Presentation is loading. Please wait.

Presentation is loading. Please wait.

7 ERT 422/4 Piping and instrumentation diagram (P&id) MISS. RAHIMAH BINTI OTHMAN (

Similar presentations


Presentation on theme: "7 ERT 422/4 Piping and instrumentation diagram (P&id) MISS. RAHIMAH BINTI OTHMAN ("— Presentation transcript:

1 7 ERT 422/4 Piping and instrumentation diagram (P&id) MISS. RAHIMAH BINTI OTHMAN (

2 Which of the following statements are true? (a)Feedback and feedforward control both require measured variable. (b)The process variable to be controlled is measured in feedback control. (c)Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. (d)Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. (e)Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. Which of the following statements are true? (a)Feedback and feedforward control both require measured variable. (b)The process variable to be controlled is measured in feedback control. (c)Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. (d)Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. (e)Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. QUIZ1 False/True QUESTION 1:

3 QUIZ1

4 QUESTION 3: Figure below shows the boiler system that used to supply hot steam to a turbine. This system need to supply 100 psi hot steam to the turbine where the PCV-100 will be opened when the pressure reached that desired pressure. With using pressure control through temperature measurement in the boiler, draw a feedforward loop control system. BOILER Process variable need to be controlled = Pressure Water Hot steam PCV-100 PIPING AND INSTRUMENTATION DIAGRAM (P&ID)

5 Which of the following statements are true? (a)Feedback and feedforward control both require measured variable. (b)The process variable to be controlled is measured in feedback control. (c)Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. (d)Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. (e)Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. Which of the following statements are true? (a)Feedback and feedforward control both require measured variable. (b)The process variable to be controlled is measured in feedback control. (c)Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. (d)Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. (e)Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. QUIZ1 False/True QUESTION 1:

6 Answer 1: Batch distillation Reactor Distillate product tank Acid feed tank Ethanol-water mixture Cold water in Hot water out Ethanol liq. Ethyl acetate Condenser The Block Flow Diagram (BFD)

7 Answer 1 Figure below shows the boiler system that used to supply hot steam to a turbine. This system need to supply 100 psi hot steam to the turbine where the PCV-100 will be opened when the pressure reached that desired pressure. With using pressure control through temperature measurement in the boiler, draw a feedforward loop control system. BOILER TT Process variable need to be controlled = Pressure TIC Y Water Hot steam PI PIPING AND INSTRUMENTATION DIAGRAM (P&ID)


Download ppt "7 ERT 422/4 Piping and instrumentation diagram (P&id) MISS. RAHIMAH BINTI OTHMAN ("