Presentation is loading. Please wait.

Presentation is loading. Please wait.

PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING.

Similar presentations


Presentation on theme: "PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING."— Presentation transcript:

1 PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING NOVEMBER 20, 2013

2 RSA IMPROVEMENTS, PMP & STANDARDS PROGRAM

3 PROGRAM YEAR 2013 TASKCONTRACTVALUEMBE 1 Runway 15R-33L Standards Compliance Earthwork Project $21,800,00025% 2 Runway 15R Deicing Pad Pavement Rehab. And Stnds. Compliance $14,169,00030% 3 Low Maintenance Grassing Test Plots $133,00025% 4 General Aviation Pavement Rehabilitation $994,00020% 5 RSA Program Environmental Stream Restoration Project $2,079,00026% 6 Runway 15L-33R Runway Safety Area Improvements $4,960,00020% 7 Runway 15R-33L RSA, PMP and Standards Compliance Project $83,235,00020% 8 Runway and 15R- 33L Obstruction Clearing Project $413,0004% 9* Runway 15R-33L NAVAIDS Project $5,409,00013% *Graphic location same as Task 7

4 15R 33L EARTHWORK CONTRACT VALUE: $ 21,756,470 Contract Completes – Summer 2014 MBE: 25% PROJECT OVERVIEW: Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall. CONTRACT VALUE: $ 21,756,470 Contract Completes – Summer 2014 MBE: 25% PROJECT OVERVIEW: Clearing and grubbing. Storm drain installation. Box culvert installation. Sanitary sewer and underground fire hydrant relocation. Mass earthwork, grading and retaining wall.

5 RUNWAY 15R DEICING CONTRACT VALUE: $ 14,168,409 Contract Completes – November 2013 MBE: 30% PROJECT OVERVIEW: Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings. CONTRACT VALUE: $ 14,168,409 Contract Completes – November 2013 MBE: 30% PROJECT OVERVIEW: Removal of existing pavement. Installation of new glycol drainage infrastructure, lighting, diversion vaults. New concrete pavement and pavement markings.

6 ENVIRONMENTAL STREAM RESTORATION CONTRACT VALUE: $ 2,078,771 Contract Completes – July 2014 MBE: 26% PROJECT OVERVIEW: Grading of stream channels and placement of fill. Construction of in-stream structures. Removal of invasive vegetation and plantings. CONTRACT VALUE: $ 2,078,771 Contract Completes – July 2014 MBE: 26% PROJECT OVERVIEW: Grading of stream channels and placement of fill. Construction of in-stream structures. Removal of invasive vegetation and plantings.

7 RUNWAY 15L 33R RSA CONTRACT VALUE: $ 4,959,398 Contract Completes – Spring 2014 MBE – 14% PROJECT OVERVIEW: New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS. CONTRACT VALUE: $ 4,959,398 Contract Completes – Spring 2014 MBE – 14% PROJECT OVERVIEW: New vehicle service road and airfield equipment access road. Drainage pipe, box culvert and structure installation. Preparation of site and infrastructure for future relocation of existing NAVAIDS.

8 CONTRACT VALUE: $ 83,235,000 Proposed Schedule – September 2013 to April 2015 PROJECT OVERVIEW: Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements. CONTRACT VALUE: $ 83,235,000 Proposed Schedule – September 2013 to April 2015 PROJECT OVERVIEW: Comprehensive Pavement Rehabilitation. Runway Safety Area Grading and Improvements. NAVAID Relocations and Infrastructure Improvements. Runway and Taxiway Lighting Improvements. Taxiway Realignments. Runway Incursion Prevention Elements. RUNWAY 15R 33L RSA

9 PROGRAM YEAR PROGRAM ELEMENTS 6 Runway Navaids & Runway 28 Displacement 15A New T/W Uniform & T/W Uniform 1 And South Portion De-ice Pad 15B Runway 4-22 Conversion To Taxiway Papa 15C New Taxiway Construction (EB- 75) 15D Old Taxiway Delta Demolition PROGRAM VALUE M 15D 15B 15C 15A 6

10 10 EXISTING TERMINAL SECURITY CHECKPOINTS IN THE THROAT OF THE CONCOURSES RESTRICT EGRESS/ EVACUATION CAPACITY CORRIDOR WIDTH IN ORIGINAL PORTIONS OF CONCOURSES INADEQUATE

11 11 LONG TERM TERMINAL PLAN UPPER LEVEL PLAN NEW CHECKPOINTS BETWEEN CONCOURSES BEHIND SECURITY CONNECTORS ALLOW FOR LOAD BALANCING AND CONNECTING FLIGHTS

12 12 LONG TERM TERMINAL PLAN PHASING PLAN CONCOURSE D ORIGINALLY FIRST BECAUSE DEFICIENCIES WERE GREATER DUE TO THE NUMBER OF GATES SERVED. SWA / AIRTRAN MERGER AND CONSOLIDATION ON CONCOURSES A/B/C SHIFTED PRIORITIES TO BC CONNECTOR AB C E

13 13 CONCOURSE C WIDENING B/C CONNECTOR BC CONNECTOR PROGRAM TWO CONSTRUCTION PROJECTS

14 14 BC CONNECTOR FINAL UPPER LEVEL PLAN 9 LANE CHECKPOINT

15 BC CONNECTOR CONTRACT VALUE: $ 43,937,000 MBE: 20% PROJECT OVERVIEW: Secure passenger corridor connecting Concourse B and C. Nine (9) Lane Security Checkpoint. Observation Deck improvements. Concessions and Office Spaces.

16 BC CONNECTOR

17 NEW BC SECURITY CHECKPOINT

18 NEW BC CONNECTOR

19 CONCOURSE C WIDENING CONTRACT VALUE: $ 28,799,512 Completion Date – January 2013 MBE: 31% PROJECT OVERVIEW: Renovate Concourse C to include larger passenger hold rooms and a wider corridor and exit. New passenger boarding bridges. New baggage handling system. New public restrooms. Modify mechanical & electrical systems.

20 DE CONNECTOR CONTRACT VALUE: $ M CONTRACT VALUE: $ M Proposed Design Schedule: September September 2014 Proposed Design Schedule: September September 2014 Proposed Construction Schedule: January November 2016 Proposed Construction Schedule: January November 2016

21 DE CONNECTOR

22 ARRIVAL LEVEL PLAN

23 DE CONNECTOR DEPATURE LEVEL PLAN

24 NEW DE SECURITY CHECKPOINT

25 DE SECURITY CHECKPOINT VIEW FROM TERMINAL D

26 DE SECURITY CHECKPOINT VIEW FROM TERMINAL E

27 DE CONNECTOR

28 VIDEO OF PROJECT OVERVIEW: BWI CONFORM.wmv

29 *Program **Advertised ***BidsDue ****Bid Opening Contract Number & TitleProposed DateProject Value MAA-CO Parking Access and Revenue Control System (PARCS) ***May 2013$8M-$11M MAA-CO Airfield Capacity Enhancement Project **April 2014$80M MAA-CO International Building Expansion **December 2013$7M MAA-CO Comprehensive Interior/Exterior Modification 2014 **November 2013$25M MAA-CO Long Term Parking Lot B Pavement Rehabilitation **November 2013$1.7M MAA-CO Pedestrian Walkway from CRCF to the East Tenant Lot *October 2013$.5M MAA-CO Public Parking Area Pavement Rehabilitation **November 2013$1M MAA-CO Central Terminal Third Floor Elevator Upgrades **November 2013$.5M MAA-CO Air Cargo Drive Pavement Rehabilitation *February 2014$1.7M


Download ppt "PAUL L. SHANK P.E., C.M. CHIEF ENGINEER BWI MARSHALL AIRPORT MARYLAND TRANSPORTATION BUILDERS AND MATERIALS ASSOCIATION WHERE WE ARE – WHERE WE ARE GOING."

Similar presentations


Ads by Google