1 Kangean Energy Indonesia Ltd. Nov. 19, 2014
UPCOMING PROJECTS Kangean Energy Indonesia Ltd. Nov. 19, 2014

2 Agenda Kangean Block Upcoming Projects TSB Phase-2 Development Project
South Saubi Exploration Project

3 Kangean Block

4 TSB Phase-2 Development South Saubi Exploration
Upcoming Projects TSB Phase-2 Development South Saubi Exploration

5 TSB Phase-2 Projects (Exploitation)

6 TSB Development Phase-1 Phase-2

7 TSB Phase-2 Development
Water Depth : 90 – 250m Drill 4 wells (Sirasun, Batur) Lay Flowline and install Subsea Structure Lay Umbilical Install Subsea Control System Flowline tie-in to Existing Terang Manifold Umbilical tie-in to Existing UTA Note : Green colour – pipeline system (Phase 2) Blue colour – SCS (Phase 2)

8 Major Contracts in TSB Phase-2 Project
Subsea X’mas Tree & Subsea Control System (Q Q1 2017) Subsea EPCI (Q – Q1 2018) Drilling Rig (Q Q3 2017) Drilling Materials and Services

9 SOW and Requirement Subsea X’mas Tree Supplied Equipment
4ea x Nom. 7” -10K Subsea Xmas tree 5ea x Subsea Wellhead (18-3/4” x 10K) 5ea x Tubing Hanger Installation Service QA/QC Service

10 SOW and Requirement Subsea Control System
Equipment Supply (SCS infield & SCS Topside) One (1) set SCS infield components including UTA, Cobraheads, SDU’s with related accessories, HFL/EFL, spare parts and consumables for CONTRACTOR furnished items, to be fit with SS Installation Contractor’s manufactured umbilical, pile bases, structural members/ protection frames etc. One (1) set of SCS topside components including MCS, EPU and ROS for installation on the existing FPU. One (1) set Tree Instrumentation for respective SSXT: APT, UPTT, DPTT, SAM and SECM. Support Services project management, design eng, QA/QC, FAT, SIT, EFAT, SRT, transportation, shipment assistance, pre- installation test, pre-submergence check etc. Installation Services

11 SOW and Requirement Subsea EPCI Flowlines (incl. Tie-in)
10” Infield Flexible Flowline from SIO-1 to Sirasun Manifold, approx. 7.9km 12” Infield Flexible Flowline from SIO-2 and SIO-3 to Sirasun Manifold, approx. 1.8km and 1.6km 10” Infield Flexible Flowline from BTO-1 to Batur Tee, approx. 1.2km 26” OD, API X65, WT 20.6mm Production Flowline from Sirasun Manifold to Existing Terang Manifold, approx. 23.3km Subsea Structures (incl. Foundation) Sirasun Manifold - pile foundation Batur In-line Tee - mudmat Pipeline End Termination (PLET) - pile foundation Sirasun Subsea Distrubution Unit (SDU) - pile foundation Batur Subsea Distribution Unit (SDU) – mudmat

12 SOW and Requirement Subsea EPCI <Main vessels>
Installation - Water Depths (app. 90m – 250m) <Main vessels> Derrick Lay Barge (DLB), S-Lay To install all flowlines, SCS, Umbilical and subsea structures Diving Support Vessel (DSV) To perform pre-lay survey, span correction and tie-in (flowlines to subsea structures) To install pile foundations for subsea structures To perform Pre-commissioning

13 SOW and Requirement Rig Services
Floater Drilling Unit (Semi-Sub or Drill ship) 4 wells (Subsea Completion wells) Water Depth: 350ft – 750ft Drilling Depth: 4700ft – 6500ft 3horizontal wells and 1 deviated well Requirement SSXT Handling Capacity Able to handle SSXT(5m x 5m, 65ton) from supply boat to moon pool (5.5m x 5.5m)

14 Required Materials and Services (Drilling)
Item Remarks Casing 30”, 20”, 13-3/8” & 9-5/8” Cementing Accessories Float Shoe, Float Collar, Centralizer Liner Hanger 9-5/8” x 13-3/8” SSXT & SS-Wellhead 7” nom. Bore - 5K SSXT 18-3/4” – 10K SS-wellhead Gravel Pack Shunt tube system Tubing & Accessories 7” or 5-1/2” Tubing, 7” TRSCSSV Bit 26”, 17-1/2”, 12-1/4”, 8-1/2” 36” HOP Rental Equipment Drillling Jar, Fishing Tool, Stabilizer(36”, 26”), Riser brush, Casing scraper

15 Required Services (Drilling & Completion)
Item Remarks Mud & Completion Fluid High Performance WBM, NaCl(/NaBr) Brine Filtering system, Centrifuge rental, LMP at Supply Base Cementing Service 30”, 20”, 13-3/8” 9-5/8” Liner, other pumping, Bulk Plant at Supply Base Mud Logging System w/Data Engineer, Mud logger, Sample Catcher ROV Working Class SSXT & Wellhead Installation Running Tool Rental & Installation Service Directional Drilling PDM, RST, MWD, LWD Casing Installation 30”, 20”, 13-3/8”, 9-5/8” Liner, 7”(5-1/2” Tubing) Torque turn monitoring for tubing Liner Hanger Setting 9-5/8” x 13-3/8” Liner Hanger Open Hole Gravel Pack 8-1/2” horizontal section Well Cleaning Flow 7-3/8” Subsea Landing String, Surface equipment Coiled Tubing N2 lifting, Open/Close FIV, Retrieve BPV Wireline Tractor Open/Close FIV, Retrieve BPV Slickline Pressure/Temperature data acquisition

16 Required Services (Drilling Support)
Item Remarks Site Survey in 2016 as required Rig Positioning For 4 wells (4times) Anchor Handling Tug Supply Vessel 2 AHTS vessels + 1 supply vessel Helicopter Denpasar to/from Rig Weather forecast For TSB field VSAT For Floater Drilling Unit

17 South Saubi Projects (Exploration)

18 Major Contracts in South Saubi Project
3D Seismic Survey (Q2 2015) Drilling Rig (Q1 2016) Drilling Materials and Services (Q – Q1 2016)

19 SOW and Requirements (3D Seismic Survey)
3D Marine Seismic Acquisition Deep marine (WD~3,000ft) Full fold area: 215 sq. km Maximum offset: 6 km 3D Seismic Data Processing Onboard processing through PoSTM Main processing through PrSTM Onboard QC’s Acquisition / Navigation / Processing 30 ~ 40 days

20 SOW and Requirements (Drilling Rig)
Floater Drilling Unit (Semi-Sub or Drill ship) 1 well (DST if any positive indication, P&A) Water Depth: 3060ft Drilling Depth: 13950ft (DST case) Vertical well Requirement Managed Pressure Drilling System to drill safely reservoir (carbonate) To mitigate risk in relation with mud loss and kick

21 Drilling Materials and Services
Item Remarks Casing 36”, 20”, 16”, 13-5/8”, 9-5/8” and 7” Cementing Accessories Float Shoe, Float Collar, Centralizer Liner Hanger 16” x 20”, 11-3/4” x13-5/8” and 9-5/8” x 13-5/8” SS-Wellhead 18-3/4” – 10K SS-wellhead Bit 42”, 26”, 17”, 14-1/2”, 12-1/4”, 10-5/8” and 8-1/2” Rental Equipment Drilling Jar, Fishing Tool, Stabilizer, Casing scraper Site Survey in 2015 Rig Positioning For 1 well Anchor Handling Tug Supply Vessel 2 AHTS vessels Helicopter Denpasar to/from Rig Weather forecast For South Saubi field VSAT For Floater Drilling Unit

22 Required Services (Drilling & Completion)
Item Remarks Wellhead Installation Running Tool Rental & Installation Service Mud & Completion Fluid High Performance WBM or SBM Cementing Service 20”, 16”, 13-5/8”, 9-5/8”, 7” Liner or Casing, other pumping, Bulk Plant at Supply Base Mud Logging System w/Data Engineer, Mud logger, Sample Catcher Casing Installation 20”, 16”, 13-5/8”, 9-5/8”, 7” Liner Hanger Setting 11-3/4” x 13-5/8” and 9-5/8” x 13-5/8” Liner Hanger ROV Working Class Logging while Drilling PDM, MWD, LWD Hole Enlargement Tool 16” x 20”, 14-1/2” x 17-1/2”, 12-1/4” x 14-1/2”, 10-5/8” x 12-1/4” Managed Pressure Drilling System For carbonate reservoir drilling H2S Service H2S Detector, Breathing apparatus, Blower Wireline Logging Formation evaluation for reservoir, Cement bond log, Set bridge plug, contingency back-off DST For carbonate reservoir testing

23 Thank you