1 El Cerrito High School Stadium 07/15/2014

2 Conceptual Design

3  General Contractor Wright Contracting  Architect of RecordWLC Architects  Construction ManagerHector De Leon  Project EngineerMaria Zupo  Inspector of RecordKris Gilbert

4 Site Plan

5  Contract Amount $13,438,000  Notice of Award11/21/13  Notice to Proceed01/27/14  Duration608 days  Completion Date09/27/15  Change Order$10, (0.07%)

6  Site retaining walls at Ashbury and Colusa  Fence piers at Colusa  Building retaining walls and foundations  Site grading and compaction  Underground utilities

7 Backfilling at Ashbury

8 Site Walls and Foundation

9 Building Footings

10 Retaining Wall Construction at Colusa

11 Retaining Wall Construction at Ashbury