TWG III REPORT DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA.

Similar presentations


Presentation on theme: "TWG III REPORT DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA."— Presentation transcript:

1 TWG III REPORT DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA DI JOGJAKARTA PROVINCE UNIVERSITAS MUHAMMADIYAH YOGYAKARTA

2 Objectives Utilize energy efficiently and rationally reducing the energy usage to supporting national development. Energy optimization, to reduce the energy cost. Conserve natural energy resources through technology choice policy and energy utilizing efficiently to achieve energy security.

3 Regulation Government Regulation No.5 /2006: National Energy Policy Presidential Decree No.2 /2008: Water and Energy Saving Decree of Ministry of ESDM RI No. 031 /2005: Energy Saving Procedure

4 Electrical Energy consumer

5 Survey Result Household Total respondent : 320 (Urban : 200, Suburban : 120) Own CRT TV : 66% Own Refrigerator : 57% Own AC : 29% Own PC : 36%

6 Industry Only 200 KVA and above Leathers : 20 Limestones : 49 Foods : 36 Woods : 30 Hospital Class C and above (3500 VA until 200 KVA) Total :63

7 Public Sector (Goverment Building) 2200 VA – 5500 VA : VA – 200 KVA : 146

8 Household Scenario Change old refrigerator to energy efficient refrigerator Use 160 liter, 70 watt refrigerator Price is IDR 1,400,000 Pay back period is 118 months for electricity price IDR 495 and 74 months for IDR 790

9 Refrigerator Total savingsIDRKWhFor 600 Optimistic(31,812,520,277)139,877,13683,926,281,600 Moderate(19,290,586,187)85,950,86451,570,518,400 Total Energy Savings

10 Household Scenario Television Reduce time, turn off mode

11 Total Energy Savings Total savingsIDRKWh Optimistic8,874,119,16919,519,145 Moderate8,874,119,16919,519,145

12 Household Scenario AC Replace old AC with AC with inverter (energy efficient AC) AC with inverter is 175 watt Price is IDR 5,000,000

13 AC with inverter Total savingsIDRKWh Optimistic3,742,250,76052,855,740 Moderate2,494,833,84035,237,160 Total Energy Savings

14 Household Scenario Personal Computer Replace Personal Computer with Notebook PC price is IDR 2,750,000 Netbook price is IDR 3,500,000 All scenario are not feasible For electricity price IDR 495, pay back period more than 10 years For electricity price IDR 790, pay back period is 109 months

15 Total Energy Savings

16 Total savingsIDRKWhFor 600 Optimistic(94,190,031,603)80,068,00948,040,805,376 Moderate(58,868,769,752)50,042,50630,025,503,360 Calculation with electricity price IDR 495 include Calculation exclude electricity price IDR 495 Total savingsIDRKWhFor 600 Optimistic(17,171,687,011)26,935,83416,161,500,160 Moderate(10,732,304,382)16,834,89610,100,937,600

17 Industry Implementing Altivar Inverter Pay back period is 37 months

18 Total Energy Savings Total savingsIDRKWh Optimistic216,691,6081,748,736 Moderate135,432,2551,092,960

19 Industry Improvement of Unbalance Voltage Energy savings : 8689 KWh/year Total savingsIDRKWh Optimistic Moderate

20 Social Sector Operating time reducing of AC Reduce 2 hours Total savingsIDRKWh Optimistic Moderate

21 Social Sector Implementing Altivar Inverter Pay back period is 34 months

22 Total Energy Savings Total savingsIDRKWh Optimistic199,043,2611,496,880 Moderate110,579,589831,600

23 Social Sector Refrigerant Retrofit Pay back period is 34 months

24 Total Energy Savings Total savingsIDRKWh Optimistic111,296,3793,742,200 Moderate 74,197,5862,494,800

25 Public Sector Refrigerant Retrofit Pay back period is 34 months

26 Total Energy Savings Total savingsIDRKWh Optimistic353,592,4793,635,280 Moderate 212,155,4872,181,168

27 Public Sector Operating time reducing of AC Reduce 1 hours Total savingsIDRKWh Optimistic49,230,720140,659 Moderate 29,538,432199,869

28 Government involvement Financial Subsidy Tax reduction Loan Knowledge / Awareness Technical Capacity