1 UPCOMING PROJECTS Kangean Energy Indonesia Ltd. Nov. 19, 2014.

Similar presentations


Presentation on theme: "1 UPCOMING PROJECTS Kangean Energy Indonesia Ltd. Nov. 19, 2014."— Presentation transcript:

1 1 UPCOMING PROJECTS Kangean Energy Indonesia Ltd. Nov. 19, 2014

2 Agenda Kangean Block Upcoming Projects TSB Phase-2 Development Project South Saubi Exploration Project 2

3 3 Kangean Block

4 4 Upcoming Projects TSB Phase-2 Development South Saubi Exploration

5 TSB Phase-2 Projects (Exploitation) 5

6 TSB Development Phase-1 Phase-2

7 TSB Phase-2 Development Note : Green colour – pipeline system (Phase 2) Blue colour – SCS (Phase 2) Drill 4 wells (Sirasun, Batur) Lay Flowline and install Subsea Structure Lay Umbilical Install Subsea Control System Flowline tie-in to Existing Terang Manifold Umbilical tie-in to Existing UTA Water Depth : 90 – 250m

8 Major Contracts in TSB Phase-2 Project 1.Subsea X’mas Tree & Subsea Control System (Q2 2015 - Q1 2017) 2.Subsea EPCI (Q1 2016 – Q1 2018) 3.Drilling Rig (Q1 2017 - Q3 2017) 4.Drilling Materials and Services 8

9 SOW and Requirement  Subsea X’mas Tree o Supplied Equipment  4ea x Nom. 7” -10K Subsea Xmas tree  5ea x Subsea Wellhead (18-3/4” x 10K)  5ea x Tubing Hanger o Installation Service o QA/QC Service 9

10 SOW and Requirement  Subsea Control System  Equipment Supply (SCS infield & SCS Topside) One (1) set SCS infield components including UTA, Cobraheads, SDU’s with related accessories, HFL/EFL, spare parts and consumables for CONTRACTOR furnished items, to be fit with SS Installation Contractor’s manufactured umbilical, pile bases, structural members/ protection frames etc. One (1) set of SCS topside components including MCS, EPU and ROS for installation on the existing FPU. One (1) set Tree Instrumentation for respective SSXT: APT, UPTT, DPTT, SAM and SECM.  Support Services project management, design eng, QA/QC, FAT, SIT, EFAT, SRT, transportation, shipment assistance, pre- installation test, pre-submergence check etc.  Installation Services 10

11 SOW and Requirement  Subsea EPCI o Flowlines (incl. Tie-in) 10” Infield Flexible Flowline from SIO-1 to Sirasun Manifold, approx. 7.9km 12” Infield Flexible Flowline from SIO-2 and SIO-3 to Sirasun Manifold, approx. 1.8km and 1.6km 10” Infield Flexible Flowline from BTO-1 to Batur Tee, approx. 1.2km 26” OD, API X65, WT 20.6mm Production Flowline from Sirasun Manifold to Existing Terang Manifold, approx. 23.3km o Subsea Structures (incl. Foundation) Sirasun Manifold - pile foundation Batur In-line Tee - mudmat Pipeline End Termination (PLET) - pile foundation Sirasun Subsea Distrubution Unit (SDU) - pile foundation Batur Subsea Distribution Unit (SDU) – mudmat 11

12 SOW and Requirement  Subsea EPCI o Installation - Water Depths (app. 90m – 250m) Derrick Lay Barge (DLB), S-Lay – To install all flowlines, SCS, Umbilical and subsea structures Diving Support Vessel (DSV) – To perform pre-lay survey, span correction and tie-in (flowlines to subsea structures) – To install pile foundations for subsea structures – To perform Pre-commissioning 12

13 SOW and Requirement  Rig Services – Floater Drilling Unit (Semi-Sub or Drill ship) – 4 wells (Subsea Completion wells) – Water Depth: 350ft – 750ft – Drilling Depth: 4700ft – 6500ft 3horizontal wells and 1 deviated well – Requirement SSXT Handling Capacity – Able to handle SSXT(5m x 5m, 65ton) from supply boat to moon pool (5.5m x 5.5m) 13

14 Required Materials and Services (Drilling) 14 ItemRemarks Casing30”, 20”, 13-3/8” & 9-5/8” Cementing AccessoriesFloat Shoe, Float Collar, Centralizer Liner Hanger9-5/8” x 13-3/8” SSXT & SS-Wellhead7” nom. Bore - 5K SSXT 18-3/4” – 10K SS-wellhead Gravel PackShunt tube system Tubing & Accessories7” or 5-1/2” Tubing, 7” TRSCSSV Bit26”, 17-1/2”, 12-1/4”, 8-1/2” 36” HOP Rental EquipmentDrillling Jar, Fishing Tool, Stabilizer(36”, 26”), Riser brush, Casing scraper

15 Required Services (Drilling & Completion) 15 ItemRemarks Mud & Completion Fluid High Performance WBM, NaCl(/NaBr) Brine Filtering system, Centrifuge rental, LMP at Supply Base Cementing Service 30”, 20”, 13-3/8” 9-5/8” Liner, other pumping, Bulk Plant at Supply Base Mud Logging System w/Data Engineer, Mud logger, Sample Catcher ROV Working Class SSXT & Wellhead Installation Running Tool Rental & Installation Service Directional Drilling PDM, RST, MWD, LWD Casing Installation 30”, 20”, 13-3/8”, 9-5/8” Liner, 7”(5-1/2” Tubing) Torque turn monitoring for tubing Liner Hanger Setting 9-5/8” x 13-3/8” Liner Hanger Open Hole Gravel Pack 8-1/2” horizontal section Well Cleaning Flow 7-3/8” Subsea Landing String, Surface equipment Coiled Tubing N2 lifting, Open/Close FIV, Retrieve BPV Wireline Tractor Open/Close FIV, Retrieve BPV Slickline Pressure/Temperature data acquisition

16 Required Services (Drilling Support) 16 ItemRemarks Site Survey in 2016 as required Rig PositioningFor 4 wells (4times) Anchor Handling Tug Supply Vessel2 AHTS vessels + 1 supply vessel HelicopterDenpasar to/from Rig Weather forecastFor TSB field VSATFor Floater Drilling Unit

17 South Saubi Projects (Exploration) 17

18 Major Contracts in South Saubi Project 1.3D Seismic Survey (Q2 2015) 2.Drilling Rig (Q1 2016) 3.Drilling Materials and Services (Q4 2015 – Q1 2016) 18

19 SOW and Requirements (3D Seismic Survey) 19 3D Marine Seismic Acquisition – Deep marine (WD~3,000ft) – Full fold area: 215 sq. km – Maximum offset: 6 km 3D Seismic Data Processing – Onboard processing through PoSTM – Main processing through PrSTM Onboard QC’s – Acquisition / Navigation / Processing – 30 ~ 40 days

20 SOW and Requirements (Drilling Rig) Rig – Floater Drilling Unit (Semi-Sub or Drill ship) – 1 well (DST if any positive indication, P&A) – Water Depth: 3060ft – Drilling Depth: 13950ft (DST case) Vertical well – Requirement Managed Pressure Drilling System to drill safely reservoir (carbonate) – To mitigate risk in relation with mud loss and kick 20

21 Drilling Materials and Services 21 ItemRemarks Casing 36”, 20”, 16”, 13-5/8”, 9-5/8” and 7” Cementing Accessories Float Shoe, Float Collar, Centralizer Liner Hanger 16” x 20”, 11-3/4” x13-5/8” and 9-5/8” x 13-5/8” SS-Wellhead 18-3/4” – 10K SS-wellhead Bit 42”, 26”, 17”, 14-1/2”, 12-1/4”, 10-5/8” and 8-1/2” Rental Equipment Drilling Jar, Fishing Tool, Stabilizer, Casing scraper Site Survey in 2015 Rig Positioning For 1 well Anchor Handling Tug Supply Vessel 2 AHTS vessels Helicopter Denpasar to/from Rig Weather forecast For South Saubi field VSAT For Floater Drilling Unit

22 Required Services (Drilling & Completion) 22 ItemRemarks Wellhead Installation Running Tool Rental & Installation Service Mud & Completion Fluid High Performance WBM or SBM Cementing Service 20”, 16”, 13-5/8”, 9-5/8”, 7” Liner or Casing, other pumping, Bulk Plant at Supply Base Mud Logging System w/Data Engineer, Mud logger, Sample Catcher Casing Installation 20”, 16”, 13-5/8”, 9-5/8”, 7” Liner Hanger Setting 11-3/4” x 13-5/8” and 9-5/8” x 13-5/8” Liner Hanger ROV Working Class Logging while Drilling PDM, MWD, LWD Hole Enlargement Tool 16” x 20”, 14-1/2” x 17-1/2”, 12-1/4” x 14-1/2”, 10-5/8” x 12-1/4” Managed Pressure Drilling System For carbonate reservoir drilling H2S Service H2S Detector, Breathing apparatus, Blower Wireline Logging Formation evaluation for reservoir, Cement bond log, Set bridge plug, contingency back-off DST For carbonate reservoir testing

23 Thank you 23