MEANS OFFICE BUILDING PRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL Eddie Aquino, Jimmy Fu, Alvin SarmientoSpring 2011.

Similar presentations


Presentation on theme: "MEANS OFFICE BUILDING PRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL Eddie Aquino, Jimmy Fu, Alvin SarmientoSpring 2011."— Presentation transcript:

1 MEANS OFFICE BUILDING PRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL Eddie Aquino, Jimmy Fu, Alvin SarmientoSpring 2011

2 PROJECT TEAM Eddie AQUINO PROJECT MANAGER/3D MODELLER Jimmy FU PROJECT ENGINEER/ CONSTRUCTION SITE LOGISTICS Alvin SARMIENTO PROJECT ESTIMATOR/SCHEDULER 2

3 PROJECT REQUIREMENTS  Three-story office building w/ underground garage  Concrete waffle slab  Spread footings  Structural Steel framing with steel deck  Penthouse structure CMU  Steel joist roof  Construction budget 10.5 million – 12 million

4 PROJECT LOCATION COMPONENT Street Looking Southeast COMPONENT Street Looking Southwest

5 PROJECT LOCATION  2.60 Acres  IP (PD)  URBAN  Freeways

6 3D MODEL PDF Simulation

7 Cost Estimates  Timberline Sage  Ranked most used estimating software by ENR AutoCAD Timberline Primavera MS Project

8 Cost Estimates  Features  CSI MasterFormat  Provides detailed labor, material, and equipment cost estimates  Provides total cost/unit and total amount per item

9 Cost Estimates  Problems Encountered  Can not access Division Mechanical and Electrical Systems

10 Cost Estimates  Problems Encountered  Final cost estimates from Timberline does not match cost estimates given in excel sheet

11 Schedule  MS Project  Timeline: January 27, 2011 – January 6, 2012  RS Means 2002 and Golden Bear Construction Inc. RS Means Office Building Schedule Superstructure GarageMeasurementDaily Output based on RS Means productionApproximate Completion Structural Steel Columns/Beams114 Tons14.4 Tons8 days 1st FloorMeasurementDaily Output based on RS Means productionApproximate Completion Structural Steel Columns/Beams114 Tons14.4 Tons8 days Metal Deck18,900 SF3,500 SF6 days Concrete Fill Over Metal Deck18,900 SF8,640 SF3 days Waffle Slab18,900 SF2,380 SF8 days Fire Proofing18,900 SF3,000 SF7 days

12 Schedule

13  Accuracy of schedule and duration of project  Each activity has a predecessor  At any time during schedule, one or more activities can occur  Advantages  Simple to use  Disadvantages  Activities may not have any predecessor or successor

14 CONSTRUCTION SITE

15 CONSTRUCTION EQUIPMENT ACTION MOBILE INDUSTRY MODEL 1250 (46’x12’) LINDEN COMANSA LC 500 Series


Download ppt "MEANS OFFICE BUILDING PRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL Eddie Aquino, Jimmy Fu, Alvin SarmientoSpring 2011."