June 20, 2013 CSSC Transportation Update. APG Traffic Counts Tuesday (2/26/13)Wednesday (2/27/13)Thursday (2/28/13) 6:00 – 7:00 AM143013331318 7:00 –

Similar presentations


Presentation on theme: "June 20, 2013 CSSC Transportation Update. APG Traffic Counts Tuesday (2/26/13)Wednesday (2/27/13)Thursday (2/28/13) 6:00 – 7:00 AM143013331318 7:00 –"— Presentation transcript:

1 June 20, 2013 CSSC Transportation Update

2 APG Traffic Counts Tuesday (2/26/13)Wednesday (2/27/13)Thursday (2/28/13) 6:00 – 7:00 AM :00 – 8:00 AM :00 – 9:00 AM Tuesday (2/26/13)Wednesday (2/27/13)Thursday (2/28/13) 6:00 – 7:00 AM :00 – 8:00 AM :00 – 9:00 AM Harford Gate (MD-22) Maryland Gate Gate (MD-715)

3 APG Traffic Counts Inside the Numbers –Harford Gate (MD-22) Average 5,386 vehicles 6 – 9 AM –Maryland Gate (MD-715) Average 3,316 vehicles 6 – 9 AM –Totals for APG North Average 8,702 vehicles 6 – 9 AM

4 APG Priority Intersections

5 APG-BRAC Intersections MD-715 / US Rt. 40 –Fully funded for all phases –Under construction –Under budget and ahead of schedule –Little concerns with traffic detour (excellent communication) –Ramp to open June / July 2013 –Intersection open for traffic Summer 2013

6 APG-BRAC Intersections US 40 / MD 7 / MD 159 –Two phase project Phase 1 (underway) = Two left turn lanes on Rt. 7 Phase 2 = Widening US 40 to allow two additional lanes in each direction / updating phase one to include two left turns, one shared through lane, and one channelized right –ROW $1.06 million (funded) –Utilities $4 million (funded) –Cost $11 - $13 million

7 APG-BRAC Intersections MD-22 / Old Post Road –Fully funded for all phases –100% design –Cost $7 - $10 million –Schedule Construction spring / summer 2013 Open to traffic spring 2015

8 APG-BRAC Intersections MD-22 / Paradise Road –Fully funded for all phases –99% design –ROW acquisition complete –Cost $9 - $12 million –Schedule ROW demolition underway Construction spring / summer 2015 Open to traffic spring 2017

9 APG-BRAC Intersections MD-22 / Beards Hill Road –Fully funded for all phases –75% design –Cost $9 - $12 million –Schedule Complete design 2013 Construction spring 2014 Open to traffic spring 2016

10 Rt. 22 Intersections All 3 intersections underway between summer 2013 and spring 2017 Road will remain open to traffic RT 22 Gate averages 5,386 vehicles per day

11 APG Gate Schedules During Furlough (July 8, 2013 – September 20, 2013) GateSunMonTuesWedThursFriSat Federal Holiday RT Hrs RT 22Closed 6AM – 6PM Closed AberdeenClosed GateSunMonTuesWedThursFriSat Federal Holiday RT 2424 Hrs Wise RdClosed 6AM – 6PM Closed MagnoliaClosed Aberdeen Area Edgewood Area

12 New E-ZPass two-axle toll rates (effective July 1, 2013) E-ZPass Maryland Hatem Memorial Bridge Plan: –$20.00 for unlimited trips annually E-ZPass Maryland Standard Plan Rates (10% discount off the cash rate): –$7.20 (round trip) - Hatem Bridge and JFK Highway (I-95 Bridge)

13 APG-CSSC Transportation Center Support APG TDM efforts Increase awareness of existing transit options Serve as communications center for transit Coordinate telework study Promote alternatives to SOV travel Collect data to support effort

14 Telework Study Examine APGs current telecommute policy and identify best practices among similar defense communities Offer recommendations that APG could adopt in support of telework and TDM efforts Awarded to Wells & Associates June 2013 –June 17, 2013: Study Kick-off with APG –November 2013: Final Recommendations delivered

15 APG-CSSC Transportation Center UPDATE 3 MONTH MILESTONES: –Interacted with over 200 people –Provided and implemented solution for installation shuttle termination –Added 4 new vanpools (24 Total) –27 new participants in the Army Mass Transportation Benefit program (March- April) –Participated in 8 events, including setting up in the lobby of JPEO-CBD –Published an article in the APG News and ARL newsletter UPCOMING PROJECTS: –APG Commuter Day, Ripkin Stadium, Ironbirds game, July 12 and August 23 –APG Vanpool Day, August 2013 –Location-specific commuter mixers –Continuation of news articles –Continue to grow participation