Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cable selection project Factory office installation.

Similar presentations


Presentation on theme: "Cable selection project Factory office installation."— Presentation transcript:

1 Cable selection project Factory office installation

2 maximum demand sub- mains cable Each factory/warehouse consists of the following loads W mercury vapour lamps 4-60watt incandescent lamps 3-18watt fluorescent. External 1-500watt sodium vapour lamp. External 6-10A double single phase outlets 3-20A 3 phase outlets 1- 15A three phase storage hot water

3 Office Lighting 8-double 36 watt fluorescent lights Power 8- double10A single phase outlets 1- single 10A single phase outlet

4 Step 1 Divide the installation into circuits and distribute these circuits across the three phases Calculate the maximum demand of the installation The maximum demand of the sub- mains is the load on the heaviest loaded phase

5 Arrange into circuits Factory Circuit 1 (4-250W) lamps (R ) Circuit 2 (4-250W) lamps (W) Circuit 3 (4-60watt) + 2 EF 60W (B) Circuit 4 (3-18watt) F/lamps (W) Circuit 5 (1x500watt SV lamps) (B) Circuit 6 (2 double 10A) outlets (R) Circuit 7 (2 double 10A) outlets (W) Circuit 8 (2 double 10A) outlets (B) Circuit 9 (20A 3 phase) outlet Circuit 10 (20A 3 phase) outlet Circuit 11(20A 3 phase) outlet Circuit 12 (15A 3 phase) HWS Office Circuit13 (8 double36 watt fluorescent) (B) Circuit14 (3 double 10A outlets) (R) Circuit15 (3 double 10A outlets) (W) Circuit16 (2 double 1 single 10A outlet) (B)

6 MD Sub-mains using table C2 Circuit no Load group LoadcalculationRWB 1 A (4-250W)MV lamps 1.5A each4 x 1.5 = A (4-250W) MV lamps 1.5A each4 x 1.5 = A (4-18W) energy saver 0. 05A each 2x60w exhaust fans at 0.3A each A (3-18W) fluorescent 0.12A each A 1-500w sodium vapour lamps 0.8 pf B i 2-10A double 1Phase outlets = B i 2-10A double 1Phase outlets = B i 2-10A double 1Phase outlets = Factory

7 Circuit no Load group LoadcalculationRWB 9 B (iii)20A three phase outletFull load20 10 B (iii)20A three phase outlet75% Full load15 11 B (iii)20A three phase outlet75% Full load15 12 G15A three phase HWSFull load15 office 13 A8-twin 36w fluorescent B (i)3-10A double outlets single phase B (i)3-10A double outlets single phase B (i)2-10A double 1-10A single Outlets single phase 16.3 Maximum D Maximum demand Sub-mains

8 Cable size for sub-main to factory/warehouse unit1 The Maximum demand is 106A Mains Sub-mains X90 SDI Cables double insulated buried in separate U/G conduit Current carrying capacity T7/18 25mm² = 135A Voltage drop T41 Vc =1.62mV/Am So 25mm² X90 SDI Cables in separate conduits will satisfy both current and voltage drop requirements. Unit 1 has the longest run (38 metres) so 25mm² will satisfy units 2 and 3

9 Installation load The installation consists of the following loads. Lighting 24 – 250W mercury vapour Lamps 24 – 2x36W Fluorescent Luminaires 0.78A each 12 – 18W fluorescent to replace 60W 8 – 18W Fluorescent 6 – 60W exhaust fans 0.3A each 3 – 500W

10 Installation load Power 42 – double 10A single phase outlets 3 – single 10A single phase outlets 9 – 20A three phase outlets 3 – 3 phase HWS

11 Load Group loadCalculationRWB 24 – 250W mercury vapour Lamps (8 per phase) 8 x 1.5 = – 2x36W Fluorescent Luminaires (8 per phase) – 18W fluorescent (0.05A) to replace 60W 4 x 0.05 = – 60W exhaust fans (0.3A each) 2 x 0.3 = – 18W Fluorescent (0.12A) 3,3,2 per phase 0.12 x 3 = x 2 = – 500W Double +1 single 10A single outlets per phase (29 per phase) 87 outlets total – 20A three phase outlets x 15 = A 3phase HWS 3 x 15 = 4545 MD Consumers Mains maximum demand

12 Cable Size consumers mains The consumer mains are X90 SDI cables installed in conduit U/G for a length of 40 metres Determine the cable size to suit current and voltage drop requirements Table 2.4 item 2 refers to Table 7/16 150mm² = 330A The cable can carry the MD current Check for voltage drop. Table 41 Vc for 150mm² conductors = 0.309mV/Am (60ºC) The cable is rated at 90ºC and by choosing a Vc value at 60ºC this allows for temperature rise under Short circuit conditions

13 Progressive Voltage drop Turret MSB DB unit3 DB Unit 1 DB Unit 2 Consumers main Volt drop volts Sub-main voltage drop 6.52 volts Volts6.52 Volts 40 metres 38 metres 20 metres 10 metres

14 Progressive Voltage drop distribution board unit 1 Consumers mains Sub-main Final sub-circuits volts 3 phase Value 6.52 volts 3 phase value = volts 3 phase Therefore the 3 phase voltage drop allowed in all 3 phase circuits supplied from the DB Unit1 is 20 – = V To determine the single phase voltage allowed in final sub circuits Therefore the single phase Voltage drop allowed in all single phase circuits supplied from distribution board Unit 1 is 11.5 – 5.93 = 5.57 Volts 5.57 volts allowed in all single phase circuits Volts allowed in all 3 phase circuits

15

16 Circuit arrangements Cable Designation Maximum demand Installation ParametersAZ/NZS 3008/1/1 Table No column Consumers mains 302 AXLPE (X90) SDI enclosed UG Table 2.4 Table Sub-mains106 AX90 SDI enclosed U/GTable 2.4 Table x250W MV Lamp Factory 2 circuits 6ATPS V90 installed with 3 other circuits De rate 0.78 Table 2.1 Table 9 Table A outlets Factory 16ATPS V90 installed with 3 other circuits spaced De rate 0.87 item22 Table 2.1 Table 9 Table

17 Cable designation Maximum demand Installation parameters AS/NZS 3008 Table no Column no 3 phase outlets 20ATPS V90 installed with 2 other circuits On cable De rate 0.82 Table 2.1 Table 12 Table EF + Battens In Toilets 0.8ATPS unenclosed 3 other circuits on cable tray up wall from switchboard Table 2.1 Table 9 Table 24 De-rate HWS15TPS unenclosed 3 other circuits on cable tray up wall with 3 other circuits Table 2.1 Table 12 Table 24 De-rate W SV2.8ATPS installed enclosed U/G Table 2.4 Table

18 Cable Size 20A 3Ø outlets Distribution board Unit 1 MSB Unit 1 DB U/G turret Mains Sub-main 20A 3Ø outlet Determine the cable size for the 20A 3 phase outlets 1 per circuit, longest run 38 metres The cable is 3core TPS V 90 installed enclosed in air. No de-rating for this section. Unenclosed in air spaced on perforated tray up wall above switchboard 4 circuits To satisfy voltage drop requirements Table 42 a 4 mm² Cable with a Vc value of 9.71 mV/Am value is required

19 Cable Size 20A 3Ø outlets Distribution board Unit 1 MSB Unit 1 DB U/G turret Mains Sub-main 20A 3Ø outlet Determine the cable size for the 20A 3 phase outlets 1 per circuit, Route length 25 metres Current carrying capacity is the limiting factor in this circuit To satisfy Current carrying capacity, a 4mm² TPS cable is required

20 Cable Size 20A 3Ø outlets MSB Unit 1 DB U/G turret Mains Sub-main 20A 3Ø outlet Determine the cable size for the 20A 3 phase outlets 1 per circuit, Route length 15 metres In this instance Voltage drop is not the governing factor. A 4mm² cable is required for CCC

21 10A single phase outlets 6 outlets in warehouse 2 per phase, (3 circuits). Circuit 1 (38m route length) The outlet is at the end of the run therefore use MD =10A Therefore from Table 42, 4mm² cable is required for volt drop Cable enclosed in conduit on wall with 3 0ther circuits spaced ( 4 circuits ) Table 9/6 4mm² cable = 26A De-rating Table 22 (0.9) 26 x 0.87 = 23.4A

22 10A single phase socket outlets Circuit 2 (30m route length) Therefore from Table mm² with a Vc value of 15.6mV/A.m is required Circuit 3 route length 20m route length can also be wired in 2.5mm² Table 9 column 6 (2.5mm² cable)=20Ax0.9 =18A So a 2.5mm² cable will satisfy both CCC and Vd

23 Light Circuits unit 1 Circuit 1 (4x250W mercury vapour) Route length 38m Maximum Demand 4 x 1.5A = 6A. Circuit beaker rating 10A. Determine Cable size So from Table 42 a 2.5mm² cable with a Vc value of 15.6mV/A.m three phase 15.6 x =18mV/A.m is required

24 Light Circuits unit 1 Circuit 2 (4x250W mercury vapour) Route length 44m Maximum Demand 4 x 1.5A = 6A. See clause % of circuit protective device can be used Circuit beaker rating 10A. Determine Cable size So from Table 42 a 2.5mm² cable with a Vc value of 15.6mV/A.m three phase 15.6 x =18mV/A.m is required

25 Circuit 3 four battens and 2 EF Toilets Route length 28m So from Table mm² cable is required Table 9 column 6 (1.5mm² cable = 14A)

26 Circuit 4 (3x 18W) Fluorescent Route length 50m Voltage drop is not a factor for this circuit Either 1mm² or 1.5mm² can be used

27 Circuit 5 (500W) sodium Vapour Route length 16m TPS Cable V90 Installed enclosed U/G Distribution Board 500W Sodium vapour Voltage drop is not a factor for this circuit Either 1mm² or 1.5mm² can be used

28 Hot Water Cylinder 3 phase 15A Route length 28m Cable 3core + E enclosed TPS V90 Table 12 column 2 (2.5mm² = 23A) Check Voltage drop Table 41 (2.5mm² = 15.6mm²)Therefore 2.5mm² Cable

29 Office 8-2x36W(0.78A) fluorescent one circuit Route length 40m Use 10A MCB Rule % circuit protective device for voltage drop Table mm² = 28.6mV/Am. Use 1.5mm² cable

30 Office10A socket outlets Circuit 14 (three double outlets) Route length 22m TPS cable installed unenclosed in air Table 9 column 4 (2.5mm² = 26A)Use 20MCB Rule (50.% circuit protective device for voltage drop) Table mm² = 15.6mV/Am 2.5mm Cable for all socket outlet circuits in the office.

31 Fault loop impedance The earth fault-loop impedance in an MEN system comprises the following parts, starting and ending at the point of the fault. a) The protective earthing conductor, (PE), including the main earthing terminal/connection or bar and MEN. b) The neutral return path, consisting of the neutral conductor, (N), between the main neutral terminal or bar and the point at the transformer (the earth return path R G to R B has a relatively high resistance and may be ignored for an individual installation in an MEN system)

32 Fault loop impedance c) The path through the neutral point of the transformer and the transformer winding. d) The active conductors as far as the point of the fault. The earth fault-loop is normally regarded as consisting of the following two parts- i) conductors upstream or external to the reference point; and ii) conductors down stream or internal to the reference point. Refer to appendix B for detail

33 Path taken by an earth fault current

34 Earth fault-loop impedance Distributor's networkFault current I A Main Earth MEN Neutral Bar Faulty equipment Soil resistance high between electrodes A H POS

35 Determine maximum route length to satisfy fault loop impedance. The maximum length of a circuit can be determined using Table B1 (Exceptions include circuits wired in 4mm² cable protected by a 16A or 20A Type C MCB) The maximum length for this example will need to be calculated

36 Calculation 16A MCB A 4mm² Cable protected by a 16A MCB can be run 109m and not exceed the earth fault loop impedance requirements

37 Switchboards Units 1-3 LLL L L PP PPPPHW LP PP 120A Main switch MCBS

38 Main Switch Board


Download ppt "Cable selection project Factory office installation."

Similar presentations


Ads by Google