Presentation is loading. Please wait.

Presentation is loading. Please wait.

Republic of South Africa IPP Procurement Programme

Similar presentations


Presentation on theme: "Republic of South Africa IPP Procurement Programme"— Presentation transcript:

1 Republic of South Africa IPP Procurement Programme
IPPs: An Investor & Community Perspective Maduna Ngobeni Department of Energy of South Africa

2 Introduction In August 2011, the Minister determined that 3725MW of renewable energy be procured by IPPs in five different rounds (“Bid Windows”), subsequent to which the DOE initiated the procurement process. In December 2012, in a trio of further determinations, the Minister determined that a further 3200MW of renewables generation capacity was to be procured from IPPs, as well as IPP procurement of coal, gas, hydro and cogeneration generation capacity under the Baseload Programme and the Medium Term Risk Mitigation Project.

3 Introduction (cont’d)
To-date, the Department has: Under renewables Bid Window 1, entered into 28 agreements on 5 November 2012 totaling 1416MW generation capacity; Under renewables Bid Window 2, entered into 19 agreements on 9 May 2013 totaling 1044MW generation capacity. With regards to renewables Bid Window 3: Received 93 bids on the 19 August 2013 Appointed 17 preferred bidders totaling 1456MW generation capacity The Department was pleased to note the competitive pricing offered in the bids received

4 Introduction (cont’d)
Technology MW capacity determined MW capacity already procured Renewables 6 725 3 916 Small Renewables (≤ 5MW) 200 Coal 2 500 Gas 3 126 Hydro 2 609 Cogeneration 800 Total 15 960

5 PROCUREMENT

6 Procurement Process Background
Procurement documents* Request for Proposals Part A: General Requirements and Rules Part B: Qualification Criteria Part C: Economic Development Power Purchase Agreement Contract between the IPP and the Seller Wind PPA Solar PPA CSP PPA Other technologies etc. Implementation Agreement Contract between the IPP and the Department Obligation for IPP to deliver on economic development obligations On buyer default – Department to pay the IPP * Subject to variation across each programme.

7 Procurement Process Background
Request for Proposal (RFP)* RFP Part A Requirements Rules Qualification RFP Part B Environment Land Economic Develop Finance Technical Price Capacity Comparative Evaluation RFP Part C Economic development Job creation Local content Preferential procurement Enterprise development Socio-economic development * Subject to variation across each programme.

8 COMPARATIVE evaluation
Price 70 %* 30 % ED Project cost Rand/MWh Job creation Socio economic Local content Bidders with the highest combined price and economic development scores that fall within the capacity allocation per Bid Window are awarded preferred bidder status. * Subject to variation across each programme.

9 Contractual Arrangement
IPP Government Eskom Bidders are issued standardised agreements as part of the RFP. PPAs are issued on a per technology basis. Power Purchase Agreement (PPA) Implementation Agreement (IA) Government Framework Support Agreement

10 STRUCTURE OF AN IPP

11 Project Structure Majority of bidders in the renewables programme use a project finance structure. Project finance debt is generally more expensive than corporate debt as the only collateral is the project assets. However, a project finance structure shields the equity sponsors from harm should the project fail. Renewables Programme  Bid Window 1 Bid Window 2 Bid Window 3 Project Finance Preferred Bidders 27 18 11 Corporate Finance Preferred Bidders 1 6 Average Debt-Equity Split for Project Finance Preferred Bidders 71:29 75:25 72:28

12 Typical Shareholding Structure*
Smaller South African players have the opportunity of teaming up with large international players to form a project company. * A typical shareholding structure on the renewables programme. Shareholding structures may be substantially different in other programmes.

13 Funding Packages The DOE wishes to optimise the involvement of black people in the IPP projects and ensure that capacity is built within shareholders which are owned or controlled by black people or local communities to enable them to participate in the energy sector. In support of this, the DBSA may offer a funding package (in the form of a loan) to eligible candidates. The IDC and PIC may also provide loans to South African shareholders.

14 RENEWABLES & SMALL RENewAbleS

15 Focus on ED The DOE is committed to furthering economic development in South Africa as can be seen by the 30% weighting assigned to ED in the scoring mechanism of the renewables programme. The table below illustrates some of the criteria on which the ED scoring is based in the renewables programme: Criterion Outcome Job Creation A bidder is incentivised to create jobs for South African citizens with further incentives to hire black citizens, skilled blacks citizens and citizens from the local community. Local Content At least 40% to 45% of the construction cost spend of a project must be local. This encourages local manufacturing growth. Socio-economic development A project is required to spend at least 1% of gross revenue earned during operations on socio-economic development.

16 Small Renewables Fund The DOE, with National Treasury, is looking to set up a fund to assist small, new developers with financing, as well as reducing the cost and complexity to bid. KfW (German Government development bank) has offered a 34 million euro loan to contribute to the fund. The DOE will seek to involve commercial banks (the DOE has already received commitment from the commercial banks to contribute to the fund) and other funders to create a fund large enough to cater to the market.

17 Small Renewables Fund (cont’d)
The fund may well offer standardised documents and panels of EPC and O&M contractors and equipment suppliers (these are the primary participants in an IPP project); this will assist small new developers to become involved and will further the Department’s aim of encouraging local developers. This fund will take some time to create which means that the small renewables programme will need to shift timelines to move in line with the fund’s creation. However, this will allow more local developers to participate which is desirable to the DOE, the greater Government, the country and local communities.

18 RENEWABLES FACTS & FIGURES

19 Total Project Funding per MW
All figures nominal in R’millions/MW Technology Bid Window 1 Bid Window 2 Bid Window 3 Solar PV 36.6 28.9 18.7 Wind 21.0 19.4 21.6 Concentrated solar power with storage (min 3 hrs per day) 75.8 89.7 Small hydro (≤ 40MW) 44.1 Landfill gas 16.0 Biomass 64.3

20 Total Jobs Created* Figures represent totals during construction and operations combined. Technology Bid Window 1 Bid Window 2 Bid Window 3 Solar PV 8 498 6 079 9 632 Wind 4 271 4 025 11 118 Concentrated solar power with storage (min 3 hrs per day) 3 265 2 344 4 812 Small hydro (≤ 40MW) 553 Landfill gas 246 Biomass 336 * One job = 12 person-months

21 All Renewables Locations

22 THANK YOU


Download ppt "Republic of South Africa IPP Procurement Programme"

Similar presentations


Ads by Google