Siemens Cranes Important Points in SIMOCRANE Engineering and Commissioning Dr. Qing Chen Product Management.

Similar presentations


Presentation on theme: "Siemens Cranes Important Points in SIMOCRANE Engineering and Commissioning Dr. Qing Chen Product Management."— Presentation transcript:

1 Siemens Cranes Important Points in SIMOCRANE Engineering and Commissioning Dr. Qing Chen Product Management

2 V2.0 SP2 has default setting to aviod problem 1&2
Overview V2.0 SP2 has default setting to aviod problem 1&2 Problem Problems: Simotion CPU goes to Stop frequent encoder error or TO-error Invert-ready signal comes and goes PLC-control does not work Too long time for axis switchover Trolley’s reaction is too slow Project doesn’t work after copy and paste Axis switchover takes too long time

3 Task-Configuration Setting
Problem 1: CPU goes to stop Solution: ‘Task configuration’ in ‘execution system’ should NOT be set at ‘error reaction with program error’ with CPU in Stop but ExcutionFaultTask If the reason is task overflow, then ‘Task configuration’ in ‘execution system’ can be set at ‘number of level overflows in the loop clock’ max. 5 Solution

4 TO-Configuration setting (1)
Problem 2: frequent encoder error Solution: expert listconfiguration data, set 'TypeOfAxis.NumberOfEncoders.Encoder_1.SensorControlConfig.tolerateSensorDefect’ to YES Solution

5 TO-Configuration setting (2)
Problem 2: frequent TO-error Solution: expert listconfiguration data, set ‘TypeOfAxis_DriveControlConfig_pulsesEnabled_bitNumber’ to 11  'TypeOfAxis_DriveControlConfig_pulsesEnabled_pzdNumber  to 4 'TypeOfAxis_DriveControlConfig_releaseDisableMode to 7 Solution

6 TO-Configuration setting (3)
Problem 2: frequent TO error Solution: expert listconfiguration data, set 'RestartCondition.restartAxisCondition’ to NO_CONSTAINTS Solution

7 TO-Configuration setting (4)
Problem 2: frequent TO error Solution: expert listconfiguration data, set 'Restart.behaviorInvalidSysvarAccess’ to DEFAULT_VALUE Solution

8 Leadscrw pitch = diameter of wheel / drum * π
TO-Mechanics Setting Problem 3: Invert-ready signal comes and goes Solution: Setting Load gear / Measureing gear / Leadscrew pitch Solution Leadscrw pitch = diameter of wheel / drum * π

9 TO-Monitoring Setting (1)
Problem 3: Invert-ready signal comes and goes Solution: Following error Deactivated at beginning Setting at the end of commissioning Solution

10 TO-Monitoring Setting (2)
Problem 3: Invert-ready signal comes and goes Positioning and Standstill Solution

11 PLC-program Problem 4: PLC control does not work
Problem 5: Switchover takes too long time Solution: Correct sequence (PLC) for activating of function refer to application examples of S7 control (Chapter 8.4) refer to S7-Program examples on CD (V2.0 SP2) Efficient programming Do not use unnecessary Timer or too long Timer

12 Jerk = (maximum_speed/ramp uptime) / Jerk_time
Setting of Jerk Problem 6: Trolley starts up too slowly 6s (ramp-up=4s, V_max=4216.5mm/s, jerk=600mm/s^3) Solution: increasing jerk (till V2.0 SP1) or reduce jerk-time (at V2.0 SP2) Jerk = (maximum_speed/ramp uptime) / Jerk_time High jerk (2000)  shorter jerk_time (0.5s) Solution

13 Project copy and paste Problem 7: Copy old application project to use for new project, upgrading with new Crane Libraries, the same function doesn’t work. Solution: remove the old connections, see attachment Solution User Application Project should be updated in certain time interval by using the standard-application of Simocrane Basic Technology

14 Axis Switchover Problem 8: Axis switchover takes too long time
Solution: Optimizing PLC-Program Change setting of an internal parameter of Sinamics (only for Sinamics FW V2.6), please contact Siemens Cranes Solution

15 Thank you