GENERAL INSPECTOR Practice Questions Next. General Inspector Practice Questions 1. a) Ditch excavation b) Toe trench excavation c) Borrow excavation d)

Similar presentations


Presentation on theme: "GENERAL INSPECTOR Practice Questions Next. General Inspector Practice Questions 1. a) Ditch excavation b) Toe trench excavation c) Borrow excavation d)"— Presentation transcript:

1 GENERAL INSPECTOR Practice Questions Next

2 General Inspector Practice Questions 1. a) Ditch excavation b) Toe trench excavation c) Borrow excavation d) General excavation The excavation of a roadside ditch in the roadway section (part of the typical roadway cross section) is paid for under which of the following excavation bid items?

3 General Inspector Practice Questions Next CORRECT! 1.The excavation of a roadside ditch in the roadway section (part of the typical roadway cross section) is paid for under which of the following excavation bid items?

4 General Inspector Practice Questions Next INCORRECT! The correct answer is D, General Excavation. The answer can be found in Section (d), Pg 94, 2008 Standard Specifications (Volume 2). 1.The excavation of a roadside ditch in the roadway section (part of the typical roadway cross section) is paid for under which of the following excavation bid items?

5 General Inspector Practice Questions a) 0°F b) 32°F c) 35°F d) 40°F 2.The Contractor should stop placement of Continuously Reinforced Concrete Pavement when the air temperature falls below ____________.

6 General Inspector Practice Questions Next CORRECT! 35°F 2.The Contractor should stop placement of Continuously Reinforced Concrete Pavement when the air temperature falls below ____________.

7 General Inspector Practice Questions INCORRECT! The correct answer is C, 35°F. The answer can be found in Section , Pg 501 of the 2008 Standard Specifications. Next 2.The Contractor should stop placement of Continuously Reinforced Concrete Pavement when the air temperature falls below ____________.

8 General Inspector Practice Questions a) True True b) False False 3.The Contractor will obtain and pay for permits required for crossing or encroaching upon navigable streams.

9 General Inspector Practice Questions Next CORRECT! 3.The Contractor will obtain and pay for permits required for crossing or encroaching upon navigable streams.

10 General Inspector Practice Questions INCORRECT The correct answer is False. The answer can be found in Section , Pg 62 of the 2008 Standard Specifications. Next 3.The Contractor will obtain and pay for permits required for crossing or encroaching upon navigable streams.

11 General Inspector Practice Questions a) 0 (there is no variance allowed) b) 1 c) ½ d) ¼ 4.When installing pipe materials, the Contractor cannot vary from the established line and grade by more than ______, provided the variation does not result in a level of reverse sloping invert (flowline).

12 General Inspector Practice Questions CORRECT! Next 4.When installing pipe materials, the Contractor cannot vary from the established line and grade by more than ______, provided the variation does not result in a level of reverse sloping invert (flowline). ½

13 General Inspector Practice Questions INCORRECT The correct answer is C, ½ inch. The answer can be found in Section (b), Pg 176 of the 2008 Standard Specifications. Next 4.When installing pipe materials, the Contractor cannot vary from the established line and grade by more than ______, provided the variation does not result in a level of reverse sloping invert (flowline).

14 General Inspector Practice Questions a) 6 b) 8 c) 10 d) half the total depth of the hole 5.When installing wood sign posts, the post holes should be backfilled in layers not exceeding ________.

15 General Inspector Practice Questions 5.When installing wood sign posts, the post holes should be backfilled in layers not exceeding ________. Next CORRECT! 6

16 General Inspector Practice Questions 5.When installing wood sign posts, the post holes should be backfilled in layers not exceeding ________. Next INCORRECT The correct answer is A, 6 inches. The answer can be found in Section , Pg 572 of the 2008 Standard Specifications.

17 General Inspector Practice Questions a) True True b) False False 6.The Contractor shall furnish all facilities necessary to permit the Engineer to have safe access to the work to be inspected.

18 General Inspector Practice Questions 6.The Contractor shall furnish all facilities necessary to permit the Engineer to have safe access to the work to be inspected. Next CORRECT!

19 General Inspector Practice Questions 6.The Contractor shall furnish all facilities necessary to permit the Engineer to have safe access to the work to be inspected. Next INCORRECT The correct answer is True. The answer can be found in Section (b), Pg 36 of the 2008 Standard Specifications.

20 General Inspector Practice Questions a) True True b) False False 7.When measuring painted temporary striping, the intervals between skip lines will be included in the measurement.

21 General Inspector Practice Questions 7.When measuring painted temporary striping, the intervals between skip lines will be included in the measurement. CORRECT! Next

22 General Inspector Practice Questions 7.When measuring painted temporary striping, the intervals between skip lines will be included in the measurement. INCORRECT The correct answer is False. The answer can be found in Section (c), Pg 33 of the 2008 Standard Specifications. Next

23 General Inspector Practice Questions a) True True b) False False 8.Bridge rail installation on the bridge end panels is incidental to the Reinforced Concrete Bridge End Panel bid item.

24 General Inspector Practice Questions 8.Bridge rail installation on the bridge end panels is incidental to the Reinforced Concrete Bridge End Panel bid item. CORRECT! Next

25 General Inspector Practice Questions 8.Bridge rail installation on the bridge end panels is incidental to the Reinforced Concrete Bridge End Panel bid item. INCORRECT The correct answer is False. The answer can be found in Section , Pg 280 and Section , Pg 344 of the 2008 Standard Specifications. Next

26 General Inspector Practice Questions a) True True b) False False 9.When applying asphalt tack coat, the bar height of the asphalt distributor should be set for double-lap coverage.

27 General Inspector Practice Questions 9.When applying asphalt tack coat, the bar height of the asphalt distributor should be set for double-lap coverage. CORRECT! Next

28 General Inspector Practice Questions 9.When applying asphalt tack coat, the bar height of the asphalt distributor should be set for double-lap coverage. INCORRECT The correct answer is False. The answer can be found in Section , Pg 439 of the 2008 Standard Specifications. Next

29 General Inspector Practice Questions a) 12 b) 18 c) 24 d) 300 mm 10.What is the minimum overlap requirement for geotextile used for embankment stabilization?

30 General Inspector Practice Questions 10.What is the minimum overlap requirement for geotextile used for embankment stabilization? CORRECT! Next

31 General Inspector Practice Questions 10.What is the minimum overlap requirement for geotextile used for embankment stabilization? INCORRECT The correct answer is C, 24 inches. The answer can be found in Section (a-2), Pg 110 of the 2008 Standard Specifications. Next

32 General Inspector Practice Questions a) True True b) False False 11.On a project that is Federally-funded, a Certificate of Materials Origin (CMO) is needed for a temporary impact attenuator.

33 General Inspector Practice Questions 11.On a project that is Federally-funded, a Certificate of Materials Origin (CMO) is needed for a temporary impact attenuator. CORRECT! Next

34 General Inspector Practice Questions 11.On a project that is Federally-funded, a Certificate of Materials Origin (CMO) is needed for a temporary impact attenuator. INCORRECT The correct answer is False. The answer can be found in the Non-Field Tested Materials Acceptance Guide, Pg 2. Next

35 General Inspector Practice Questions a) 95% of optimum moisture b) ± 4% c) ± 2% d) minus 4% to plus 2% 12.Moisture content at the time of compacting moisture-density testable embankment materials must be how close to optimum moisture content?

36 General Inspector Practice Questions 12.Moisture content at the time of compacting moisture-density testable embankment materials must be how close to optimum moisture content? CORRECT! Next

37 General Inspector Practice Questions 12.Moisture content at the time of compacting moisture-density testable embankment materials must be how close to optimum moisture content? INCORRECT The correct answer is D, minus 4% to plus 2%. The answer can be found in Section (b-2-a), Pg 88 of the 2008 Standard Specifications. Next

38 General Inspector Practice Questions a) True True b) False False 13.Payment for installing 8-foot guardrail posts instead of the normal 6-foot posts will be a cost per length bonus in addition to the regular payment.

39 General Inspector Practice Questions 13.Payment for installing 8-foot guardrail posts instead of the normal 6-foot posts will be a cost per length bonus in addition to the regular payment. CORRECT! Next

40 General Inspector Practice Questions 13.Payment for installing 8-foot guardrail posts instead of the normal 6-foot posts will be a cost per length bonus in addition to the regular payment. INCORRECT The correct answer is False. The answer can be found in Section , Pg 536 of the 2008 Standard Specifications. Next

41 General Inspector Practice Questions a) ½ to 1, measured from the top of the riser b) 1 to 1 ½, measured from the top of the riser c) ½ to 1, measured from the top of the sprinkler d) 1 to 1 ½, measured from the top of the sprinkler 14.How far above finished grade should sprinkler heads be positioned?

42 General Inspector Practice Questions 14.How far above finished grade should sprinkler heads be positioned? CORRECT! Next

43 General Inspector Practice Questions 14.How far above finished grade should sprinkler heads be positioned? INCORRECT The correct answer is C, ½ to 1, measured from the top of the sprinkler. The answer can be found in Section (a), Pg 682 of the 2008 Standard Specifications. Next

44 General Inspector Practice Questions a) Type 4 b) Type 3 c) Type 2 d) Type 1 15.What type of inlet protection involves installing biofilter bags?

45 General Inspector Practice Questions 15.What type of inlet protection involves installing biofilter bags? CORRECT! Next

46 General Inspector Practice Questions 15.What type of inlet protection involves installing biofilter bags? INCORRECT The correct answer is A, Type 4. The answer can be found in Section (d), Pg 55 of the 2008 Standard Specifications. Next

47 General Inspector Practice Questions a) 1 b) 2 c) 3 d) 4 16.What is the minimum number of inspections the Agency will make jointly with the Contractor during each plant establishment period?

48 General Inspector Practice Questions 16.What is the minimum number of inspections the Agency will make jointly with the Contractor during each plant establishment period? CORRECT! Next

49 General Inspector Practice Questions 16.What is the minimum number of inspections the Agency will make jointly with the Contractor during each plant establishment period? INCORRECT The correct answer is C, 3. The answer can be found in Section , Pg 657 of the 2008 Standard Specifications. Next

50 General Inspector Practice Questions a) True True b) False False 17.Approved Unstamped Drawings take precedence over the Standard Drawings.

51 General Inspector Practice Questions 17.Approved Unstamped Drawings take precedence over the Standard Drawings. CORRECT! Next

52 General Inspector Practice Questions 17.Approved Unstamped Drawings take precedence over the Standard Drawings. INCORRECT The correct answer is False. The answer can be found in Section (a), Pg 34 of the 2008 Standard Specifications. Next

53 General Inspector Practice Questions a) True True b) False False 18.The Agency will pay the Contractor to maintain the roadway surfacing in a detour if it is not constructed according to the Plans.

54 General Inspector Practice Questions 18.The Agency will pay the Contractor to maintain the roadway surfacing in a detour if it is not constructed according to the Plans. CORRECT! Next

55 General Inspector Practice Questions 18.The Agency will pay the Contractor to maintain the roadway surfacing in a detour if it is not constructed according to the Plans. INCORRECT The correct answer is False. The answer can be found in Section (a-1), Pg 8 of the 2008 Standard Specifications. Next

56 General Inspector Practice Questions a) The certificate must be delivered to the Engineers representative with the shipment of material, or be an identification plate or mark, decal, sticker, label or tag attached to the container or material. b) The certificate must certify that the material meets the contract requirements and identify the specific test methods used by number (ODOT, AASHTO, ASTM, UL or other). c) The certificate must permit positive determination that the material delivered to the project is the same material covered by the certificate. d) All of the above. 19.Which of the following statements about a Quality Compliance Certificate is true?

57 General Inspector Practice Questions 19.Which of the following statements about a Quality Compliance Certificate is true? CORRECT! Next

58 General Inspector Practice Questions 19.Which of the following statements about a Quality Compliance Certificate is true? INCORRECT The correct answer is D, all of the above. The answer can be found in the Non-Field Tested Materials Acceptance Guide, Pg 1 and Section (b), Pg 50 of the 2008 Standard Specifications. Next

59 General Inspector Practice Questions a) 1/8 pound b) 1/4 pound c) 1/2 pound d) 1 pound 20.What is the required application rate of granular fertilizer per tree per application?

60 General Inspector Practice Questions 20.What is the required application rate of granular fertilizer per tree per application? CORRECT! Next

61 General Inspector Practice Questions 20.What is the required application rate of granular fertilizer per tree per application? INCORRECT The correct answer is D, 1 pound. The answer can be found in Section , Pg 650 of the 2008 Standard Specifications. Next

62 General Inspector Practice Questions a) True True b) False False 21.During all construction activities, the Agency is required to retain the Erosion and Sediment Control Plan.

63 General Inspector Practice Questions 21.During all construction activities, the Agency is required to retain the Erosion and Sediment Control Plan. CORRECT! Next

64 General Inspector Practice Questions 21.During all construction activities, the Agency is required to retain the Erosion and Sediment Control Plan. INCORRECT The correct answer is False. The answer can be found in Section (c), Pg 43 of the 2008 Standard Specifications. Next

65 General Inspector Practice Questions a) Hanson Pipe and Products, Tualatin, Oregon b) Cascade Concrete Products, Scappoose, Oregon c) Central Oregon Redi-Mix, Redmond, Oregon d) Advantage Precast, Keizer, Oregon 22.Which of the following is NOT an approved supplier of concrete pipe?

66 General Inspector Practice Questions 22.Which of the following is NOT an approved supplier of concrete pipe? CORRECT! Next

67 General Inspector Practice Questions 22.Which of the following is NOT an approved supplier of concrete pipe? INCORRECT The correct answer is C, Central Oregon Redi-Mix. The answer can be found in the Non-Field Tested Materials Acceptance Guide, Pg 6. Next

68 General Inspector Practice Questions a) 7 days b) 5 days c) 3 days d) 1 day 23.How many counting days after a signal footing is poured can the Contractor erect the signal pole?

69 General Inspector Practice Questions 23.How many counting days after a signal footing is poured can the Contractor erect the signal pole? CORRECT! Next

70 General Inspector Practice Questions 23.How many counting days after a signal footing is poured can the Contractor erect the signal pole? INCORRECT The correct answer is A, 7 days. The answer can be found in Section , Pg 273 of the 2008 Standard Specifications, and Table Next

71 General Inspector Practice Questions a) True True b) False False 24.Conditionally Approved products from the QPL need specific, prior approval for each project they are used on.

72 General Inspector Practice Questions 24.Conditionally Approved products from the QPL need specific, prior approval for each project they are used on. CORRECT! Next

73 General Inspector Practice Questions 24.Conditionally Approved products from the QPL need specific, prior approval for each project they are used on. INCORRECT The correct answer is True. The answer can be found on the Qualified Products List Information Page. Next

74 General Inspector Practice Questions a) 5°C b) 40°F c) 50°F d) 60°F 25.What is the minimum surface temperature for placing a 2 lift of Open Graded HMAC?

75 General Inspector Practice Questions 25.What is the minimum surface temperature for placing a 2 lift of Open Graded HMAC? CORRECT! Next

76 General Inspector Practice Questions 25.What is the minimum surface temperature for placing a 2 lift of Open Graded HMAC? INCORRECT The correct answer is C, 50°F. The answer can be found in Section , Pg 477 of the 2008 Standard Specifications. Next

77 General Inspector Practice Questions a) Manual of Field Test Procedures b) Standard Specifications c) Supplemental Specifications d) Special Provisions 26.Which of the following documents takes precedence if there are conflicting references or if no reference is made in the Contract to material specifications or test methods?

78 General Inspector Practice Questions 26.Which of the following documents takes precedence if there are conflicting references or if no reference is made in the Contract to material specifications or test methods? CORRECT! Next

79 General Inspector Practice Questions 26.Which of the following documents takes precedence if there are conflicting references or if no reference is made in the Contract to material specifications or test methods? INCORRECT The correct answer is D, Special Provisions. The answer can be found in Section , Pg 49 of the 2008 Standard Specifications. Next

80 General Inspector Practice Questions a) BJ Super b) Opticom Model 752 c) Both A and B d) None of the above 27.Which of the following is an approved Traffic Signal Loop Sealant?

81 General Inspector Practice Questions 27.Which of the following is an approved Traffic Signal Loop Sealant? CORRECT! Next

82 General Inspector Practice Questions 27.Which of the following is an approved Traffic Signal Loop Sealant? INCORRECT The correct answer is A, BJ Super. The answer can be found in the Qualified Products List, Pg Next

83 General Inspector Practice Questions a) True True b) False False 28.The Project Superintendent of a project can be designated as the Traffic Control Supervisor.

84 General Inspector Practice Questions 28.The Project Superintendent of a project can be designated as the Traffic Control Supervisor. CORRECT! Next

85 General Inspector Practice Questions 28.The Project Superintendent of a project can be designated as the Traffic Control Supervisor. INCORRECT The correct answer is False. The answer can be found in Section , Pg 19 of the 2008 Standard Specifications. Next

86 General Inspector Practice Questions a) True True b) False False 29.When using the count method of measuring guardrail, the number of standard sections will be counted and multiplied by 12.5 feet.

87 General Inspector Practice Questions 29.When using the count method of measuring guardrail, the number of standard sections will be counted and multiplied by 12.5 feet. CORRECT! Next

88 General Inspector Practice Questions 29.When using the count method of measuring guardrail, the number of standard sections will be counted and multiplied by 12.5 feet. INCORRECT The correct answer is True. The answer can be found in Section , Pg 535 of the 2008 Standard Specifications. Next

89 General Inspector Practice Questions a) True True b) False False 30.Commercial Grade Concrete must be placed within 90 minutes of batching and mixing.

90 General Inspector Practice Questions 30.Commercial Grade Concrete must be placed within 90 minutes of batching and mixing. CORRECT! Next

91 General Inspector Practice Questions 30.Commercial Grade Concrete must be placed within 90 minutes of batching and mixing. INCORRECT The correct answer is True. The answer can be found in Section (b), Pg 171 of the 2008 Standard Specifications. Next

92 General Inspector Practice Questions a) True True b) False False 31.Spot alignment control points on tangent sections for Painted Permanent Pavement Striping shall be every 50 feet.

93 General Inspector Practice Questions 31.Spot alignment control points on tangent sections for Painted Permanent Pavement Striping shall be every 50 feet. CORRECT! Next

94 General Inspector Practice Questions 31.Spot alignment control points on tangent sections for Painted Permanent Pavement Striping shall be every 50 feet. INCORRECT The correct answer is True. The answer can be found in Section , Pg 554 of the 2008 Standard Specifications. Next

95 General Inspector Practice Questions a) True True b) False False 32.If more than 50 tons/day of material is received from a scale, the Contractor shall make random check weighings at least every 10 th day on which more than 50 tons is received, or when 10,000 tons has been weighed, whichever occurs first.

96 General Inspector Practice Questions 32.If more than 50 tons/day of material is received from a scale, the Contractor shall make random check weighings at least every 10 th day on which more than 50 tons is received, or when 10,000 tons has been weighed, whichever occurs first. CORRECT! Next

97 General Inspector Practice Questions 32.If more than 50 tons/day of material is received from a scale, the Contractor shall make random check weighings at least every 10 th day on which more than 50 tons is received, or when 10,000 tons has been weighed, whichever occurs first. INCORRECT The correct answer is True. The answer can be found in Section (f-1), Pg 101 of the 2008 Standard Specifications. Next

98 General Inspector Practice Questions a) 24 b) 18 c) 12 d) What is the minimum cover from finished surfaces for Rigid Nonmetallic conduit placed on roadways and shoulders?

99 General Inspector Practice Questions 33.What is the minimum cover from finished surfaces for Rigid Nonmetallic conduit placed on roadways and shoulders? CORRECT! Next

100 General Inspector Practice Questions 33.What is the minimum cover from finished surfaces for Rigid Nonmetallic conduit placed on roadways and shoulders? INCORRECT The correct answer is D, 30 inches. The answer can be found in Section (c), Pg 588 of the 2008 Standard Specifications. Next

101 General Inspector Practice Questions a) Place a watertight cap over the outlet end b) Place free draining cover material around the inlet end c) Remove ends of remaining pipe to at least 2 feet below subgrade d) All of the above 34.Which of the following should a Contractor do when an abandoned pipe is encountered?

102 General Inspector Practice Questions 34.Which of the following should a Contractor do when an abandoned pipe is encountered? CORRECT! Next

103 General Inspector Practice Questions 34.Which of the following should a Contractor do when an abandoned pipe is encountered? INCORRECT The correct answer is C, remove ends of remaining pipe to at least 2 feet below subgrade. The answer can be found in Section (a-7), Pg 82 of the 2008 Standard Specifications. Next

104 General Inspector Practice Questions a) 1% of the mobilization amount or 1% of the original contract amount, whichever is smaller b) 50% of the mobilization amount or 5% of the original contract amount, whichever is smaller c) 10% of the mobilization amount or 10% of the original contract amount, whichever is smaller d) There is no payment due at this time. 35. When 5% of the original contract amount is earned from other contract items, not including advances on materials, the contractor should be paid which of the following for mobilization?

105 General Inspector Practice Questions 35. When 5% of the original contract amount is earned from other contract items, not including advances on materials, the contractor should be paid which of the following for mobilization? CORRECT! Next

106 General Inspector Practice Questions 35. When 5% of the original contract amount is earned from other contract items, not including advances on materials, the contractor should be paid which of the following for mobilization? INCORRECT The correct answer is B. The answer can be found in Section , Pg 4 of the 2008 Standard Specifications. Next

107 General Inspector Practice Questions a) Capable of at least 2000 vibrations a minute b) Have a gross static weight of at least 6 tons c) Be tandem or multiple axle, multiple wheel type d) Both A and B 36.HMAC vibratory rollers (not used for finish rolling) shall be:

108 General Inspector Practice Questions 36.HMAC vibratory rollers (not used for finish rolling) shall be: CORRECT! Next

109 General Inspector Practice Questions 36.HMAC vibratory rollers (not used for finish rolling) shall be: INCORRECT The correct answer is A, capable of at least 2000 vibrations a minute. The answer can be found in Section (b), Pg 476 of the 2008 Standard Specifications. Next

110 General Inspector Practice Questions a) The ODOT Construction Manual b) Section of the ODOT Standard Specifications c) The Non-Field Tested Materials Acceptance Guide (NFTMAG) d) The Qualified Products List (QPL) 37.Where can a list of approved manufacturers of steel reinforcement for concrete can be found?

111 General Inspector Practice Questions 37.Where can a list of approved manufacturers of steel reinforcement for concrete can be found? CORRECT! Next

112 General Inspector Practice Questions 37.Where can a list of approved manufacturers of steel reinforcement for concrete can be found? INCORRECT The correct answer is D, the QPL. The answer can be found in the Qualified Products List, Pg Next

113 General Inspector Practice Questions a) Entire message is displayed within 7.5 seconds b) Using no more than two (2) displays within any message cycle c) Messages shall not scroll horizontally or vertically across the sign face d) Both A and C e) All of the above 38.Which of the following are requirements when the contractor is using a Portable Changeable Message Sign (PCMS)?

114 General Inspector Practice Questions 38.Which of the following are requirements when the contractor is using a Portable Changeable Message Sign (PCMS)? CORRECT! Next

115 General Inspector Practice Questions 38.Which of the following are requirements when the contractor is using a Portable Changeable Message Sign (PCMS)? INCORRECT The correct answer is D, both A and C. The answer can be found in Section (b), Pg 28 of the 2008 Standard Specifications. Next

116 General Inspector Practice Questions a) Inorganic fertilizer b) Inorganic fertilizer c) Low-phosphorus fertilizer d) None of the above 39.What type of fertilizer is required when it is used near water?

117 General Inspector Practice Questions 39.What type of fertilizer is required when it is used near water? CORRECT! Next

118 General Inspector Practice Questions 39.What type of fertilizer is required when it is used near water? INCORRECT The correct answer is C, low-phosphorus fertilizer The answer can be found in Section (b-3), Pg 626 of the 2008 Standard Specifications. Next

119 General Inspector Practice Questions a) Selected granular backfill b) HMAC c) Control low strength material d) Both A and B 40.What is the required material to use when backfilling a signal conduit trench in an existing roadway area?

120 General Inspector Practice Questions 40.What is the required material to use when backfilling a signal conduit trench in an existing roadway area? CORRECT! Next

121 General Inspector Practice Questions 40.What is the required material to use when backfilling a signal conduit trench in an existing roadway area? INCORRECT The correct answer is C, controlled low strength material. The answer can be found in Section (g-1-c-2), Pg 589 of the 2008 Standard Specifications. Next

122 General Inspector Practice Questions a) Quality Compliance Certificate b) Test Result Certificate c) Field Inspection Report d) Manufacturers Warranty e) All of the above 41.Which of the following Quality Compliance Documents are required for precast Concrete Barrier if supplied by an approved supplier?

123 General Inspector Practice Questions 41.Which of the following Quality Compliance Documents are required for precast Concrete Barrier if supplied by an approved supplier? CORRECT! Next

124 General Inspector Practice Questions 41.Which of the following Quality Compliance Documents are required for precast Concrete Barrier if supplied by an approved supplier? INCORRECT The correct answer is C, Field Inspection Report. The answer can be found in the Non-Field Tested Materials Acceptance Guide, Pg 21. Next

125 General Inspector Practice Questions a) 4 feet b) 6 feet c) 8 feet d) 2 feet 42.What is the required post spacing for supported sediment fence?

126 General Inspector Practice Questions 42.What is the required post spacing for supported sediment fence? CORRECT! Next

127 General Inspector Practice Questions 42.What is the required post spacing for supported sediment fence? INCORRECT The correct answer is A, 4 feet. The answer can be found in the Standard Drawings RD Next

128 General Inspector Practice Questions a) Standard Drawing RD100 b) Sheet 4 c) Sheet 3 d) Sheet 5 43.Which of the following sheets shows the locations of Bid Item 860?

129 General Inspector Practice Questions 43.Which of the following sheets shows the locations of Bid Item 860? CORRECT! Next

130 General Inspector Practice Questions 43.Which of the following sheets shows the locations of Bid Item 860? INCORRECT The correct answer is D, Sheet 5. Next

131 General Inspector Practice Questions 44.The 12 pipe extension on Sheet 4B is NOT required to have watertight joints. a) True True b) False False

132 General Inspector Practice Questions 44.The 12 pipe extension on Sheet 4B is NOT required to have watertight joints. CORRECT! Next

133 General Inspector Practice Questions 44.The 12 pipe extension on Sheet 4B is NOT required to have watertight joints. INCORRECT The correct answer is True. The answer can be found on Sheet 2C. Next

134 General Inspector Practice Questions a) 100 biofilter bags and 300 of straw wattles b) 12 check dams, 2 inlet protection and 1000 of sediment fence, supported c) 1 tire wash facility, 2000 of plastic sheeting and 0.75 acre of matting d) 12 check dams, 2 inlet protection and 1000 of sediment fence, unsupported 45.The required Erosion and Sediment Control Emergency Measures for the Project are:

135 General Inspector Practice Questions 45.The required Erosion and Sediment Control Emergency Measures for the Project are: CORRECT! Next

136 General Inspector Practice Questions 45.The required Erosion and Sediment Control Emergency Measures for the Project are: INCORRECT The correct answer is D. The answer can be found in the Section , Pg of the Special Provisions. Next

137 General Inspector Practice Questions 46.Items such as strain poles, terminal cabinets, pedestrian and vehicle signals become the property of the contractor upon removal. a) True True b) False False

138 General Inspector Practice Questions 46.Items such as strain poles, terminal cabinets, pedestrian and vehicle signals become the property of the contractor upon removal. CORRECT! Next

139 General Inspector Practice Questions 46.Items such as strain poles, terminal cabinets, pedestrian and vehicle signals become the property of the contractor upon removal. INCORRECT The correct answer is False. The answer can be found in the Section , Pg 50 of the Special Provisions. Next

140 General Inspector Practice Questions 47.The minimum required thickness of aggregate base material is 6 inches for sidewalk ramps and pedestrian landings. a) True True b) False False

141 General Inspector Practice Questions 47.The minimum required thickness of aggregate base material is 6 inches for sidewalk ramps and pedestrian landings. CORRECT! Next

142 General Inspector Practice Questions 47.The minimum required thickness of aggregate base material is 6 inches for sidewalk ramps and pedestrian landings. INCORRECT The correct answer is False. The answer can be found on Sheet 2B-5, Section A-A. Next

143 General Inspector Practice Questions a) Construction approach b) PCC monolithic curb and sidewalk c) Road connection d) This is a No Work zone 48.At station CL Lt., what is to be constructed?

144 General Inspector Practice Questions 48.At station CL Lt., what is to be constructed? CORRECT! Next

145 General Inspector Practice Questions 48.At station CL Lt., what is to be constructed? INCORRECT The correct answer is C, road connection. The answer can be found on Sheet 4. Next

146 General Inspector Practice Questions a) 2 inches b) 3 inches c) 4 inches d) There is only one lift of HMAC base course at this station 49.At station CL 28+00, the second lift of HMAC base course shall be what thickness?

147 General Inspector Practice Questions 49.At station CL 28+00, the second lift of HMAC base course shall be what thickness? CORRECT! Next

148 General Inspector Practice Questions 49.At station CL 28+00, the second lift of HMAC base course shall be what thickness? INCORRECT The correct answer is B, 3 inches. The answer can be found on Sheet 2A-2. Next

149 General Inspector Practice Questions a) 3, ¾ open graded b) 2, Level 3 ¾ open graded c) 2, ¾ open graded d) 2, ¾ dense graded 50.At station CN 91+90, what is the thickness and type of wearing course needed?

150 General Inspector Practice Questions 50.At station CN 91+90, what is the thickness and type of wearing course needed? CORRECT! Next

151 General Inspector Practice Questions 50.At station CN 91+90, what is the thickness and type of wearing course needed? INCORRECT The correct answer is B, 2 inches, Level 3 ¾ inch open graded The answer can be found on Sheet 2A- 3. Next

152 General Inspector Practice Questions a) Clamped to signal pole b) Mounted overhead on mast-arm c) Re-installed with existing hardware d) None of the above 51.How is sign #57 mounted?

153 General Inspector Practice Questions 51.How is sign #57 mounted? CORRECT! Next

154 General Inspector Practice Questions 51.How is sign #57 mounted? INCORRECT The correct answer is A, clamped to signal pole. The answer can be found on Sheet S Next

155 General Inspector Practice Questions a) 50 foot minimum for 2.3 acres of exposed soil b) 25 foot minimum radius c) 20 foot width over an existing 18 foot wide approach d) None of the above 52.Which of the following is NOT correct for a construction entrance?

156 General Inspector Practice Questions 52.Which of the following is NOT correct for a construction entrance? CORRECT! Next

157 General Inspector Practice Questions 52.Which of the following is NOT correct for a construction entrance? INCORRECT The correct answer is A, 50 foot minimum for 2.3 acres of exposed soil. The answer can be found in the Standard Drawings RD Next

158 General Inspector Practice Questions 53.The Agency Archaeologist for this project is Patrick OGrady. a) True True b) False False

159 General Inspector Practice Questions 53.The Agency Archaeologist for this project is Patrick OGrady. CORRECT! Next

160 General Inspector Practice Questions 53.The Agency Archaeologist for this project is Patrick OGrady. INCORRECT The correct answer is True. The answer can be found in the Section , Pg 20 of the Special Provisions. Next

161 General Inspector Practice Questions a) 6 tons b) 8 tons c) 10 tons d) 12 tons 54.According to Contract 13127, a steel-wheeled roller that is used for finish rolling of a Level 3 HMAC mix shall have a minimum static weight of _______.

162 General Inspector Practice Questions 54.According to Contract 13127, a steel-wheeled roller that is used for finish rolling of a Level 3 HMAC mix shall have a minimum static weight of _______. CORRECT! Next 8 tons

163 General Inspector Practice Questions 54.According to Contract 13127, a steel-wheeled roller that is used for finish rolling of a Level 3 HMAC mix shall have a minimum static weight of _______. INCORRECT The correct answer is B, 8 tons. The answer can be found in the Section (a), Pg 45 of the Special Provisions. Next

164 General Inspector Practice Questions a) ± 1/3 of specified thickness b) ± 1/3 of manufacturers recommendations c) ± 1/3 or – 1/10 of specified thickness d) None of the above 55.The placement tolerance for the thickness of lines for pavement markings are which of the following?

165 General Inspector Practice Questions 55.The placement tolerance for the thickness of lines for pavement markings are which of the following? CORRECT! Next

166 General Inspector Practice Questions 55.The placement tolerance for the thickness of lines for pavement markings are which of the following? INCORRECT The correct answer is C, ± 1/3 or -1/10 of specified thickness. The answer can be found in the Section , Pg 47 of the Special Provisions. Next

167 General Inspector Practice Questions Next