVPUR -KATHOTIA RAILWAY LINE

11 TORI SHIVPUR KATHOTIA RAILWAY LINE
Shivpur Kathotia Section Kathotia Shivpur Tori Shivpur Section Tori

12 TORI SHIVPUR KATHOTIA RAILWAY LINE Proposed Length of Railway Line
Sl. No. Particulars Total (km) Status 1 Tori- Shivpur 44.37 Nearly 55% land yet to be acquired/handed over. Tree cutting in progress in Forest patches (Only 47% completed) 2 Shivpur - Kathautia 49.08 Stage-I forestry clearance application is yet to be filed to MoEF 3 Total 93.45 Total Cost Rs Crs.

13 TORI-SHIVPUR SECTION Type of Land Requisitioned Acquired / Handed Over Yet to be Acquired/ handed over Remarks Forest Nil Govt. of Jharkhand accorded approval for diversion on Tree cutting is in progress. GungleJhari To be transferred Govt / GM Raiyati 206.30 To be obtained Total 55% (approx.) area yet to be given

14 SHIVPUR-KATHOTIA SECTION
Type of Land Requisitioned Acquired/ Handed over YET TO BE Acquired/ Handed over Remarks Forest Nil After getting NOC for GMJJ land, Stage –I forestry clearance application will be initiated. Gungle-Jhari To be transferred Govt/ GM 72.150 Raiyyati To be acquired TOTAL

15 RAIL INFRASTRUCTURE WORKS UNDERTAKEN BY EC RAILWAY
Sl. No. Work/ Activity Value (Rs. In Crores) Present Status Tori – Shivpur – Kathotia BG Rail line – By EC Railway, Patna / Hajipur. Project Cost revised from Rs Crores to Rs Crores Railway CAPITAL COST (Revised cost Rs Crores) : – This rail line having length of Kms. is being constructed by EC Railway on deposit term basis from land acquisition, forestry clearance etc. upto commissioning.  FUNDING OF THE PROJECT : –  Initially it was decided that CCDAC will provide funds for this rail line. In the 70th CCDAC meeting held on , “In principle approval” was accorded by CCDAC of the then project cost of Rs Crores with 100% assistance from CCDAC. Later the cost was revised by Railways from Rs 2345 Crores to Rs Crores. CCDAC has been requested by CCL for approval of Revised cost estimate of Rs Crores. Till now CCDAC has provided Rs Crores only out of total deposited amount of Rs Crores for this rail line project. In the 74th meeting of CCDAC held on 26th December 2013, CCDAC agreed “in-principle” to pay the expenditure incurred by CCL limiting to initial sanctioned assistance of Rs Crores only. A letter from MOC was received on , wherein it is mentioned that balance fund requirement cannot be arranged from CCDAC. It was advised to take up the matter with CIL for arrangement of fund for this crucial rail line project.

16 Present Status Payment to Railways:
Till now CCL has deposited Rs Crores with Railways (Rs Crores received from CCDAC & Rs Crores by CCL). CCDAC has been requested for reimbursement of the amount deposited by CCL with railways. Also as desired by Railway, Consent letter has been sent to EC Railway for survey of future 2nd & 3rd line near existing Tori /Mahuamilan Station. SCHEDULE DATE OF COMPLETION : – Tori – Shivpur section - June’2016.(vide Railways letter dtd ). March 2015(As per 3rd IMC meeting held on ) Shivpur – Kathotia section - June’2018, if forestry clearance is granted latest by March’2015. Details of Land Payment & Tree felling Status As requested by railways, CCL management had previously conveyed the acceptance to EC Railway, Patna on for payment of 2.4 times the normal land compensation for emergency acquisition of balance Raiyati land by Railways under Jharkhand Swaichik Bhoo–Arjan Niyamawali – 2010 as per the provisions of Govt. of Jharkhand. A meeting was held on at Ranchi between the Chief Secretary, Govt. of Jharkhand and Chairman Railway Board, New Delhi in which serious concern was expressed on the delay in the commissioning of this rail line. To expedite the land acquisition issues, a task force consisting of DC,DFO and SP was constituted, which would meet every fortnight along with officials of Railways. GM, Van Nigam, Govt. of Jharkhand was assigned the task of cutting remaining trees along the rail alignment in Tori-Shivpur section within 3(Three) months time. As intimated by Railways, 3 (Three) task force meetings have been conducted by DC/Chatra.

17 Present Status Details of Land Payment & Tree felling Status As requested by railways, CCL management had previously conveyed the acceptance to EC Railway, Patna on for payment of 2.4 times the normal land compensation for emergency acquisition of balance Raiyati land by Railways under Jharkhand Swaichik Bhoo–Arjan Niyamawali – 2010 as per the provisions of Govt. of Jharkhand. A meeting was held on at Ranchi between the Chief Secretary, Govt. of Jharkhand and Chairman Railway Board, New Delhi in which serious concern was expressed on the delay in the commissioning of this rail line. To expedite the land acquisition issues, a task force consisting of DC,DFO and SP was constituted, which would meet every fortnight along with officials of Railways. GM, Van Nigam, Govt. of Jharkhand was assigned the task of cutting remaining trees along the rail alignment in Tori-Shivpur section within 3(Three) months time. As intimated by Railways, 3 (Three) task force meetings have been conducted by DC/Chatra.

18 Present Status  CIVIL ENGINEERING WORKS : – As per the record notes of the 3rd Inter Ministerial Committee (IMC) meeting held on , all tenders for Civil Engineering Works upto 44 Km length in Tori-Shivpur section was to be finalised by October 2013. However as per present status, work is presently in progress in the portion upto 36 Km for an awarded value of Rs Crores. Further , Tendering is in process for works amounting to Rs Crores. The work is in progress physically in non forest patches only in 0 to 36 Kms. from Tori end. About lakhs Cu.m out of lakhs Cu.m approx. of earth work has been completed. Expenditure : – Till date the Railways have made an expenditure of Rs.188 Cores only (i.e. 20% approx of total deposited amount of Rs Crores) by CCL.

19 MAJOR CONSTRAINTS Evacuation Land Authentication (Annexure -1)
FC (Annexure -2)

20 CCL – YEAR END STOCK (MT)
Stock dropped to below 10 MT level for the first time in 8 years in

21 CAPITAL OUTLAY (2015-20) 2014-15 2015-16 2016-17 2017-18 2018-19
SL NO H E A D TOTAL BE RE PROJ 1 LAND 39.79 40.00 100.00 190.00 210.00 750.00 2 REHABILITATION 3.95 10.00 35.00 20.00 120.00 3 RESIDENTIAL & WELFARE 2.74 160.00 4 SERVICE BUILDING 5.04 15.00 70.00 5 ROADS 340.00 6 P & M HEMM 417.08 325.00 410.00 135.00 110.00 185.00 CHP 21.88 50.00 200.00 OTHERS (INCL.UG) 30.00 60.00 270.00 7 MINE DEVELOPMENT 23.01 8 WASHERY 1.55 25.00 150.00 775.00 9 RAILWAY SIDING 1.5 44.7 10 EXPLORATION / PLAN. 56 45.00 90.00 435.00 11 OTHERS 12.46 5.00 TOTAL 585.00 628.20 600.00

22 EQUIPMENT PROCUREMENT PLAN

23 Shovel Dumper Dozers Drill 2014-15 2 12 13 19 63 7 25 26 2015-16 3 4 9
YEAR Shovel Dumper Dozers Drill 10 M3 4-6 M3 < 4 M3 100T 60T 410HP 320HP 160mm 2 12 13 19 63 7 25 26 3 4 9 67 11 1 14 62 15 21 6 5 10 49

24 HEMM POPULATION (1.1.2015) SHOVEL 106 DUMPER 493 DOZER 183 DRILL 108
WATER TANKER 62 GRADER 53 LOADER 37 CRANE 78 TYRE HANDLER 6 CABLE REELER 1

25 CATTERPILLAR VS BEML DUMPERS
Capacity Make Performance Nos. % Avl % Utl. On Roll S/off Wkg 60 T BEML 105 73 38 CAT 56 88 49 85 T 44 36 13 11 10 74 31 100 T 34 62 26 18 89 45

26 2.70 Technological Development & Mechanization of Mines Proposed
Present technology Production level FY 14 1. LHD / SDL WITH BORD AND PILLAR 0.510 Future technology Future Production level (Rated capacity of mines) Continuous Miners in 3 mines – Churi-Benti, Parej East and Piparwar- Mangardaha UG 2.70

27 Technological Development & Mechanization of Mines Proposed
Surface Miners in all projects having more than 5 MTY capacity. Crushed coal (-) 100 mm production from 6 mega projects in – 94 MT 2. Minimization of road transport : Installation of belt conveyor from face to CHP Rapid Loading System and Silo Loading

28 Technological Development & Mechanization of Mines Proposed
3. Complete Transparency through ICT Techniques WAN GPS, RFID, CCTV, automatic weighment & boom barrier based monitoring system E tendering, e refund Single Window Grievance Redressal Cell – Samadhan Kendra Mass Promotion

29 SOLUTION Identification of customers to lift coal from pit head under the scheme " as is where is”. Tori-Sihivpur-Kathutia Railway Line Productivity enhancement

30 Thank You 30 30

31 Measures Suggested 1.Improvement in efficiency and productivity of men and machines: Annexure 1 & 2 2.Identification of outsourcing patches of existing mines which were hitherto considered unviable due to high stripping ratio. 3. Depending on land availability , outsourcing beyond the departmental capacity in existing mines 4. Opencasting underground mines wherever feasible 5.Rationalisation of men and machines 6. Standardisation of machines – 60 T dumpers with 5 m3 shovel and 100 T dumpers with 10 m3 shovels 7.Waiving environmental clearance for small patches with production of less than 0.50 MTY. 8. Introduction of piece rated concept for drill, dumper and shovel operators 9. Dedicated Cell for land acquisition and E&F clearance Fresh recruitment of sufficient officials Horizontal transfer of willing executives in various grades 10. Right person for right job

32 HEMM Maintenance Practices Maintenance Infrastructure
Annexure 1 POINTS TO IMPROVE AVAILABILITY OF HEMM WITH RELIABILITY 1 HEMM Procurement Sandardisation of Shovel -Dumper Combination ( 1. 60T Dumper with 6.5 Cu.M Shovel, T Dumper with 10 Cu. M Shovel) preferable make of Dumpers Catterpillar/ Komatsu and for Shovel - P&H. The concept of MARC for Higher capacity equipment should be enhanced from 70% to 90 % of economic life of the equipment with operators and payment should be made for each hour of utilisation. 2 Equipment procurement for Two years requirement at a time. 4 Joint venture with Tyre manufacturer for smooth flow of tyres 5 Spares Availability Depot At Door for Bigger Area /Project for immediate Spares availability. Web Integration of All Stores of Subsidiary 7 To ensure quality spares availability Right in time. 8 CIL's Model Depot agreement may be implemented Judiciously ( To implement Model Depot Agreement in TOTO as per the lead company.) 9 Procurement of spares for at least for two years for Imported Items. 10 To ensure availability of Consumables just in time. 11 To ensure issuance of spares from Stores 24X7. 12 Provisioning of Handling equipment at Stores ( Fork lifter, Pick & carry Crane etc) 13 HEMM Maintenance Practices To implement maintenance practices as per OEM recommendations Judiciously . 14 To implement Condition Based Maintenance practices. 15 To Implement Three Tier maintenance Practices ( At Field, Base Work Shops & RRS / CRS) along with proper generation of float assemblies. 16 Staggered Maintenance 17 Medium term Rate Contract for Overhaul / Repair of Major Sub assemblies by OEMs after expiry of warranty period for remaining rated life. ( Bucket, Crowd Mechn, Under carriage, Electricals, E engine, transmissions, Blade etc.) 18 Provisioning of Computer with Data Entry Operator for proper recording & Forecasting of Schedule maintenance. 19 Provisioning of Adequate Skilled manpower. 20 Man Power Human capital Generation through Specialised Training. Steps have already been initiated. Fresh engineers are being sent to equipment manufacturers like HEC, BEML, L&T, REL, Atlas Copco etc for the purpose. 21 Provisioning of Skilled Technical manpower ( Auto Electrician, HT electrician, EP Fitter, Welder Etc) 22 Proper training of manpower for Skill Development. 23 Job Rotation for multi Skill Development. 24 Maintenance Infrastructure Provisioning of Proper maintenance Infrastructure ( Maintenance Van, Diesel Bowser, Tyre handler etc.). 25 Provisioning of Maintenance tools & Special Tools ( Flow meter, Pressure gauge, Torque multiplier etc) 26 EOT Crane & Fork lifter & articulated Pick & carry crane. 27 Provisioning of DG set at Workshops. 28 Centralise Lubrication for all grades of Lubricant in the Base Work Shop. T 29 Tyre Mounting & De mounting device 30 Provisioning of Adequate washing facilities ( Multi Jet washing Pump with ETP )) 31 Provisioning of Diesel Dispensing Unit at All Workshop with water Separation plant. 32 Provisioning of Flushing cart at all workshop for maintaining cleanliness of all lubricating oil. 33 Miscellaneous Standarisation of fleets of equipment project wise/ Area wise 34 Motivational tool for enhancement of Availability of HEMM. 35 Enforce discipline & non interference of external agencies. 36 Steps to be taken to minimise Operational Abuse of Equipment ( Proper blasting, Bench height , Haul road etc).

33 Annexure 2 POINTS TO IMPROVE EFFICIENCY & PRODUCTIVITY. 1
1 Motivational tool for enhancement of utilisation hours (a) Operators comfort, (b) AC Canteen facility associated with AC mobile canteen, (c) introduction of piece rated concept of operators. 2 Mine Geometry (a) To work according to Mine operation rolling plan for at least three year. (b) To maintain proper faces, benches, haul raods, dump yards along with proper illumination & dust supression. 3 Proper fragmentation 4 Contingency fleet for unintrupted availability of HEMM for production. 5 To Implement Four Shift working or Two shift with extension of Back Shift. 6 Staggered maintenance & Hot Seat exchange of operators 7 To maintain separate road for Dozer & Light vehicle movement 8 To ensure Rest shelter with Drinking water facility at face as well as at workshop 9 Proper communication system. 10 Provisioning of light vehicles in Back Shift. 11 To ensure throughput of trained operators. 12 Provision of Supervisors ( Electrical Supervisor / Foreman) 13 Enforce discipline & non interference of external agencies.

34 Productivity Improvement Plan
Surface Miners in all projects having more than 5 MTY capacity. Crushed coal (-) 100 mm production from 6 mega projects in – 86 MT 2. Minimization of road transport : Installation of belt conveyor from face to CHP Rapid Loading System and Silo Loading 3 Replacement of 35 T dumper with 60 T dumpers

35 Productivity Improvement Plan
3. Complete Transparency through ICT Techniques WAN GPS, RFID, CCTV, automatic weighment & boom barrier based monitoring system E tendering, e refund Single Window Grievance Rederessal Cell – Samadhan Kendra Mass Promotion

36 Productivity Improvement Plan
4. Discipline enforcement 5. Introduction of Continuous Miners in Churi-Benti, Parej East , Piparwar-Mangardaha (proposed) Sidings within leasehold for group A and B mines

37 Productivity Improvement Plan
7.Land Restoration 8. Green Energy Hub in group A mines 9.ITI and Multi skill Development centre

38 CONCLUSION 1.Implementaion of Kaya Kalp Model : Silver bullet for Coal Industry

39

40 Forest Land Involved (Ha)
1. Forestry Clearance Sl No Mine Forest Land Involved (Ha) Production FC Required 1 Urimari OC 63.64 2.0 ,Feb’15 2 Rohini OC 74.81 , Dec’14 3 Amlo OC 39.66 2.50 ,Dec’15 4 Dhori East OC 25.4 0.60 5 KD Hesalong OC 126.72 4.30 6 Kedla OC 50.50 0.70 7 Govindpur Ph II OC 10.52 2.00 ,Sept.’15 8 Karo OC 226.67 3.50 9 Purnadih OC 170.90 3.00 10 Rajrappa OC 277.15 11 Parej East UG 87.0 0.20

41 Forest Land Involved (Ha)
1. Forestry Clearance Sl No Mine Forest Land Involved (Ha) Production FC Required 12 Tarmi OC 97.44 1.0 ,Sept.’15 13 Amrapali OC 12.00 ,June’16 14 Ashoka Expn. OC 403.84 20.00 15 Magadh OC 20.000 16 Topa OC RO 71.58 1.20 17 Churi-Benti UG 79.0 0.54 18 Tapin South Expn. OC 2.00 , Mar’17 19 Pachra OC 409.28 15.00 20 Sanghamitra OC 572.72 12.50 21 Pichri OC 22 Piparwar- Mangardaha UG 43.08 0.21

42 2. Environmental Clearance
Sl No Mine Production EC Required 1 Govindpur Ph II OC 2.00 ,Feb’15 2 Selected Dhori (Q3) OC - , Feb’15 3 Topa UG 0.025 , June’15 4 KD Hesalong OC 4.30 , Sept’15 5 Kedla OC 0.70 6 Sangam OC 0.25 7 Karo OC 3.50

43 2. Environmental Clearance
Sl No Mine Production EC Required 8 Tapin South Expn. OC 2.00 , Dec’16 9 Parej East UG 0.20 , Sept’15 10 Pachra OC 15.00 , Dec’15 11 Sanghamitra OC 12.50 12 Pichri OC 1.20 13 Kalyani OC 14 Piparwar-Mangardaha UG 0.221

44 5. Land Authentication and Physical Possession
Sl No Mine Land Involved (Ha) Production Required 1 KD Hesalong OC 27 4.30 , April’15 2 Khasmahal OC 15.05 1.50 3 Amrapali OC 239.47 12.00 , Dec’14 4 Ashoka Expn. OC 70.44 20.00 5 Karo OC 22.95 3.50 6 Magadh OC 568 7 North Urimari OC 78.38 3.00 8 Piparwar OC 27.58 9.15 MT , 9 Purnadih OC 298.78 10 Rajrappa OC 134.25 2.00 11 Topa RO OC 82.59 1.23 12 Chainpur OC 0.40

45 5. Land Authentication and Physical Possession
Sl No Mine Production Required 13 Pachra OC 20.0 14 Sanghamitra OC 12.0 5 Chatti-Bariatu, Kerandarai OC 6.50 16 Pichri OC 1.20

46 Production and Dispatch
(Figs in MT) (LIKELY) After years of almost no growth in coal production, CCL registered a growth of 4.1 % in

47 CCL – YEAR END STOCK (MT)
Stock dropped to below 10 MT level for the first time in 8 years in

48 2. CAPEX – TARGET VS ACTUAL (Rs Crs)

49 Production Augmentation- 6 Mega Projects
Sl No Project Production in (MT) Constraints 1. Ashoka Expn. OC 20.00 Land Authentication, Physical Possession, FC 2. Amrapali OC 12.00 Land authentication, Evacuation, FC 3. Magadh OC 4. Pachra OC 15.00 -DO-, EC 5. Sanghamitra OC 12.50 6. Chatti-Bariatu , Kerandari OC 6.50 Blocks to be handed over to CCL, - DO- TOTAL 86.00

50 Mine Closure – Reserve Depletion
Production Piparwar OC 12.31 Selected Dhori (Q 3) 4.73 Kalyani OC 1.88 TOTAL 18.92 Production loss due to mine closure in next few years : 19 MT

51 Production Sustenance - 11 Projects
Sl No Project Production in (MT) 1. Govindpur Ph II OC 2.00 2. Karma OC 1.00 3. Karo OC 3.50 4. Konar OC 5. Kathara OC 1.90 6. North Urimari OC 3.00

52 Production Sustenance - 11 Projects
Sl No Project Production in (MT) 7. Purnadih OC 3.00 8. Rajrappa OC 2.00 9. Rohini OC 10. Tetarikhar OC 11. Tapin OC 2.80 TOTAL 26.70


Download ppt "Central Coalfields Limited"

Similar presentations


Ads by Google