1 UTA Airport TRAX Line North Temple Viaduct & Construction Phasing

2 North Temple Viaduct Detours North Temple viaduct closure and construction begins April 18. Construction will take 18 months Alternative A Westbound detour – 300 West to 600 North to 900 West Alternative B Eastbound detour – 900 West to 400 South to 300 West

3 UTA Bus Routes UTA bus routes that travel North Temple will be rerouted beginning April 4. For specific route information visit

4 When Is the Airport Line Being Built?

5 North Temple Construction - Phases Phase 1 Phase 2 Phase 3 Phase 4 Phase 5

6 Spring/Summer 2010 North Temple Phasing – Spring 2010 North Temple Phasing – Spring/Summer 2010

7 Spring 2011 Summer/Fall 2010 North Temple Phasing – Summer/Fall 2010 North Temple Phasing – Spring 2011

8 Summer 2011 North Temple Phasing – Summer 2011

9 Downtown Phasing – Spring 2012 – Fall 2012

10 Communications and Marketing Weekly construction updates Regular one-on-one visits to corridor properties Comprehensive marketing plan Milestone events Direct mail Radio Billboards Print Looking for others ways to communicate construction information

11 Airport Construction & Viaduct Open House Thursday, March 18 5 p.m. to 7 p.m. UTA FrontLines Headquarters 669 West 200 South

12 Thank you Matt Sibul, UTA Airport TRAX Project Manager: Chad Saley, UTA Public Involvement: Bill Knowles, Downtown Salt Lake Ombudsman: Hour Construction Issue Hotline: