1 HOSPITAL PENAWAR DEVELOPMENT & IMPROVEMENT 10 JANUARY 2012

2 OPS PULIH – M & E

3 Pending Job INI ADALAH KERJA -KERJA MAINTENANCE DEPT SAHAJA UNTUK BULAN NOV YANG BELUM DAPAT DISELESAIKAN : 15 NOV 2011 1.HOSTEL A (suiz problem) = not done 20 NOV 2011 1.Tambah lampu papan tanda OHC Clinic = Done 2. Pasang lampu at HK dept = Done 21 NOV 2011 2.Pintu utama A&E goyang teruk = Dlm proses 22 NOV 2011 1. Aircond server room = Dlm Proses (staff baru masuk) 27 NOV 2011 2.Tambah lampu redspot hawker at cafe = lampu dah beli

4 Picture A&E

5 Lighting Classic

6 LIFT ' B ' IMPROVEMENT

7 TARGET BUAT : 10 JANUARY 2012

8 IN PROGRESS

9 BUMBUNG BOCOR

10 IN PROGRESS target date : January 2012 work order date : 31 DEC 2011 masalah : investigate period ~ waiting the raining day (belum dapat apa-apa feedback sehingga 10 JAN 2012)

11 ROOM 305 REFURBISHMENT

12 IN PROGRESS TINTED ~ DONE (4/1/2012) WALLPAPER ~ 12 JANUARY 2012 TRACK CURTAIN ~ 11 JANUARY 2012 CURTAIN ~ 11 JANUARY 2012 * CEILING YANG BOCOR BELUM DAPAT DIPERBAIKI ALTERNATIVE * TUKAR PAPAN CEILING SAHAJA UNTUK TIDAK NAMPAK KOTOR DAN BERKULAT

13 WORK DONE - TINTED

14 ASSEMBLY COVERED AREA

15 IN PROGRESS target date ~ 2nd January work order date ~ 31 DEC 2011 masalah ~ RUNGATE belum memberi feedback untuk tetapkan tarikh buat Rungate : waiting for approval

16 CURRENT AND PROPOSE IMAGE

17 MRI

18 DEMOLISH EXISTING WALL

19 CLEARANCE

20 TRANSIT WARD 3

21 overall all done accept wall lighting, tv installation and call bell lighting and painting wall not decide yet...

22 RECEPTIONIST COUNTER REFURBISHMENT

23 CURRENT

24 PROPOSAL DR ADNAN APPROVED FOR 3 RD DESIGN 1 2 3

25 OPS SUCI

26 ON JOB Training on 4-5 January 2012 1. Siti Nurain Hamzah

27 IT DEVELOPMENT OT CLINICAL SYSTEM – 80% -TARGET NEXT WEEK RUN NURSING REPORT – RECENT UPDATE – TRAINING TROLLEY CHINA – ON THE WAY

28 PENAWAR CORNER LANDSCAPE

29 IN PROGRESS KERJA - KERJA MEMBUAT PLAN MINI PADANG GOLF SEDANG GIAT DIJALANKAN DAN KERJA - KERJA PEMBERSIHAN RUMPUT DAN PEMOTONGAN JUGA DIJALANKAN.

30 IN PROGRESS

31 NURSING - ROSTER MX & TRAINING

32 TRAINING Meeting with Ina & Matron Marziah *Schedule / Content of Labour room Mx a) Antenatal care - Stages of labour b) Post Natal Care c) Observation - Vital sign, Pad chart, contraction, Feotal Heart, VE. d) Epidural Care e) Medication f) Compication g) Emergency Rescue h) Spritual Support i) Education for pt's & family will e-mail slide A.S.A.P.

33 CAFE IMPROVEMENT

34 PENAMBAHA N SIMEN FOOD DISPLAY NASI CAMPUR HAWKERS AREA SINK I DAPUR WORKING TABLE S I NK I KA K I L I MA ROTIROTI DONUT DISPLAY CHILLER AISKRIMAISKRIM MEJA MAKAN CAFÉ & KITCHEN DEVELOPMENT NEW PLAN LAYOUT PETI SEJUK ROTI CANAI MEJA BUAT AIR CASHEIR COUNTER

35 BUDGET FOR NEW EQUIPMENT QUOTATION / BUDGET (RM)DECISSION 1. FOOD DISPLAY 5 @ 6 HOLD STAINLESS STEEL – 6 HOLE/1 RACK RM 2030, 5 HOLES/2 RACK RM 2080, 6 HOLE/2 RACK RM 2150 APPROVED - 5 HOLES/2 RACK RM 2080, TO PROCEED PO 2. DAPUR 2 @ 3 TUNGKU STAINLESS STEEL NASI AYAM STAINLESS STEEL STALL – 2 TUNGKU RM 950, 3 TUNGKU RM 1050 – RM 1250 APPROVED - 3 TUNGKU RM 1250 TO PROCEED PO RM 1230 TO PROCEED PO 3. COUNTER AIR STAINESS STEEL – 2 RACK RM 1330, 2 RACK & SINK RM 1660 TO DESIGN BY RUNGATE – EN KENT 4. COUNTER CASHEIR – BUDGET RM 1500 (TO FIND QUOTATION) TO DESIGN BY RUNGATE – EN KENT 5. MENU LIGHT BOX - 10 BOX – RM 1000 (EXCLUDE PICTURE) WAITING HAWKERS & KOUNTER AIR RENOVATION DONE 6. MEJA MAKAN + KERUSI EMPAT SEGI @ BULAT 10 - 12 SET – BUDGET RM 300/SET = 3000 (TO FIND QUOTATION) PENDING 7. NEW PINGAN MAKAN HIJAU (50 PCS) BERALAS KERTAS TOTAL BUDGET RM 10,510 – BUDGET RM 150 (TO FIND QUOTATION) TOTAL BUDGET APPROVED RM 4560

36 IN PROGRESS – PO ISSUE

37 ORHER THING / MATTERSPROPOSEDECISSION 1. PROPOSE KITCHEN HELPER CUM CHEF – PROPOSE MENU ALA THAI DAN LAUK NASI CAMPUR - ADA CANDIDATE APPROVED 2. WATER FILTER FOR DRINK TO REDUCE COST EXPENSES – TO REDUCE COST WATER SUPPLY FROM DR SUKIDA RM 70/WEEK @ RM280/MTH APPROVED BUDGET RM 1000

38 CAFÉ RENOVATION WORKBUDGET (RM)DECISSION 1. KERJA MENYEMIN DEPAN HAWKERS 2. KERJA PEMECAHAN BILIK BUAT AIR SEKARANG TOTAL BUDGET RM 4000 – RM 500 – RM 3500 JOBS ORDER: REQUEST FOR PLAN AND DESIGN FORWARD TO RUNGATE – DONE

39 PENAWAR BUS

40 IN PROGRESS BUS DESIGN APPROVAL Target : Date send letter : 11 January 2012 - SPAD Muar Date to get approval : within 1 week.

41 AMBULANCE JER - NEW DESIGN & PUSPAKOM

42 IN PROGESS PROJEK: 1. NEW DESIGN EXTERNAL FOR AMBULAN JER 9594 2. NEW DESIGN FOR INTERNAL (PESSENGER AREA) 3. UPGRADING EQUIPMENT / MACHINE 4. PENGHANTARAN AMBULAN KE PUSPAKOM UNTUK PEMERIKSAAN BERKALA PLANNING THIS WEEK: 1.1 - MEMBUAT LAKARAN CADANGAN DESIGN AMBULAN (STICKER BAHAGIAN LUAR) 1.2 - CONFORMATION STICKER 1.3 - MENGHANTGAR LAKARAN STICKER KE SYARIKAT PEMBUAT STICKER DAN DAPATKAN QUOTATION 1.4 - CONFORMATION STICKER DAN HANTAR AMBULAN UNTUK PENAMPALAN 1.5 - PENGHANTARAN PEMERIKSAAN KE PUSPAKOM. GAMBARAN LAKARAN KOSONG AMBULAN

43 PROPOSAL NEW DESIGN

44 NEW LOOK

45 NEW UNIFORM – HOSPITAL BLOCK

46 Total staff involved:- NoDepartmentTotal Staff 1Billing4 2Cashier/Dispensary7 3Imaging7 4Medical Record5 5Physio5 6Clinic6 7Reception4 Total38

47 1st stage - distribution to Medical Record & Receptionist Staff - distribute by Thursday 12.1.12 - Staff list - * Samsilawati said * Norwahidah Rahmat * Mohd Nizwan * Premela * Siti Aminah * Siti Syafiqa * Siti NUrain Hamzah * Zulaiha Nordin * Noorpazilah Tukiman

48 NEUROSURGERY

49 UPDATE - Infrastructure for ICU - ICP Monitor - pending and sourcing by Ahmad (Post Craniotomy) - Appointment with Dr Johari (visiting consultant ) - 19.01.2012

50 HEALTHY WORK POLICY FOR STAFFS

51 CATEGORY Pre employment medical check up - By category - male & female - Type of test - * Medical History * BMI * Urine Drug * UPT * Blood Pressure * height * Fasting Blood Sugar * Proposed date - 15th January 2012

52 THANK YOU