1 Project Management Tools MHA 6350 Dr. Burton

2 How Hillary looks upon a crook vs. how Hillary looks upon an American hero:

3 Tools GANTT Charts PERT/CPM

4 GANTT CHARTS Developed by Charles Gantt in 1917. The layout of a Gantt Chart uses information in columns on the left of a matrix to identify tasks, task managers, duration and in some cases cost. To the right of each task in the matrix is a bar that denotes to duration of the task. Project management software employs Gantt charts.

5 Project: Constructing a Home Task (Activity) (a) Excavating (b) Pour Foundation c) Outside Plumbing (d) Framing (e) Inside Plumbing (f) Wiring (g) Roofing (h) Brickwork (i) Plumbing Inspection (j) Shingling (k) Cover Walls (l) Interior Finishing (m) Exterior Finishing (n) Landscaping

6 Project: Constructing a Home Task (Activity)Preceding Activity Expected time to complete (a) Excavating--5 days (b) Pour Foundationa2 c) Outside Plumbinga6 (d) Framingb12 (e) Inside Plumbingd10 (f) Wiringd9 (g) Roofingd5 (h) Brickworkb9 (i) Plumbing Inspectionc, e1 (j) Shinglingg2 (k) Cover Wallsf, i, j3 (l) Interior Finishingk9 (m) Exterior Finishingh, g7 (n) Landscapingm8

7 Project: Constructing a Home Task (Activity) (a) Excavating (b) Pour Foundation c) Outside Plumbing (d) Framing (e) Inside Plumbing (f) Wiring (g) Roofing (h) Brickwork (i) Plumbing Inspection (j) Shingling (k) Cover Walls (l) Interior Finishing (m) Exterior Finishing (n) Landscaping 10/5 10/10 10/15 10/20 10/25 10/30 11/4 11/9 11/14 11/19 11/24 11/29

8 Examples Links http://www.smartdraw.com/examples/view/index.aspx?catID=.Examples.Sma rtDraw.Gantt_Charts%2c_Project_Charts_%26_Timelines.Gantt_Charts http://www.ganttchart.com/

9 13-28 1 3 4 5 6 2 1 2 3 4 5 7 11 10 8 9 6 7 89 11 12 13 14 15 16

10 Program Evaluation and Review Technique (PERT) May also be referred to as: Critical Path Method (CPM) Developed in the late 50s by the Navy. Was used the Polaris program for submarined launched ballistic missiles. Originally adopted by the Department of Defense for large projects. Later was adopted by construction industry. PERT uses work groupings called activities. Activities are measured in time. Each activity is represented by an arrow.

11 Project: Constructing a Home Task (Activity)Preceding ActivityExpected time to complete (a) Excavating--5 days (b) Pour Foundationa2 c) Outside Plumbinga6 (d) Framingb12 (e) Inside Plumbingd10 (f) Wiringd9 (g) Roofingd5 (h) Brickworkb9 (i) Plumbing Inspectionc, e1 (j) Shinglingg2 (k) Cover Wallsf, i, j3 (l) Interior Finishingk9 (m) Exterior Finishingh, g7 (n) Landscapingm8

12 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5

13 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 Dummy Activity

14 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 0 5 29 7 19 11 TE Earliest Possible Event Time

15 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 0 5 29 7 1930 24 28 26

16 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 0 5 42 7 1930 24 1624 31 33 39

17 Project: Constructing a Home Task (Activity)Preceding ActivityExpected time to complete (a) Excavating--5 days (b) Pour Foundationa2 c) Outside Plumbinga6 (d) Framingb12 (e) Inside Plumbingd10 (f) Wiringd9 (g) Roofingd5 (h) Brickworkb9 (i) Plumbing Inspectionc, e1 (j) Shinglingg2 (k) Cover Wallsf, i, j3 (l) Interior Finishingk9 (m) Exterior Finishingh, g7 (n) Landscapingm8 FINISH TOTAL 42 days

18 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 0 5 29 7 19 24 31 30 33 42 CRITICAL PATH 29 TL Latest Allowable Event Times 42 Backwards Pass Subtract each activity from succeeding TL Where event is beginning point for more than one activity use the smallest difference. 33 30 197 5 0 34 27

19 34 5 6 28 7 1 9 1011 Outside plumbing Source: Lapin, 1994 Start a Excavating A PERT network for constructing a home. Inside plumbing Plumbing inspection FINISH b Foundation d Framing f Wiring k Walls l Interior Finish h 9 Brickwork Roof- ing Landscaping Exterior Finishing 7 m 0 j 2 Shingling n 8 5 2 12 9 3 9 c 6 e 10 i 1 g 5 0 5 29 7 19 24 31 3033 42 CRITICAL PATH 29 Event Slack Times = TL - TE 42 3330 19 7 5 0 34 27 TL 3 TE 3 3 0 00 0 0 0 0 0

20 Planning and Control Activity Scheduling ES=Early Start Time = TE for preceding event. EF=Early Finishing Time = ES + t LF=Late Finishing Time = TL for succeeding event. LS=Late Start Time = LF - t

21 Limits for Scheduling (a) Excavating 50055 (b) Pour Foundation 25577 c) Outside Plumbing 65231129 (d) Framing 127719 (e) Inside Plumbing 1019 29 (f) Wiring 919212830 (g) Roofing 519222427 (h) Brickwork 97181627 (i) Plumbing Inspection 129 30 (j) Shingling 224282630 (k) Cover Walls 330 33 (l) Interior Finishing 933 42 (m) Exterior Finishing 724273134 (n) Landscaping 831343942 Activity t Starting Times Finishing Times ES LS EF LF Preceding TE LF – t ES + t Succeeding TL

22 Activity Slack time = LF - EF. (a) Excavating550 (b) Pour Foundation770 c) Outside Plumbing291118 (d) Framing19 0 (e) Inside Plumbing29 0 (f) Wiring30282 (g) Roofing27243 (h) Brickwork271611 (i) Plumbing Inspection30 0 (j) Shingling30264 (k) Cover Walls33 0 (l) Interior Finishing42 0 (m) Exterior Finishing34313 (n) Landscaping42393 Activity Finishing Time Activity Slack Time LF EF


Download ppt "Project Management Tools MHA 6350 Dr. Burton. How Hillary looks upon a crook vs. how Hillary looks upon an American hero:"