Download presentation
Presentation is loading. Please wait.
Published byHudson Millage Modified over 10 years ago
1
Suvarnabhumi International Airport ..WELCOME MEE Net..
MJTA Consortium
2
SUVARNABHUMI INTERNATIONAL AIRPORT
. MJTA Consortium
3
SUVARNABHUMI AIR CONDITIONING SYSTEM
4
SUVARNABHUMI AIR CONDITIONING SYSTEM
BUILDING CONFIGURATION The Terminal building requires to have large hall area without concrete pole or with minimal concrete pole for passengers’ convenience. For maximum passengers comfort with ease of traveling within the airport compound, the building comprise of two sectors, the Terminal and Concourse building. The Concourse building is for airplane connection to boarding bridges. The Terminal building is for handling departure and arrival passengers. For energy saving purpose, the airconditioning will be provided only from floor level to 3 or 4 meter above the floor since passengers will not stay higher than 2 meters above the floor MJTA Consortium
5
SUVARNABHUMI AIR CONDITIONING SYSTEM
BUILDING SIZE Concourse Width m. Length 3,123 m. Hight m. Terminal Width 108 m. Length 441 m. Hight 40 m. MJTA Consortium
6
SUVARNABHUMI AIR CONDITIONING SYSTEM
AREA FOR AIR CONDITIONING Concourse 248,445 SQ.M. Terminal 119,906 SQ.M. TOTAL OF ,351 SQ.M. MJTA Consortium
7
CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM
Usage of direct sun light with minimal electrical lamps during day time. Air conditioning will be provided only from floor level to 3 or 4 meter above the floor to reduce the air conditioning load by means of Stratification technique. This technique use Radiant Floor Cooling together with Recirculated Air Cooling System. 3. Control intake fresh air for continual changing number of passengers. MJTA Consortium
8
CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM
4. Adjust Variable Chilled Water Volume for continual changing cooling load. Use Chilled Water Temperature Difference ( delta T ) larger than normal conventional type which will require lesser pipe size and flow rate, thus reduced the pump size and energy required. Reduce make up water of Cooling Tower by way of water filter instead of bleed-off 7. Reduce solar heat gain through glass by way of using Frit, a small circular pad, spread evenly on glass which help reduce the Solar Factor MJTA Consortium
9
CONCEPTUAL DESIGN FOR ENERGY SAVING OF SUVARNABHUMI AIR CONDITIONING SYSTEM พลังงาน
8. Reduce infrared radiation from ceiling and wall by way of applying Low-E Infrared Hard Coating on ceiling and wall. Reduce convective heat gain from electrical lamps since the heat gain will be combined with hot air above stratification level which will cause no effect to passengers. Reduce radiation heat gain by way of using radiant floor cooling together with conventional air conditioning system. MJTA Consortium
10
Air Conditioning System
MJTA Consortium
11
Radiant Floor Cooling Cooling tube to Diffuser Header Diffuser
Poly Etelene 1 header=10 loops Diffuser MJTA Consortium
12
SUVARNABHUMI INTERNATIONAL AIRPORT.
Radiant Floor Shop Drawing: Configuration Detail Drawing. 12 MJTA Consortium
13
SUVARNABHUMI INTERNATIONAL AIRPORT.
Radiant Floor Shop Drawing: Floor Plan 13 MJTA Consortium
14
SUVARNABHUMI INTERNATIONAL AIRPORT.
VAC System. Temperature Layer 14 MJTA Consortium
15
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria Ambient Temp. 35C db 28C wb Indoor Temp. 24C±1 db Relative Humidity 55+5% RH Lighting: Circulation, Holdroom 10 W/m2 Office 15 W/m2 Retail 35 W/m2 MJTA Consortium
16
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria Outside Air: Circulation, Holdroom 17 m3/hr/person Office m3/hr/person Retail m3/hr/person Passengers: Terminal + Concourse 22,879 persons (30 MAP) (Peak Hour) ,379 persons (45 MAP) OA total ,011 m3/hr (30 MAP) 582,511 m3/hr (45 MAP) MJTA Consortium
17
SUVARNABHUMI AIR CONDITIONING SYSTEM
Design Criteria Total Cooling Capacity 41,666 KW = 11, Tons (30 MAP) 43,238 KW = 12, Tons (45 MAP) MJTA Consortium
18
SUVARNABHUMI AIR CONDITIONING SYSTEM
AOT purchase chilled water from DCAP (Districted Cooling System and Power Plant Company Limited). DCAP has installed 8 ABSORPTION CHILLERS at CENTRAL PLANT located within Parking building next to the Terminal building. DCAP installed 4 ABSORPTION CHILLERS ( DOUBLE EFFECT TYPE ) on each plant (EAST and WEST PLANT) and each absorption chiller has the capacity of 2,100 TR (norminal) and can produce 706 m3/hr ( L/S) chilled water at return temp. of 14 C and supply temp. of 5 C MJTA Consortium
19
SUVARNABHUMI AIR CONDITIONING SYSTEM
4 Absorption Chiller Cooling TR (7,386 kW) = 8,400 TR (29,544 kW) 4 Secondary chilled water 706 m3/hr ( L/S) = 2,824 m3/hr ( L/S) Supply Temp o C Return Temp o C TOTAL COOLING CAPACITY OF EAST AND WEST PLANTS = 16,800 TR (59,088 kW) MJTA Consortium
20
SBIA : TERMINAL COMPLEX
30 MILLION ANNUAL PASSENGER REDUCED CONCORSE WIDTH 4.35M AND REVISED MATERIAL OF CONSTRUCTION MJTA Consortium
21
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP
A) Heat Transmission + Electrical Load at Peak Hour East Concourse Building 7,464 kW. West Concourse Building 7,381 kW. Terminal Building 4,875 kW. Jetbridge East Concourse kW. Jetbridge West Concourse kW. Sub Total A) = 20,896 kW. MJTA Consortium
22
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d)
B) Occupancy and O.A Load B.1 Officers + Employees + Visitors + Meeters = 13,879 Persons Total Adjusted Heat Gain 130 W/Person; 13879 x 130/ = 1,804 kW. Total O.A Supply 353,011 Cubic Meter Per Hour Total O.A. Load = x 353,011/3.6 x (90-51)/1,000 = 4,551 kW. MJTA Consortium
23
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d)
B) Occupancy and O.A Load (Cont’d) B.2 TPHP of 30 Million Annual Flow as Recommended by FAA is Equivalent to 9,000 persons TPHP Load of Passenger = 9,000 x 130 / 1, = 1,170 kW. O.A. Load for TPHP = 1.19 x 9,000 x 17 / 3.6 x (90-51) / 1, = 1,972 kW. Sub Total B) = 9,497 kW. MJTA Consortium
24
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d)
C) Machine Room Cooling Load 6 sets AHU Capacity each 142 kW. = kW. Sub Total C) = kW. D) PCA. Chiller Heat Rejection PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 = 9,726 kW. Sub Total D) = 9,726 kW. E) Electrical Load Heat Dissipated from Transformers and LVSB = 695 kW. Sub Total E) = 695 kW. MJTA Consortium
25
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP (Cont’d)
Heat Transmission + Electrical Load at Peak Hour = 20,896 kW Occupancy and O.A Load = 9,497 kW Machine Room Cooling Load = kW PCA. Chiller Heat Rejection = 9,726 kW Electrical Load = kW Total Peak Hour Chiller Cooling Capacity = 41,666 kW MJTA Consortium
26
SBIA : TERMINAL COMPLEX
45 MILLION ANNUAL PASSENGER REDUCED CONCORSE WIDTH 4.35M AND REVISED MATERIAL OF CONSTRUCTION MJTA Consortium
27
WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP
A) Heat Transmission + Electrical Load at Peak Hour East Concourse Building 7,464 kW. West Concourse Building 7,381 kW. Terminal Building 4,875 kW. Jetbridge East Concourse kW. Jetbridge West Concourse kW. Sub Total A) = 20,896 kW. MJTA Consortium
28
WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d)
B) Occupancy and O.A Load B.1 Officers + Employees + Visitors + Meeters = 13,879 Persons Total Adjusted Heat Gain 130 W/Person; 13879 x 130/1000 = 1,804 kW. Total O.A Supply 353,011 Cubic Meter Per Hour Total O.A. Load = x 353,011/3.6 x (90-51)/1,000 = 4,551 kW. MJTA Consortium
29
WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d)
B) Occupancy and O.A Load (Cont’d) B.2 TPHP of 45 Million Annual Flow as Recommended by FAA is Equivalent to 13,500 persons TPHP Load of Passenger = 13,500 x 130 / 1,000 = 1,755 kW. O.A. Load for TPHP = 1.19 x 13,500 x 17 / 3.6 x (90-51) / 1, = 2,959 kW. Sub Total B) = 11,069 kW. MJTA Consortium
30
WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d)
C) Machine Room Cooling Load 6 sets AHU Capacity each 142 kW. = kW. Sub Total C) = kW. D) PCA. Chiller Heat Rejection PCA. Chiller Capacity each 350 Ton, 525 HP Motor, Max Heat Rejection is 1,621 kW. Per set, 6 sets x 1,621 = 9,726 kW. Sub Total D) = 9,726 kW. E) Electrical Load Heat Dissipated from Transformers and LVSB = 695 kW. Sub Total E) = 695 kW. MJTA Consortium
31
WATER SIDE PEAK COOLING LOADS SUMMARY 45 MAP (Cont’d)
Heat Transmission + Electrical Load at Peak Hour = 20,896 kW Occupancy and O.A Load = 11,069 kW Machine Room Cooling Load = kW PCA. Chiller Heat Rejection = 9,726 kW Electrical Load = kW Total Peak Hour Chiller Cooling Capacity = 43,238 kW MJTA Consortium
32
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP
MJTA Consortium
33
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP (Cont’d)
MJTA Consortium
34
WATER SIDE PEAK COOLING LOADS SUMMARY 30 MAP AND 45 MAP (Cont’d)
MJTA Consortium
35
CHILLED WATER PIPE COOLING CAPACITY
CHILLED WATER PIPE SCH. 40 COOLING CAPACITY BASED ON MJTA Consortium
36
CHILLED WATER PIPE COOLING CAPACITY
MJTA Consortium
37
District Cooling System and Power Plant (DCSPP)
for Suvarnabhumi International Airport . MJTA Consortium
38
District Cooling System and Power Plant (DCSPP)
By using natural gas as fuel to generate electricity and use excess heat to produce hot steam as a requirment for absorbtion chiller to produce chilled water for air conditioning purpose. This technology will increase efficiency in generating electricity and chilled water and will also reduce energy required. MJTA Consortium
39
Airport Electrical Power Distribution
MEA 115kV Back Up MTS DCAP Airport Main Transformer 115kV 6.9kV 24kV DCAP In-house use All Area in Airport MJTA Consortium
40
Chilled Water Distribution
Train Station??, Car Park 700RT Train Station 100RT MTB&Concourse 12,600RT AOB 1500RT AIM 200RT AIMS 700RT AOB 500RT Chilled Water Supply from DCAP to ….. DCAP Airport Hotel 700RT Total 19,000RT (29,860RT) Installed TG Catering Facility 5,000RT Airport Hotel 1,500RT MJTA Consortium
41
Steam Distribution 10barg/185C/8.6t/h DCAP TG Catering 8barg/175C/3t/h
Airport Hotel Airport Hotel MJTA Consortium
42
ตำแหน่งที่ตั้งของโครงการ
POWER PLANT CHILLER PLANT FOR CATERING CHILLER PLANT FOR PASSENGER TERMINAL MJTA Consortium
43
MJTA Consortium
44
Questions and Answers
45
Thank you for your attention
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.