Presentation is loading. Please wait.

Presentation is loading. Please wait.

Engineering Services New Delhi Engineering Services 17.01.07.

Similar presentations


Presentation on theme: "Engineering Services New Delhi Engineering Services 17.01.07."— Presentation transcript:

1 Engineering Services New Delhi Engineering Services

2 Presentation Sequence
Company Profile Engineering Services, ONGC Assets Created Typical Offshore Facilities Assets under Creation/Renewal Assets Creation – Under Tendering Asset Creation – Future Plan Contd . . Engineering Services

3 Company Profile MSP Engineering Services

4 ONGC’s Strategic Vision 2001-2020
To focus on core business of E&P Doubling reserves (i.e. accreting 6 billion tonnes of O+OEG) by 2020; out of this 4 billion tonnes are targeted from the Deep-waters. Improving average recovery from 28% to 40%. Equity Hydrocarbon from abroad. SH Engineering Services

5 Financial Status ( ) ONGC posted a net profit of Rs Crores, the Highest by any Indian Company. Practically zero debt Corporate. Contributed over Rs Crores to the exchequer. Highest ever Dividend of Rs Crores by any Indian Corporate. Engineering Services

6 Recognition in Last 12 Months
ONGC became the NO. 1 E&P Company in the World and 20th among leading Global Energy majors as per Platts Top 250. ONGC became the first Central Public Enterprise to receiver the designated national authority for its clean development mechanism under the Kyoto Protocol. ONGC was conferred the “Golden Peacock Award for Corporate Social Responsibility in Emerging Economics, 2006. Engineering Services

7 Recognition in Last 12 Months
ONGC secured the NDTV Profit Business Leadership Award in the Oil and Gas Category, handed over by the Hon’ble Prime Minister of India. ONGC was awarded the highest-ever Credit Rating for any Indian corporate by the International Credit Rating Agency Moody’s Investor Services. FY06 performance of ONGC has been rated ‘Excellent’ by the Department of Public Enterprises. ONGC has become the first PSU to get ISO Certification from DNV for Internal Audit. Engineering Services

8 Engineering Services ONGC Engineering Services

9 Engineering Services, ONGC
Engineering Services is responsible for creating facilities for exploitation & transportation of hydrocarbons. To meet the above objectives, Engineering Services undertakes following activities:- Engineering Construction Facility Renewal Marine Surveys MSP Engineering Services

10 Engineering Services, ONGC
Activities Works(ISO Certified) Tendering & Award of EPC Contract Contract Execution including Project Management Engg. & Construction related Surveys. Design(ISO Certified) Engineering Consultancy Facility Optimization Technological Upgradation Maintenance Management Engineering Services

11 Engineering Services, ONGC
Offshore Process Platforms Well Platforms Clamp-on structures on existing Platforms Submarine Pipelines (trunk line, in-field lines) Offshore Power Generation/Submarine cabling etc. Onshore GGS/GCS CTF ETP Mini Refineries Pipelines Power Generation BHS SA PF Engineering Services

12 Projects Execution Strategy
Major Works Centers of Engg. Services Western Region North Eastern Region Assets: Ahmedabad, Ankleshwar, Mehsana Projects Execution Strategy Assets: Assam, Tripura Mumbai Region Central Region Assets: Mumbai High, Bassein & Satellite, Neelam & Heera & Engineering Services Southern Region Assets: Karaikal, Rajamundary Engineering Services

13 Projects Execution Strategy
Major Works Centers of Engg. Services Western Region North Eastern Region Assets: Ahmedabad, Ankleshwar, Mehsana Projects Execution Strategy Assets: Assam, Tripura Mumbai Region Central Region Assets: Mumbai High, Bassein & Satellite, Neelam & Heera & Engineering Services Southern Region Assets: Karaikal, Rajamundary Engineering Services

14 Assets Created Engineering Services

15 Assets Created Western Offshore Process Platforms : 34
(upto pre-monsoon’06) Western Offshore Process Platforms : 34 Well Platforms : 146 Clamp-on : 66 Submarine P/L (Kms) : 4500+ Eastern Offshore Well Platforms : 4 Neelam Process Complex Contd . . Engineering Services

16 Growth of Process Platforms
Nos. IC Complex * For one year Engineering Services

17 Growth of Well Platforms
Nos. * For one year Engineering Services

18 Growth of Clamp on Structures
Nos. Engineering Services

19 Growth Of Pipelines Kms. * For one year Engineering Services

20 Typical Offshore Facilities
Engineering Services

21 Typical Well Platform Requirements
Structural Steel 2000 to 3000 tonnes Submarine Pipelines 15-20 Km (4” to 18”) WF/WI/GL Other Items Valves Vessels Batteries Line Pipes CP Systems Shutdown Systems Composite Materials Solar Power Systems Life Support Systems Personal Safety Systems Fire Detection & Protection Systems Electrical, Instrumentation & Fiber Optic Cables. Engineering Services

22 Typical Process Platform Requirements
Structural Steel to 5000 tonnes Line Pipe to 50 Km from interconnecting WF/WI/GL Cables (Elect. & Instt.) Km Other Items Pipes Valves Vessels DCS PLC UPS & Batteries HVAC Systems CP Systems HT Panels LT Panels Composite Material Pipeline Coatings CCTV Systems Paging & Intercoms Gas Turbine Generator Process Gas Compressor MOL Pumps & Water Injection Pumps Air Compressors Solar Power Systems Fire Detection & Protection Systems Produced Water Treatment Systems Life Support &Personal Safety System Electrical, Instt. & Fiber Optic Cables. Engineering Services

23 Assets Under Creation / Renewal
Engineering Services

24 Asset Under Creation Facilities Value : US$ 1844 M (Rs. 8378 Crores)
Process Platform : 2 (BCP-B2 & Vasai East ) Well Platforms : 16 (Heera Re-Development, C-Series, WPP-1 & 2) Submarine Pipelines : 267 Kms Value : US$ 1844 M (Rs Crores) Engineering Services

25 Asset Under Creation Sl. No. Project Description Value Completion 1
BCP-B2 Gas Compressor Platform US$ 283 M (Rs Crs.) 2. Vasai East Process-cum Booster Compressor Platform Well Platform US$ 456 M (Rs Crs.) 3. WPP-I US$ 239 M (Rs Crs.) 4. WPP-2 US$ 189 M (Rs. 866 Crs.) 5. C-Series Well Platforms US$ 388 M (Rs Crs.) 6. Heera Re-development Well Platforms & Pipelines US$ 289 M (Rs Crs.) Engineering Services

26 Asset Under Renewal Facilities Awarded Cost : US$ 639 M
Process Platform : 1 (SH-RC) Well Platforms : 26 Pipelines : 239 Kms Awarded Cost : US$ 639 M (Rs Crores) Engineering Services

27 Asset Under Renewal Sl. No. Project Description Value Completion 1.
26 Well Platforms Revamp of un-manned platforms in Mumbai High US$ 71 M (Rs. 330 Crs.) 2. SH Revamp Revamp of SHP Platform US$ 42 M (Rs Crs.) 3. PRP Replacement of Old Pipeline US$ M (Rs Crs.) Engineering Services

28 Asset Creation (Under Tendering)
Engineering Services

29 Project under Tendering
Facilities Process Platforms : 1 (New MHN) Clamp-on Project : 1 Pipeline : 24 Kms. (UTG) Estimated Cost : US$ 904 M (Rs Crores) Engineering Services

30 New MHN Process Platform
Process Platform having following facilities:- Oil Handling : BOPD Gas Handling : 6.8 MMSCMD Water Handling : BOPD Living Quarters : For 220 Persons Flare Jacket : Pipeline : 100 Kms Modification of Existing : 14 Nos. Platforms Estimated Cost : US$ 821 M (Rs Crores) Schedule Completion : April, 2010 Engineering Services

31 20” Gas Line between Uran & Trombay
Laying of 20” pipeline between Uran Plant and Trombay Terminals Total Length : 24 Kms Onshore Area – 8.1 Kms Offshore Area – 8.4 Kms Marshy Area – 7.5 Kms Estimated Cost : US$ 52.4 M (Rs. 235 Crores) Schedule Completion : Engineering Services

32 6 – Clamp-on Project Installation of Clamp-on Structure alongwith Modification works in Mumbai High Well Platforms. WA Platform WB Platform WI-6 Platform IN Platform IP Platform Estimated Cost : US$ 31 M (Rs Crores) Schedule Completion : Engineering Services

33 Asset Creation:Future Plans
Engineering Services

34 Future Business Plan Offshore Onshore Project - 11 Nos.
Indicative Cost - US$ 3986 M Onshore Project - 9 Nos. Indicative Cost - US$ 2284 M Engineering Services

35 Asset Creation Future Plans - Offshore
Sl. No. Project Description Indicative Cost Completion 1. B-22 Platforms Well-cum Process Platform, Well Platform, Pipelines & Modifi. US$ M (Rs Crs.) 2. B-193 Platform US$ 406M (Rs Crs.) 3. B-Series Gas (MH) Platform Well Platform & Pipeline US$ M (Rs Crs.) Engineering Services

36 Asset Creation Future Plans-Offshore
Sl. No Project Description Indicative Cost Completion 4. Grid Inter Connectivity Grid Inter connectivity of 26 Well Platforms with Process Platforms US$ M (Rs. 850 Crs.) 5. Conversion of Sagar Samrat Conversion of Sagar Samart to MOPU US$ 75 M (Rs Crs.) 6. Pipeline Replacement Project Rolling Plan for replacement of old pipelines US$ M (Rs Crs.) 7. Re-Re-Devlop plan of MH Process & Well Platforms in Mumbai High US$ M (Rs Crs.) Not yet firmed up Engineering Services

37 Future Revamp Projects:Offshore
Sl. No. Project Description Indicative Cost Completion 1. 30 PLF. Revamp Revamp of 30 well head platforms in MH & N and H US$ 85 M (Rs. 400 Crs.) 2. Revamp of WIN, WIS, ICW & SHW PLF. Revamp of Water Injection Platforms of Mumbai High US$ M (Rs Crs.) 3. Revamping Well-head of PLF. 3rd Phase of revamp of Well-head Platforms US$ 85 M 4. Revamp of Neelam & Heera Platforms Revamp of NLM,HRG & HRA Process Platforms and 13 Well Platforms US$ 320 M (Rs Crs.) Engineering Services

38 Future Business Potential : Onshore
Sl. No. Project Description Indicative Cost Completion 1. Assam Renewal Project Revamp of existing facilities in Assam Asset US$ M (Rs Crs.) 2. Western Onshore Renewal Revamp of existing facilities in Western onshore Asset US$ M (Rs Crs.) 3. Tripura Power Plant 1000MW Power Plant in Tripura US$ 870 M (Rs Crs.) - 4. GCS and Trunk Pipeline GCS and Trunk pipeline in Tripura Project US$ 40 M (Rs. 180 Crs.) 5. Refinery and new facilities Refinery and new facilities at Rajahmundry US$ M (Rs. 148 Crs.) Engineering Services

39 Future Business Potential : Onshore
Sl. No. Project Description Indicative Cost Completion 6. Cauvery Asset New Facilities at Karikal US$ 31 M (Rs. 145 Crores) 7. Ahmedabad Asset Construction of 3 GGS US$ 25 M (Rs.120 Crores) 8. Mehsana Asset Construction of 4 GGS and 1 ETP US$ 40 M (Rs. 185 Crores) 9. Ankelashwar Asset Construction of GGS, ETP, CPF etc. US$ 47 M (Rs. 225 Crores) Engineering Services

40 Expectation from the Industry
Competitive and Clean bids. All BEC requirements to be addressed. Proven Technology No deviations Functional specifications are given in ONGC Tender, ONGC expects bidders to use this flexibility to provide:- Cost effective solution Optimized Design New generation of equipment ONGC is following Three Tier Safety System during Offshore Construction, it expects all statutory SHE considerations/ requirements are followed during execution for Crew Vessel Equipment Procedure Engineering Services

41 Thank you Engineering Services


Download ppt "Engineering Services New Delhi Engineering Services 17.01.07."

Similar presentations


Ads by Google