Overview of a Private Sector review of Border Posts along the North/South Corridor Presented by: Mike Fitzmaurice.

Similar presentations


Presentation on theme: "Overview of a Private Sector review of Border Posts along the North/South Corridor Presented by: Mike Fitzmaurice."— Presentation transcript:

1 Overview of a Private Sector review of Border Posts along the North/South Corridor Presented by: Mike Fitzmaurice

2 Border Post Monitoring Projects Completed by TLC Border Post Monitoring Projects Completed by TLC Beitbridge – FESARTA/SSATP Pilot Project (Sep 2005 – Oct 2006) Chirundu – SSATP Pre – OSBP monitoring (Oct 2006 – Sep 2007) Beitbridge Situational Analysis – RTFP/SADC (Aug 2009) DOT Surveys – Beitbridge, Lebombo, Tlokweng & Skilpadshek (Sep/Oct 2009) JICA OD (Origin/Destination) Surveys (Nov 2009 – March 2010) - Beitbridge, Forbes/Machipanda, Zobue/Mwanza, Mchinji/Mwami, Kasumbelesa, Nakonde/Tunduma, Kazungula, Katima Mulilo, Osikango/Santa Clara & Trans Kalahari/Mamuno

3 Border Posts Surveyed on NSC Beitbridge – (South Africa/Zimbabwe) Chirundu – (Zambia/Zimbabwe) Kasumbelesa – (Zambia/DRC) Kazungula – (Zambia/Botswana) Nakonde/Tunduma – (Zambia/Tanzania)

4 Summary of Findings Transit Times (in hours):- Border PostNorthboundSouthbound Beitbridge4118 Chirundu3615 Kasumbelesa9373 Kazungula3025 Nakonde/Tunduma2892 *Figures courtesy TLC Surveys

5 Summary of Findings – continued... Commercial Traffic Volumes – ADT (average daily traffic):- Border PostNorthboundSouthbound Beitbridge Chirundu Kasumbelesa171 Kazungula110**110 Nakonde/Tunduma** * All figures courtesy of Revenue Authorities **Figures not available - estimated

6 Summary of Findings – continued... Border Post Statistics:- Border PostLoad Category Split by %Traffic Flow % Empty Returns % noon pmAfter 18:00 B/BCont.ConsolReferTank Beitbridge Chirundu*****50 21 Kasumbelesa Kazungula Nakonde/Tunduma * No figures available

7 Border Post Challenges Beitbridge – Infrastructure, lack of southbound parking, 24/7 border times under utilized and corruption. Chirundu – OSBP (System downtime), IT compatibility (Asycuda System), Staff competence on OSBP procedures. Kasumbelesa – Infrastructure, lack of or non existence of truck parks, delays in customs processing of documentation & corruption.

8 Border Post Challenges - continued... Kazungula – Ferry Downtime, Infrastructure inadequate for traffic volumes, inland clearance of goods (Livingstone) causes additional delays. Nakonde/Tunduma – Infrastructure inadequate for traffic volumes, Southbound clearances delays & 100% physical examination of containerized loads (exports/imports) is of concern.

9 Other Corridor Challenges The number of permanent and mobile police checkpoints on route. Zambia – 31 Zimbabwe – 15 DRC – 6 Total - 52 Average delay – 10 min per stop Total lost time – 520 min (8 hrs 30 min) or 1 day driving time This excludes the financial implication to the transporter in bribes when foreign operators are targeted.

10 Recommendations / Solutions Beitbridge – Open old bridge, increase southbound parking, fully utilize 24/7 operating hours, improve border post operating procedures to minimise corruption opportunities. Chirundu – Sort out system downtime, find an IT solution for interfacing the two Asycuda systems and improve staff training on OSBP system.

11 Recommendations / Solutions Kasumbelesa – Opening of new border post 11 km into DRC, move ZRA/Immigration to same facility & convert current border post into transit truck park & Clearing Agent facility. Kazungula – Building of new Kazungula bridge, open truck park facilities on both sides of the border. Nakonde/Tunduma – Opening of new OSBP (under construction), do away with 100% PEs of containerized cargo & improve border post operating efficiencies

12 General Comments Improving Trade Facilitation along a Corridor route is not just about improving border post efficiencies and should include all stakeholders/role players such as: Border Post Stakeholders (Customs, Immigration, Police, Road Fund Agencies etc.) Police (checkpoints) Roads Authorities (development agencies & weighbridge authorities)

13 THANK YOU!