HOLY TRINITY CATHEDRAL RENOVATION OF INNER DOME 2009 BY ALEXANDER BUILDERS & CO. LTD.

Similar presentations


Presentation on theme: "HOLY TRINITY CATHEDRAL RENOVATION OF INNER DOME 2009 BY ALEXANDER BUILDERS & CO. LTD."— Presentation transcript:

1 HOLY TRINITY CATHEDRAL RENOVATION OF INNER DOME 2009 BY ALEXANDER BUILDERS & CO. LTD.

2 First assessment of inner dome cavity to identify make-up of structure and extent of damage. The inner dome support structure was found to consist of a Knogg structure (timber, mesh, mortar and plaster creating an inner dome) First Assessment – HTC inner dome

3 The inner dome support structure was compromised by severe termite infestation leading to cracks in the plaster. This would have to be rectified without affecting or damaging the artisan works painted on the plaster. Pest control was carried out using gas fumigation and residuals by Carib Pest before any works began on the interior structure. Works commence to reinforce & repair substructure

4 EPS foam in blocks was used to support the inner dome so that a small work crew could enter the inner cavity without damage to the face of the plaster throughout. Set-up of support structure

5

6

7

8

9

10

11 Work crews entered the 4ft inner cavity through this small crawl space to clear out all debris and affected wood before a new system of structural support was installed. Entrance to one quadrant of the Inner Dome

12 Note the wood structure that had clear signs of termite trails. Inside one quadrant of the four

13 Work-In-Progress

14

15

16

17

18

19

20

21 The Inner Dome Upon Completion

22 Moulding replaced with EPS Moulding

23 Inner Dome Upon Completion

24